This document is a Bid Addendum issued by the Department of Technology, Management and Budget (DTMB), State Facilities Administration, Design and Construction Division for a project to replace an exterior door and provide related mechanical and electrical work at the existing Housing Unit 1 Library area at the Baraga Correctional Facility in Baraga, Michigan. The project includes removing a portion of an existing masonry and brick wall, installing a new exterior door, frame and hardware with a concrete stoop, as well as providing mechanical and electrical controls for a new fin-tube radiator and enclosure, and security lighting. The bid opening date is September 18, 2024 at 2:00 pm local time. A mandatory pre-bid conference and site tour will be held on September 4, 2024. The contract completion date is May 30, 2025.
The bid must include unit prices and an overall base bid amount. Bidders must provide the required bid security, bonds, and certifications. The contract will be awarded to the responsive and responsible best value bidder, with a 10% pricing preference provided for qualified disabled veteran-owned businesses that meet the requirements. The pricing, qualifications, and past performance of the three lowest responsive bidders will be evaluated to determine the best value.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bidding and Contract Document (R 5/19) Project Name: Proposed HU-1 Yard Door File No. 472/19344.TAP
DTMB-0401D (R 05/19)
BID SUMMARY
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
STATE FACILITIES ADMINISTRATION
DESIGN AND CONSTRUCTION DIVISION
3111 W. St. Joseph Street Lansing, Michigan 48917
Bids must be submitted electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService
FILE NUMBER
472/19344.TAP
FUNDING CODE
19AMF14
DEPARTMENT/AGENCY
DOC/Baraga Correctional
CONTRACT TIME(S)
May 30, 2025 Substantial
PROJECT NAME
Proposed Housing Unit 1 Yard Door
LOCATION
Baraga, MI
BID OPENING DATE
September 18, 2024 at 2:00 pm Local Time
FOR AN EXAMINATION OF THE SITE CONTACT:
Wes Pietila 906-353-7070
SEE SECTION 00100 INSTRUCTIONS TO BIDDERS AND SECTION 00700 GENERAL CONDITIONS PROVIDED WITH THE BIDDING DOCUMENTS.
BID: WE PROPOSE TO FURNISH, PERFORM AND COMPLETE THE ENTIRE WORK IN ACCORDANCE WITH THE CONTRACT DOCUMENTS
IN CONSIDERATION OF THE BID PRICE (S) STATED BELOW.
FIRM NAME AND COMPLETE ADDRESS TELEPHONE NUMBER and E-MAIL ADDRESS
□ Qualified Disabled Veteran
FEDERAL I.D. NUMBER (LAST 4 ONLY)
(protected information required for processing payments)
BIDDER'S SIGNATURE AND TITLE DATE WITNESS' SIGNATURE DATE
By signing this bid above, bidder certifies their enclosed Qualified Disabled Veteran and Michigan-Based Business Certifications.
BASE BID FROM BID SCHEDULE (Include specified Allowances):
____________________________________________________________________________Dollars $____________________ (use words) (in figures)
Alternate1: (Add/Subtract) ______________________________________________________ Dollars $ ____________________ (use words) (in figures)
Alternate 2: (Add/Subtract) ______________________________________________________Dollars $ ____________________ (use words) (in figures)
Alternate 3: (Add/Subtract) ______________________________________________________Dollars $ ____________________ (use words) (in figures)
Builders Risk Insurance is NOT provided by the State of Michigan.
A PERFORMANCE BOND AND A PAYMENT BOND ARE REQUIRED FOR ALL BIDS OVER $50,000.00. EACH BID MUST BE
ACCOMPANIED BY A FIVE (5) PERCENT BID GUARANTEE.
BIDDERS ARE ALSO CAUTIONED TO FAMILIARIZE THEMSELVES WITH ALL OF THE OTHER CONDITIONS OF THE CONTRACT.
Project Scope of Work:
Remove a portion of an existing masonry and brick wall to provide a new exterior door, frame & hardware with concrete stoop at the existing Housing Unit 1 Library area. Provide mechanical and electrical controls for a new fin-tube radiator and enclosure. Provide security lighting.
The Bidder must figure its Base Bid on the specified, or Addendum-approved, materials and equipment only. No “or equal” or substitution proposals will be permitted after Bid opening, except as provided in the General Conditions.
Addenda: Bidder acknowledges receipt of Addenda: No. ___ dated: ________, No. ___ dated: ________ No. ___ dated:
Reid Anderson Arrow
Reid Anderson Arrow
Bidding and Contract Document (R 5/19) Project Name: Proposed HU-1 Yard Door File No. 472/19344.TAP
FIRM NAME TELEPHONE NUMBER and E-MAIL ADDRESS
BID SCHEDULE
Base Bid Schedule - The Bidder will complete the Work and accept as full payment, for the Work items listed, the following Unit Prices and/or Item Bid Prices, as applicable:
Base Bid Item No.
Bid Quantity
Description (Bidder to write price in Words)
Unit Price
Item Bid Price
1 1 Mobilization 2 1 Demolition 3 1 Proposed Install Breakdown 4 1 Electrical 5 1 Mechanical / Plumbing 6 1 Fire Alarm Contractor
OWNER DIRETED ALLOWANCE 5,000 5,000
TOTAL (This amount should equal the Base Bid amount on the Bid Summary Form) $
Base Bid (Sum of Item Bid Prices for all Base Bid Items):
__________________________________________________________________ Dollars $__________________________ (use words) (in figures)
Bidding and Contract Document (5/19) Project Name: Proposed HU-1 Yard Door File No. 472/19344.TAP
00-1
SECTION 00010 PRE-BID INFORMATION
1. Invitation to Bid (ITB) Your firm is invited to submit a Bid. The State of Michigan as the Owner will receive bids electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService, for Baraga Correctional Replacement of Ex. Doors & Windows until 2:00 p.m., local time, on February 5, 2020_. The State reserves the right to cancel this Invitation to Bid (ITB) or change the date and time for submitting Bids by announcing same at any time before the established date and time for Bid opening. Bids must remain open for acceptance by the Owner for no less than the Bid hold period. Contractor may agree to extend the Bid hold period. However, any such extension must be based upon no increase in the Bid Price and/or Contract Time.
2. Work Description The Work, Baraga Correctional Facility, Proposed Housing Unit 1 Yard Door, Baraga, Michigan, Agency No. 472, Funding Code. 19AMF14, DTMB File No. 472/19344.TAP includes, but is not necessarily limited to:
Remove portion of existing masonry and brick wall to provide a new exterior door, frame & hardware with concrete stoop at the existing Housing Unit 1 Library area. Provide mechanical & electrical controls for new fin-tube radiator and enclosure.
Provide security lighting. The site is located at: 13924 Wadaga Road, Baraga, MI 49908, as shown on the Drawings.
3. Bidding Documents Sets of Bidding Documents may be obtained at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService .
4. Bid Security Each Bid must enclose Bid Security, in the amount of five percent (5%) of the Bidder's Base Bid, paid to the “State of Michigan” in the form of a certified or cashier’s check or money order drawn upon a bank insured by an agency of the Federal Government or a bid bond with an authorized surety company. If Bid Security is by check or money order, such certified or cashier’s check or money order must be delivered in original copy before the Bid Due Time to:
State Facilities Administration Design & Construction Division
3111 W. St. Joseph Street Lansing, Michigan 48917
All other Bid information must be submitted via SIGMA as per standard bidding procedure
5. Pre-Bid Conference A mandatory X pre-bid conference will be held at 13924 Wadaga Road Baraga, MI on September 4, 2024 at __9:00 am______ Local Time. A tour of the work items will X be held on the same day, starting at __9:30 am__ local time. All prospective Bidders are required X to attend the tour. Other parties interested in the Work are encouraged to attend the tour. Addenda may be issued, in response to issues raised at the pre-bid conference and tour, or as the Owner and/or Professional may otherwise consider necessary.
The purpose of the pre-bid conference and inspection is to answer questions and provide an inspection tour of the Project site at the scheduled time on the day of the meeting. A representative will be available to assist the Contractors. Other inspection visits may be allowed if needed. Individuals needing special services to fully participate in the meeting due to a disability may contact Reid Anderson - UPEA at randerson@upea.com.
FOR CORRECTIONAL FACILITIES ONLY: All contractor/vendor representatives attending a Pre-Bid Walk Through Meeting must submit a Vender/Contractor LEIN Request five business days prior to the meeting date, (Lein Request For CAJ-1037 attached to Bid posting). Send the LEIN Request form, filled out and signed, by email to Daniel T. Smith at email address:
SmithD76@michigan.gov. The email “Subject” must include (Facility Name, Project Name, Date & Time of Pre-Bid Walk Through Meeting).
6. Equal Employment Opportunity Covenants to not discriminate in employment by Contractors, Subcontractors and Suppliers required by Law are contained in Instructions to Bidders and General Conditions and are applicable to the Work and any Sub-agreement under the Contract.
7. Contract Times The Contract Times and the associated liquidated damages are specified in the Contract.
8. Contact Person All requests or inquiries concerning the Bidding Documents or the Work must be addressed to: Reid Anderson U.P. Engineers & Architects, randerson@upea.com (906)-315-1303. Questions will be accepted until August 19, 2024 at 4:00 pm Local Time.
9. Award Subject to any agreed extension of the period for holding Bids, Bids must remain valid for acceptance by the Owner for 60 Calendar Days after the date of Bid opening. In addition, the Owner expressly reserves the right, within the Owner's sole discretion, to reject any or all Bids, to waive any irregularities, to issue post-Bid Addenda and re-bid the Work without re-advertising, to re-advertise for Bids, to withhold the award for any reason the Owner determines and/or to take any other appropriate action.
10. Performance and Payment Bonds – A performance bond and a payment bond are required for all contracts over $50,000.00.
END OF SECTION 00010
00-2
SECTION 00100 INSTRUCTIONS TO BIDDERS
1. PREPARATION OF BID: Execute Bid fully and properly. Bid Summary Form (DTMB -0401D) and Bid Form Attachments must be used and completely filled out for the Bid to be considered responsive and meeting the requirements of the contract solicitation. All Bid prices must be printed or typed in both words and figures.
2. BID CHECKLIST: Submit Bid Summary Form with original signatures plus Bid Form Attachments in accordance with the electronic bidding procedures on the SIGMA VSS website.
A complete Bid will consist of the following forms, which are included immediately following the Bid Summary Form:
Bids SUBMIT THESE Bid Forms and Bid Form Attachments All Bids □ Signed and completed Bid Summary Form (DTMB-0401D);
□ Bid Schedule;
□ Qualified Disabled Veteran (QDV) Business Representation;
□ Bid Security in the amount of 5% of Base Bid Price;
If Bid Security is by check or money order, such certified or cashier’s check or money order must be delivered in original copy before the Bid Due Time to:
State Facilities Administration Design & Construction Division
3111 W. St. Joseph Street Lansing, Michigan 48917
All other Bid information must be submitted via SIGMA as per standard bidding procedure
□ Signature Authorization or copy of the partnership agreement if signed by all partners;
□ Other Forms;
Over $50K □ Forms listed under All Bids;
□ Payment and Performance Bond (upon issuing the Notice of Award).
Over $100K □ Forms listed under All Bids;
□ Certification of a Michigan Based Business;
□ Payment and Performance Bond (upon issuing the Notice of Award).
Over $250K □ Forms listed under All Bids;
□ Certification of a Michigan Based Business;
□ Payment and Performance Bond (upon issuing the Notice of Award).
Apparent Low Bidders ONLY (upon request from the Professional)
□ Experience Modification Rating (EMR), or a letter stating why the Bidder does not have one.
□ Identification of the proposed project superintendent, with a resume or list of similar projects handled by that individual.
□ A list of at least three (3) projects completed by the Bidder, within the last three (3) years of similar size and complexity, with contact information for references for each.
□ A list of nominated sub-contractors, including proposed self-performed categories, for each Division/Trade/etc.
3. BID SUBMISSION: Bids must be submitted electronically through the SIGMA VSS website at https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService.
4. BID GUARANTEE: Each proposal must be accompanied by either a bank certified or cashier's check on an open, solvent bank or a bid bond with an authorized surety company (the surety must be listed on the current U.S. Department of the Treasury Circular 570) in the amount of five percent of the base bid payable to the State of Michigan, as a guarantee of good faith. If the successful Bidder fails to furnish satisfactory bonds and insurance within fifteen Calendar Days after Notice of Award, such guarantee must be forfeited to the State as liquidated damages. If Bid Security is by check or money order, such certified or cashier’s check or money order must be delivered in original copy before the Bid Due Time to the Issuing Office. The bid
00-3 security, exclusive of bid bonds, of all unsuccessful Bidders will be returned when an award is made or upon substitution of a bid bond. The bid security of the successful Bidder will be returned when the performance bond and labor and material bond are approved.
5. CERTIFICATE OF AWARDABILITY: Not required.
6. MICHIGAN BASED BUSINESS CERTIFICATION: All Bidders submitting Bids in excess of $100,000.00 must complete the Certification of Michigan Based Business. This information will determine if a Bidder qualifies as a "Michigan" business for purposes of application of reciprocity where applicable.
7. POST-BID SUBMITTAL: For all projects, the Professional may request a Post-Bid Submittal from the Apparent Low Bidders. The Apparent Low Bidders must submit to the Professional, within two Business Days after receipt of the Professional’s request, Experience Modification Rating (EMR), or a letter stating why the Bidder does not have one.
Identification of the proposed project superintendent with a resume or list of similar projects managed by that individual.
A list of at least three (3) projects completed by the Bidder, within the last three (3) years of similar size and complexity, with contact information for references for each.
Failure to provide the submittals may disqualify the Bid.
8. SIGNATURES: All Bids, notifications, claims, and statements must be signed as follows:
(a) Corporations: Signature of official must be accompanied by a certified copy of the Resolution of the Board of Directors authorizing the individual signing to bind the corporation.
(b) Partnerships: Signature of one partner must be accompanied by a signed copy of the legal document (e.g. Power of Attorney or partnering agreement) authorizing the individual signing to bind all partners. If Bid is signed by all partners, no authorization is required.
(c) Individual: No authorization is needed. Each signature must be witnessed.
9. BID PRICES: The Bidder’s Base Bid and Alternate Bid prices must include, and payment for completed Work will compensate in full for: all services, obligations, responsibilities, management, supervision, labor, materials, devices, equipment, construction equipment, general conditions, permits, patent fees and royalties, testing, inspection and approval responsibilities, warranties, temporary facilities, small tools, supplies, Bonds, insurance, taxes, mobilization, close-out, overhead and profit and all connections, appurtenances and any other incidental items of any kind or nature, as are necessary to complete the Work, in a neat, first quality, workmanlike and satisfactory manner in accordance with the Drawings and Specifications and as otherwise required to fulfill the requirements of the Bidding Documents. For each Cash Allowance item, the Bidder must include, within the Bid, all labor costs, construction equipment costs, insurance and Bond premiums and other general conditions costs and Fees (Bidder’s and Subcontractors’) to complete Work associated with the material, equipment or other designated item to be furnished under the Cash Allowance. For each Provisionary Allowance, the Bidder must include, within the Bid, insurance, premiums (not recoverable as labor burden) and Bond premiums required to complete Work that may be ordered under a Provisionary Allowance.
10. INSPECTION OF BIDDING DOCUMENTS AND SITE CONDITIONS: The Bidder must carefully review and inspect all documents referenced and made part of this ITB, site conditions, all applicable statutes, regulations, ordinances and resolutions addressing or relating to the goods and services under this contract. Failure to do so or failure to acquire clarifications and answers to any discovered conflicts, ambiguities, errors or omissions in the Bidding Documents will be at the Bidder’s sole risk.
11. SAFETY REQUIREMENTS AND LAWS: The Bidder awarded the Contract must comply with all applicable federal, state and local Laws including health and safety regulations, environmental protection, permits and licensing.
12. INTERPRETATIONS AND ALTERATIONS TO THE BID AND BIDDING DOCUMENTS: All requests for clarification or interpretation of the Bidding Documents, all proposals for any modifications to the Bidding Documents, all requests for information and all other questions or inquiries about the Bidding Documents and/or the Work shall be submitted in writing to the Contact Person identified in the Bid Documents. Requests or inquiries received less than seven Calendar Days before the date of Bid opening will be answered only if (a) the response can be given through an Addendum made available at least seventy-two hours before Bid opening (counting Business Days only), (b) the Bid opening is postponed by Addendum, or (c) the Work is rebid without readvertising following the issuance of post-Bid Addenda.
Bidders must not rely upon any oral statements or conversations regarding interpretations, clarifications, corrections, additions, deletions or other revisions or information to the Bidding Documents. Any addition, limitation or provision made with or attached to the Bid may render it non-responsive and/or irregular and be a cause for rejection. The Owner reserves the right to issue a post-Bid Addendum after opening the Bids and set a new date for the receipt and opening of sealed Bids. The Bidder acknowledges that any quantities of Unit Price Work given in this ITB are approximate only and payments will be made only for actual quantities of Unit Price Work completed in accordance with the Contract Documents.
00-4
13. MODIFICATION OF BID: The entire bid must be resubmitted on the SIGMA VSS website.
14. BID WITHDRAWAL: Except for timely filed claims of mathematical or clerical errors granted by the State, no Bid may be withdrawn within sixty Calendar Days after the Bid Opening time and date or before the Bid expiration date without forfeiting Bid security. The request to withdraw a Bid due to error must be submitted in writing along with the supporting documents within two Business Days after the date of Bid Opening. The claim must describe in detail the error(s), include a signed affidavit stating the facts of the alleged error(s) and request that the Bidder be released from its Bid. The review of the claim and its supporting documents by the State is only for the purpose of evaluating the Bidder’s request and must not create duty or liability on the State to discover any other Bid error or mistake. The sole liability of any Bid error or mistake rests with Bidder.
15. OBJECTION TO THE AWARD: A Bidder may file a written protest with the Director-SFA to object to the Apparent Low Bidder. This objection must be filed within seven Calendar Days after the date of Bid opening and must describe in detail the basis for the protest and request a determination. The Director-SFA will either dismiss or uphold the protest and notify the protestor within ten Calendar Days after receipt of the written protest.
16. BID IRREGULARITIES: The following irregularities on any Bid Form or Bid Form Attachment must be resolved as follows:
(a) between SIGMA entry and signed Bid Summary attachment, the signed Bid Summary attachment will be used;
(b) between words and figures, the words must be used;
(c) between any sum, computed by the Bidder, and the correct sum, the sum computed by the Bidder must be used;
(d) between the product, computed by the Bidder, of any quantity and Bid Unit Price and the correct product of the Unit Price and the quantity of Unit Price Work, the product extended by the Bidder must be used;
(e) between a stipulated Allowance and the amount entered, the Allowance must be used;
(f) any mobilization pay item exceeding the maximum specified must be ignored and the Bid must remain unchanged;
(g) if any Bidder fails or neglects to bid a Unit Price for an item of Unit Price Work but shows an "Bid Price" for that item, the missing unit price must be computed from the respective quantity and the Item Bid Price shown;
(h) if any Bidder fails or neglects to show a "Bid Price" for an item of Unit Price Work but bids a unit price, the missing Bid
Price must remain as “zero”; and
(i) if any Bidder fails or neglects to enter a Bid Price in both words and figures, the Bid Price printed or typed, whether in words or figures, must be used.
17. CERTIFICATION: The bidder certifies to the best of its knowledge and belief that, within the past three (3) years, the bidder, an officer of the bidder, or an owner of a 25% or greater interest in the bidder:
(a) Has not been convicted of a criminal offense incident to the application for or performance of a contract or subcontract with the State of Michigan or any of its agencies, authorities, boards, commissions, or departments.
(b) Has not had a felony conviction in any state (including the State of Michigan).
(c) Has not been convicted of a criminal offense which negatively reflects on the bidder’s business integrity, including but not limited to, embezzlement, theft, forgery, bribery, falsification or destruction of records, receiving stolen property, negligent misrepresentation, price-fixing, bid-rigging, or a violation of state or federal anti-trust statutes.
(d) Has not had a loss or suspension of a license or the right to do business or practice a profession, the loss or suspension of which indicates dishonesty, a lack of integrity, or a failure or refusal to perform in accordance with the ethical standards of the business or profession in question.
(e) Has not been terminated for cause by the Owner.
(f) Has not failed to pay any federal, state, or local taxes.
(g) Has not failed to comply with all requirements for foreign corporations.
(h) Has not been debarred from participation in the bid process pursuant to Section 264 of 1984 PA 431, as amended, MCL
18.1264, or debarred or suspended from consideration for award of contracts by any other State or any federal Agency.
(i) Has not been convicted of a criminal offense or other violation of other state or federal law, as determined by a court of competent jurisdiction or an administrative proceeding, that in the opinion of DTMB indicates that the bidder is unable to perform responsibly or which reflects a lack of integrity that could negatively impact or reflect upon the State of Michigan, including but not limited to, any of the following offenses under or violations of:
1. The Natural Resources and Environmental Protection Act, 1994 PA 451, MCL 324.101 to 324.90106.
2. A persistent and knowing violation of the Michigan Consumer Protection Act, 1976 PA 331, MCL 445.901 to
445.922.
3. A finding that the bidder failed to pay the wages and/or fringe benefits due within the time period, as may be required by applicable law.
4. Repeated or flagrant violations of 1978 PA 390 MCL 408.471 to 408.490 (law relating to payment of wages and fringe benefits).
5. A willful or persistent violation of the Michigan Occupational Health and Safety Act, 1974, PA 154, MCL
408.10001 to 408.1094, including: a criminal conviction, repeated willful violations that are final orders, repeated violations that are final orders, and failure to abate notices that are final orders.
6. A violation of federal or state civil rights, equal rights, or non-discrimination laws, rules, or regulations.
7. Been found in contempt of court by a Federal Court of Appeals for failure to correct an unfair labor practice as prohibited by Section 8 of Chapter 372 of the National Labor Relations Act, 29 U. s. C. 158 (1980 PA 278, as amended, MCL 423.321 et seq).
(j) Is not an Iran-Linked Business as defined in MCL 129.312.
00-5
A false statement, misrepresentation or concealment of material facts on this certification may be grounds for rejection of this proposal or termination of the award and may be grounds for debarment.
18. REJECTION OF BID: The Bidder acknowledges the right of the Owner to reject any Bids and to waive any informality, defects or irregularity in any Bid received. In addition, the Bidder recognizes the right of the Owner to reject a Bid if:
(a) the Bid is in any way incomplete or irregular;
(b) the Bidder, Subcontractor or Supplier is not responsible as determined by the Owner;
(c) the Bidder’s performance as a Contractor was unsatisfactory under a prior Contract with the Owner for the construction, repair, modification or demolition of a facility with the Owner, or under any other Contract, which was funded, directly or indirectly, by the Owner;
(d) there are reasonable grounds for believing that collusion or unlawful agreements exists between any Bidders, that a Bidder is interested in more than one Bid, or that the Bid is not genuine;
(e) the Bid exceeds the funds available.
19. MATERIALS AND EQUIPMENT SUBSTITUTION: Any Bidder wishing to use manufacturers or materials other than those specified must submit a written request to the Professional not later than seven days before due date for Bids. Request must be accompanied by product data to permit evaluation and comparison with specified products or materials. The Person submitting the request will be responsible for its prompt delivery. The Professional and the Owner will examine and evaluate the product data and if found acceptable, an Addendum will be issued and mailed or delivered to each Person who has received a set of Drawings and Specifications. All Addenda issued must be made a part of the Contract requirements. Contractor will be responsible for any extra work and expense incurred to satisfactorily and completely incorporating each substitute product into the Project.
20. MICHIGAN PRODUCTS AND RECYCLED PRODUCTS: All Contractors and Suppliers are encouraged to provide Michigan-made products and/or recycled products and/or green products and/or environmentally-friendly products whenever possible where price, quality, and performance are equal to, or superior to, non-Michigan products and the requirements of the Contract Documents. The Contractor will be required to use alternatives to landfills for waste disposal such as reuse or recycle of asphalt, bricks, concrete, masonry, plastics, paint, glass, carpet, metals, wood, drywall, insulation and any other waste materials to the extent practical.
21. PRE-AWARD PRODUCT SUBMITTALS: If requested, the Apparent Low Bidders must submit a summary of preliminary technical data on each product listed in technical spec section. The Apparent Low Bidders will furnish this summary data to the Professional within forty-eight hours of the Bid Opening. These submittals will be used to evaluate the Bid before the award. Failure to provide the submittals may disqualify the Bid.
22. CONTRACT AND CONTRACT AWARD: The Owner intends to award a Contract to the responsive and responsible best value bidder, except as provided below relative to veteran’s preference.
22.1 Determination of the lowest three Bidders shall be on the basis of the sum of the Base Bid and any additive and deductive Alternates the Owner accepts, in the order in which they are listed only. The Owner will accept an Alternate only if all other previously listed Alternates are also accepted, unless acceptance by the Owner of Alternates in a different order does not affect determination of the lowest three bidders in any way.
22.2 The bids will be evaluated for best value based on price and qualitative components by comparing the qualitative components of the three lowest responsive and responsible Bidders. The comparison may also include other Bidders whose bids are within 10% of the lowest responsive and responsible Bidder.
22.3 If a Qualified Disabled Veteran meets the requirements of the contract solicitation, provides acceptable responses to both Part One and Part Two of the Best Value Construction Bidder Evaluation to achieve a Best Value recommendation and with the veteran’s preference is the lowest responsive, responsible, best value Bidder, the Owner will award the contract to the Qualified Disabled Veteran bidder. A determination as to whether the requirements of the bid solicitation have been met will be based solely on the Owner’s and Professional’s evaluation of the Bid Summary, Bid Attachments, Bidder-provided documents, and interview.
22.4 For the purpose of evaluating and determining the low responsive bid, 10% of the lowest responsive bid (the bid that would otherwise receive the contract award if the preference were not being considered) will be deducted from all QDV bids. If the low responsive QDV bid, less the 10% preference, is less than the lowest responsive bid, then the QDV bid will be declared the official low responsive bid. The original QDV bid amount will be the basis of the contract award.
00-6
Example:
Lowest Responsive Bid $100,000 Lowest Responsive QDV Bid $109,000 Preference (10% of the Lowest Responsive Bid) $ 10,000 Lowest Responsive QDV Bid Less Preference $ 99,000 ($109,000 - $10,000) Official Low Responsive Bid $109,000
22.5 The Apparent Low Bidders will be evaluated for responsiveness and responsibility based on the following:
Compliance with the bid specifications and requirements.
The Bidder’s financial resources.
The Bidder’s technical capabilities.
The Bidder’s technical experience.
The Bidder’s past performance.
The Bidder’s insurance and bonding capacity.
The Bidder’s business integrity.
Some qualitative components that may be evaluated are:
Technical approach.
Quality of proposed personnel.
Management plans.
22.6 For contracts under $250,000, best value will primarily be based on the lowest responsive and responsible bid.
23. CONTRACT TIME; LIQUIDATED DAMAGES: Work of all trades as specified in the Contract Documents must be completed by May 30, 2025 based on except for minor replacement, correction, or adjustment items which do not interfere with the complete operation and utilization of all parts of the Contract Work. This Contract Time is of the essence and liquidated damages for each Calendar Day that expires after this Substantial Completion of the entire Work must be in the amount of $300.00. Liquidated damages are not a penalty, are cumulative and represent a reasonable estimate of the Owner’s extra costs and damages, which are difficult to estimate with accuracy in advance.
24. MOBILIZATION: If used in the Specifications/Bid schedule, all the up-front costs incurred by the Contractor must be covered by the mobilization. The costs to establish temporary site offices, to obtain required permits for commencing the Work and for bonds and insurance premiums are examples of costs to the Contractor that are covered by mobilization pay item. This cost must not exceed four percent (4%) of the Base Bid, unless otherwise expressly provided in the Bidding Documents.
25. SOIL EROSION AND SEDIMENTATION CONTROL: All Work under this Contract must meet the storm water management requirements of the Project and comply with the applicable Soil Erosion and Sedimentation Control (SESC) rules and regulations and specific provisions for same within the Contract Documents. SESC measures will be monitored and enforced by the State Facilities Administration, or another authorized enforcing agency if so delegated, through the review of the Contractor’s implementation plans and site inspections. State Facilities Administration or the Professional will notify the Contractor in writing of any violation(s) of the applicable SESC statutes and/or the corrective action(s) undertaken by the Owner and may issue stop work orders. State Facilities Administration has the right to assess a fine to the Contractor for noncompliance with the provisions of the Contract Documents and/or SESC regulations applicable to this Work and fines must be in addition to any other remediation costs or liquidated damages applicable to the Project and may exceed the value of the Contract.
END OF SECTION 00100
SECTION 00120 SUPPLEMENTARY INSTRUCTIONS
The provisions of this Section amend or supplement Section 00100 Instructions to Bidders and those other provisions of the Bidding Requirements that are indicated below. All other Bidding Requirements that are not so amended or supplemented remain in full force and effect.
END OF SECTION 00120
01-9
4. Samples: The Contractor must deliver all samples of material or equipment to the job site for examination by the State Agency and the Professional. Samples will be examined by the Professional for conformance with the design concept of the Project and for compliance with the information given in the Contract Documents. The Contractor must furnish all Work in accordance with approved samples. The following general classifications of material and equipment require submission of samples.
Samples of other items may be requested by the Professional at any time.
Item of Work Type of Sample Section Number Frame Color Samples 081313 Door Color Samples 081214 Hardware Color Samples 087100 Painting and Coating Color Samples 099000 Fin-Tube Enclosure Color Samples 238200
END OF SECTION 01300
SECTION 01400 QUALITY CONTROL
1. Testing Laboratory Services: All tests required by the Owner must fulfill ASTM, ANSI, Commercial and other Standards for testing. The Contractor must submit a minimum of three copies of each test report to the Professional for evaluation and subsequent distribution. The following general classifications of Work require submission of test reports and/or certificates of inspection. Additional submissions may be requested by the Professional at any time.
Item of Work Test Type Section Number `N/A
2. Tests:
(a) Paid by Owner: N/A
(b) Paid by Contractor: Compaction Density & Moisture Testing.
3. Concrete/Asphalt Materials: Before placement of any concrete, the Contractor must submit for the Professional's approval complete data on the trial concrete mix formulation and a testing laboratory report for ASTM C94, twenty-eight-day standard cylinder test for compressive strength of a sample of the concrete mix. For asphalt paving, the Contractor must submit the data and testing reports for ASTM D946, AC-5. The mix must have 4.5 to 6 percent of asphalt cement by weight for binder course and 5 to 7 percent of asphalt cement by weight for surface course in accordance with Asphalt Institute Manual MS-4, MS-13 and the current Michigan Department of Transportation (MDOT) Standard Specifications for Construction.
(a) The Contractor must furnish to the Professional tickets showing mix formulation, Contractor's name, Project name, mix identification for each load of concrete/asphalt delivered and installed. If the technical specifications allow added water to the concrete mix after leaving the batch plant, the delivery ticket must reflect the added water. The Owner Field Representative must receive a copy of each delivery ticket for transmittal to the Professional for evaluation.
(b) The Professional may require the Contractor to core drill questionable cast-in-place concrete/asphalt for laboratory testing. Should the laboratory analysis indicate the concrete/asphalt fails to meet specification requirements, the Contractor must pay all costs for core drilling and testing in the laboratory and replace the concrete/asphalt found to fail meeting the specification requirements. Should the laboratory analysis confirm that the concrete/asphalt meets specification requirements, the Owner will pay the Contractor for their costs for core drilling, concrete/asphalt patching and the laboratory fee for testing of the concrete/asphalt core samples.
END OF SECTION 01400
SECTION 01500 CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS
1. The Contractor must furnish and install all temporary facilities and controls required by the Work, must remove them from State property upon completion of the Work, and the grounds and existing facilities must be restored to their original condition.
2. If water or electricity is available in the area where Work will be performed, the Contractor will not be charged for reasonable use of these services for construction operation. The Contractor must pay costs for installation and removal of any temporary connections including necessary safety devices and controls. Use of services must not disrupt or interfere with operations of the State Agency.
[M12-19562]
Fill 31 23 23 - 1
SECTION 31 23 23
FILL
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes:
1. Backfilling site structures to subgrade elevations.
2. Fill for over-excavation.
B. Related Sections:
1. Section 03 30 00 - Cast-in-Place Concrete.
2. Section 31 05 13 - Soils for Earthwork.
3. Section 31 05 16 - Aggregates for Earthwork.
4. Section 31 22 13 - Rough Grading.
5. Section 31 23 16 - Excavation.
1.2 REFERENCES
A. American Association of State Highway and Transportation Officials:
1. AASHTO T180 - Standard Specification for Moisture-Density Relations of Soils
Using a 4.54-kg (10-lb) Rammer and a 457-mm (18-in.) Drop.
B. ASTM International:
1. ASTM D698 - Standard Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3)).
2. ASTM D1556 - Standard Test Method for Density and Unit Weight of Soil in
Place by the Sand-Cone Method.
3. ASTM D1557 - Standard Test Methods for Laboratory Compaction
Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3)).
4. ASTM D2922 - Standard Test Method for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth).
5. ASTM D3017 - Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth).
1.3 SUBMITTALS
A. Materials Source: Submit name of imported fill materials suppliers. Aggregate supplier shall provide current test results of materials supplied verifying that supplied products meet product requirements.
31 23 23 - 2
PART 2 PRODUCTS
2.1 FILL MATERIALS
A. Per the 2012 MDOT Standard Specifications for Construction or as listed on the drawings.
PART 3 EXECUTION
3.1 EXAMINATION
A. Section 01040 – Coordination.
B. Verify that forms are removed and excavation is free of trash and debris.
C. Verify structural ability of unsupported walls to support loads imposed by fill.
3.2 PREPARATION
A. Compact subgrade to density requirements for subsequent backfill materials.
B. Cut out soft areas of subgrade not capable of compaction in place. Backfill with granular fill and compact to density equal to or greater than requirements for subsequent fill material.
C. Scarify subgrade surface to depth of 6 inches.
D. Proof roll to identify soft spots; fill and compact to density equal to or greater than requirements for subsequent fill material.
3.3 BACKFILLING
A. Backfill areas to contours and elevations with unfrozen materials.
B. Systematically backfill to allow maximum time for natural settlement. Do not backfill over porous, wet, frozen or spongy subgrade surfaces.
C. Place material in continuous layers as follows:
1. Subsoil Fill: Maximum 12 inches compacted depth.
2. Structural Fill: Maximum 8 inches compacted depth.
3. Granular Fill: Maximum 8 inches compacted depth.
D. Employ placement method that does not disturb or damage other work.
E. Maintain optimum moisture content of backfill materials to attain required compaction density.
F. Backfill against supported foundation walls. Do not backfill against unsupported foundation walls.
31 23 23 - 3
G. Backfill simultaneously on each side of unsupported foundation walls until supports are in place.
H. Slope grade away from building minimum 2 percent slope for minimum distance of 10 ft, unless noted otherwise.
I. Make gradual grade changes. Blend slope into level areas.
J. Remove surplus backfill materials from site.
K. Leave fill material stockpile areas free of excess fill materials.
3.4 TOLERANCES
A. Section 01400 – Quality Control.
B. Top Surface of General Backfilling: Plus or minus 1 inch from required elevations.
3.5 FIELD QUALITY CONTROL
A. Section 01400 – Quality Control.
B. Contractor shall perform laboratory material tests in accordance with ASTM
D1557, ASTM D698 and AASHTO T180.
C. Contractor shall perform in place compaction tests in accordance with the following:
1. Density Tests: ASTM D1556 and ASTM D2922.
2. Moisture Tests: ASTM D3017.
D. When tests indicate Work does not meet specified requirements, remove Work, replace and retest, at no cost to Owner.
E. Frequency of Tests:
1. Contractor shall perform density testing of backfill materials prior to subsequent layer at a frequency of 2 tests per layer per abutment for all structural backfill.
F. Proof roll compacted fill surfaces under slabs-on-grade and paving.
3.6 PROTECTION OF FINISHED WORK
A. Section 01700 – Contract Close-Out: Protecting finished work.
B. Re-shape and re-compact fills subjected to vehicular traffic.
3.7 SCHEDULE
A. Abutment backfill:
1. Existing site soils, compacted to 95 percent.
END OF SECTION