472-25139-ABG Kinross PA System - Addendum 1.pdf
PDF 80 KB Posted
- Solicitation number
- RFP-171-250000001703-4
- Issued by
- Chippewa County, Michigan
About this file
This document is an Addendum No. 1 to a Request for Proposal (RFP) issued by the Michigan Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division for the Kinross Correctional Facility Public Address (PA) Upgrades project. The project file number is 472/25139.ABG, and the proposal was originally due on Thursday, May 22, 2025, though this is subject to change. The key update in this addendum is the cancellation of the site walkthrough that was originally scheduled for Monday, March 31, 2025 at 1:30 PM due to weather conditions. The project director, Alan Goschka, indicates that a future date for the site walkthrough will be determined and reposted on the SIGMA Vendor VSS system.
Proposers are advised to check SIGMA for future updates, specifically Addendum 2, which may provide additional details or modifications to the proposal due date. No specific pricing, funding sources, or detailed project scope are included in this addendum. The document serves primarily as a communication vehicle to inform potential bidders about the changes to the original RFP timeline and site visit arrangements for the public address system upgrades at the Kinross Correctional Facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 RFP (Rev 2/22)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
REQUEST FOR PROPOSAL
ADDENDUM NO. 1
This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.
Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.
TO:
ALL PROPOSERS
DATE ISSUED
03-31-2025
PROJECT NAME
Kinross Correctional Facility – Public Address (PA) Upgrades
FILE NUMBER
472/25139.ABG
PROJECT DIRECTOR
Alan Goschka
PROPOSAL DUE DATE:
Thursday, May 22, 2025 – subject to change
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
Due to weather conditions the site walkthrough scheduled for Monday, March 31, 2025 at 1:30PM is
CANCELLED.
A future date will be determined for the site walkthrough and will be reposted to SIGMA.
The Proposal Due Date is tentatively scheduled for May 22, 2025, but will be subject to change, so please check back into SIGMA for a future Addendum 2.
APPROVED BY:
Alan Goschka
PROJECT DIRECTOR DATE 03-31-2025