Amendment 0004 RFP 47PA0724R0004.pdf

PDF 228 KB Posted

Attached to
FY24 R7 TX Competitive Electric Supply
Solicitation number
47PA0724R0004
Issued by
Not on record

About this file

This document is Amendment 0004 to a Request for Proposals (RFP) for a federal contract opportunity. The amendment provides responses to questions received regarding the new Grid-Supplied Carbon Pollution-Free Electricity (CFE) requirements. Key details include:

The solicitation, numbered 47PA0724R0004, is for the supply of electricity and delivery of CFE energy attribute certificates for federal facilities in Texas. The contract will be a 48-month firm fixed-price award beginning June 2024. The estimated annual electricity quantity is 82,250,250 kWh, with the contractor required to deliver CFE energy attribute certificates equal to 75% of the total actual usage. The amendment clarifies that voluntary CFE is separate from and not included in the Grid-Supplied CFE requirements. It also explains that if there is no renewable portfolio standard or clean energy standard, the Grid-Supplied CFE is equal to the energy attribute certificates sourced from the agency's pro rata share of any electric utility distribution provider's non-bypassable charges for CFE.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PMPB

Mark West, Contracting Officer

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 0004 is hereby issued to provide responses to the Questions received as of 5:00 PM EDT on March 25th, 2024 for the new Grid-Supplied CFE requirements. All other terms and conditions remain unchanged.

[See the Description of Amendment 0004 Continuation Page]

PMPB

Carbon Pollution-Free Electricity/ Clean Energy Division 1800 F Street, NW Washington, DC 20405 USA

Carbon Pollution-Free Electricity/ Clean Energy Division 1800 F Street, NW Washington, DC 20405 USA

EQPMPB-24-0001

47PA0724R0004

1 3

3/27/2024

2/15/2024

INSTRUCTIONS (Back Page):

Instructions for items other than those that are self-explanatory, are as follows:

Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.

Item 3 (Effective date).

(1)

(2)

(3)

(4)

(5)

For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.

For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.

For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.

For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.

For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.

(a)

(b)

(c)

(d)

(e)

(f)

Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.

Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.

Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.

Item 12 (Accounting and Appropriation Data).

When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:

(2) Accounting classification Net decrease $

Include subject matter or short title of solicitation/contract where feasible.

Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.

(i)

NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".

Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)

Item 14 (Description of Amendment/Modification).

Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.

Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:

(i) Total contract price increased by $

(ii) Total contract price decreased by $

(iii) Total contract price unchanged.

State reason for modification.

When removing, reinstating, or adding funds, identify the contract items and accounting classifications.

(g)

(h)

When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --

(i) A reference to the letter determination; and

(ii) A statement of the net amount determined to be due in settlement of the contract.

(1)

(2)

(3)

(4)

(5)

(6)

STANDARD FORM 30 (REV. 11/2016) BACK

(1) Accounting classification Net increase $

Descrip�on of Amendment 0004 Con�nua�on Page ….. Page 3

47PA0724R0004 GSA ERCOT COMPETITIVE ELECTRICITY BUY

Addi�onal Ques�ons and Answers received as of Monday, March 25, 2024

Q1: Sec on A.12 states that “The electricity supplier shall track each MWh of delivered CFE in the supplier’s grid mix using EACs and deliver or re re those EACs on behalf of the customer base, including the Federal customer.” There are two types of re rements that are performed by retail suppliers: (1) re rements associated with TX state RPS mandates and (2) voluntary EACs acquired on behalf of the customer. Accordingly, is the “Grid-Supplied CFE” to be reported as part of this solicita on the sum of the TX state RPS mandate plus the 75% voluntary EAC requirement?

A1: Reference Sec�on A.11. Voluntary CFE is separate from and not included in Grid-Supplied

CFE.

Q2: When the current TX RPS mandate sunsets a�er August 2025, is the “Grid-Supplied CFE” simply equal to the 75% voluntary EAC requirement?

A2: If there is no renewable por�olio standard or clean energy standard, then the Grid-Supplied CFE is equal to the EACs sourced from the agency’s pro rata share of any electric u�lity distribu�on provider’s non-bypassable charges for CFE (e.g., a state program suppor�ng exis�ng nuclear power). “Non-bypassable” refers to a tariff charge that may not be avoided by the tariff customer.

Q3: Also, Sec on A.12 (ii) makes reference to “any electric u lity distribu on provider’s non-bypassable charges for CFE”. Is there anything specific in ERCOT that is being referenced here?

A3: The language cited is general/universal and does not reference specific charges. It applies to any charges in ERCOT mee�ng the defini�on provided in the contract.

Q4: If any non-bypassable charge were to exist, a compe ve supplier would not deliver or re re such a ributes?

A4: Per Sec�on A.12, the "electricity supplier shall track each MWh of delivered CFE in the supplier’s grid mix using EACs and deliver or re�re those EACs on behalf of the customer base". If the electricity supplier is not tracking CFE sourced from the agency’s pro rata share of the electric u�lity distribu�on provider’s non-bypassable charges for CFE using EACs and delivering or re�ring those EACs on behalf of the customer base, then that CFE is not "grid-supplied CFE".