This document contains bid drawings for shower renovations at the Alger Correctional Facility, prepared by the State of Michigan Department of Technology, Management and Budget (DTMB), Design and Construction Division. The project involves comprehensive electrical, mechanical, and plumbing upgrades across multiple housing units (Spruce, Birch, Maple, and Pine), with specific focus on replacing shower systems, installing new exhaust fans, updating electrical circuits, and modifying existing infrastructure. The bid set is dated 03/21/2025, with plan review completed on 03/14/2025, and covers renovations for second floor areas in various buildings, including new lighting, power systems, HVAC modifications, and plumbing installations.
The project appears to be phased, with specific requirements for maintaining operational shower capacity during renovations. The contractor must work in one housing unit at a time, ensuring six showers remain functional throughout the project. The renovation includes installing new I-CON shower control systems, exhaust fans, electrical circuits, and plumbing infrastructure. The drawings indicate alternate options for different buildings (Alt 1), suggesting potential variability in scope and pricing. The project involves precise coordination with existing building systems, including careful routing of ductwork, electrical conduits, and plumbing, with specific instructions to minimize structural disruption and maintain existing warranties.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ELECTRICAL KEY NOTES
PROVIDE AND INSTALL NEW LIGHT FIXTURE. RE-USE
EXISTING CIRCUIT. REFER TO SHEET E-100 FOR LIGHT
FIXTURE SCHEDULE.
PROVIDE AND INSTALL NEW LOCK SWITCH (LEGRAND MODEL
NUMBER PS20AC1WL OR APPROVED EQUAL). PROVIDE NEW
SECURITY COVER PLATE AND SECURITY SCREWS. RE-USE
EXISTING CIRCUIT.
PROVIDE AND INSTALL NEW LIGHT FIXTURE. FEED FROM
EXISTING LIGHTING CIRCUIT OUTSIDE OF SHOWER STALL.
REFER TO SHEET E-100 FOR LIGHT FIXTURE SCHEDULE.
LA
LB LB
LA
LB LB
LA
1 1
LC LC
LC LC
LA
1 1
LC LC
LC LC
3 3
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y
KEY PLAN
SCALE: NTS
wing 'A' wing 'C'
LOWER LEVEL
PLAN
NORTH
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
D
R K
EL
EC
TR
IC
AL
FL
O O
R P
LA
N
N
EW
L
IG
H
TI
N G
JF
S
E-
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
FIRST FLOOR PLAN - BUILDING SPRUCE-
AREA A - ELECTRICAL LIGHTING - NEW
SECOND FLOOR PLAN - BUILDING SPRUCE-
AREA B - ELECTRICAL LIGHTING - NEW
FIRST FLOOR PLAN - BUILDING SPRUCE-
AREA C - ELECTRICAL LIGHTING - NEW
SECOND FLOOR PLAN - BUILDING SPRUCE-
AREA D - ELECTRICAL LIGHTING - NEW
N N
PROVIDE AND INSTALL NEW LIGHT FIXTURE. RE-USE
EXISTING CIRCUIT. REFER TO SHEET E-100 FOR LIGHT
FIXTURE SCHEDULE.
PROVIDE AND INSTALL NEW LOCK SWITCH (LEGRAND MODEL
NUMBER PS20AC1WL OR APPROVED EQUAL). PROVIDE NEW
SECURITY COVER PLATE AND SECURITY SCREWS. RE-USE
EXISTING CIRCUIT.
2 2
LA
LB LB
2 2
LA
LB LB
2 21
LBLA LB
2 2
LA
LB LB
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y
KEY PLAN
SCALE: NTS
wing 'A' wing 'C'
LOWER LEVEL
PLAN
NORTH
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
D
R K
EL
EC
TR
IC
AL
FL
O O
R P
LA
N
N
EW
L
IG
H
TI
N G
JF
S
E-
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
FIRST FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA A - ELECTRICAL NEW
SECOND FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA B - ELECTRICAL NEW
FIRST FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA C - ELECTRICAL NEW
SECOND FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA D - ELECTRICAL NEW
N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N N N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N N
N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N N N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
J
(4) 3/4" CND RACEWAY
FOR TOUCH SENSOR
CABLE
(1) 3/4" CND RACEWAY FOR TOUCH
SENSOR CABLE
TO
UPPER
LEVEL
(2) 3/4" CND FOR TOUCH SENSOR
CABLE
(2) #12
(1) #10 GRD
(1) 3/4" CND
TO PANEL 'RPC',
CIRCUIT #41 IN
ELECTRICAL ROOM.
REFER TO SHEET E-502
FOR LOCATION.
ICON SHOWER CONTROLLER
COORDINATE WITH PLUMBING
CONTRACTOR FOR LOCATION
AND REFER TO P-400 FOR
MODEL NUMBER
LOW VOLTAGE
TRANSFORMER
1. ELECTRICAL CONTRACTOR TO PROVIDE A 3/4" RACEWAY FROM I-CON
SHOWER CONTROLLER TO TOUCH SENSOR LOCATION. THIS
RACEWAY WILL BE USED FOR FISHING LOW VOLTAGE SENSOR
CABLES TO EXACT SENSOR LOCATION. COORDINATE WITH OTHER
TRADES IN FEILD.
GENERAL ELECTRICAL NOTES
TO
LOWER
LEVEL
(1) 3/4" CND RACEWAY FOR TOUCH
SENSOR CABLE
EF-1
120V 1Ø, 1/3HP
(LOCATED ON ROOF)
RPC-40
(2) #12
(1) #12 GRD
(1) 3/4" CND
TO ELECTRICAL
ROOM. REFER TO
SHEET E-502 FOR
LOCATION.
TO
LOWER
LEVEL
(1) 3/4" CND
RACEWAY FOR
TOUCH SENSOR
CABLE
EF-2
120V 1Ø, 1/3HP
RPC-42
(2) #12
(1) #12 GRD
(1) 3/4" CND
TO ELECTRICAL
ROOM. REFER
TO SHEET E-502
FOR LOCATION.
(1) 3/4" CND RACEWAY FOR TOUCH
(1) 3/4" CND
RACEWAY FOR
TOUCH SENSOR
CABLE
TO PANEL 'RPC',
CIRCUIT #39 IN
ELECTRICAL ROOM.
REFER TO SHEET
E-502 FOR LOCATION.
TO
UPPER
LEVEL
(2) 3/4" CND FOR TOUCH
SENSOR CABLE
ICON SHOWER CONTROLLER
COORDINATE WITH PLUMBING
CONTRACTOR FOR LOCATION
AND REFER TO P-400 FOR
MODEL NUMBER
LOW VOLTAGE
TRANSFORMER
2(2) #12
(1) #10 GRD
(1) 3/4" CND
ELECTRICAL KEY NOTES
PROVIDE AND INSTALL NEW CIRCUIT FROM EXISTING PANEL
"RPC" LOCATED IN ELECTRICAL ROOM FOR NEW EXHAUST FAN
ON ROOF. PROVIDE AND INSTALL ALL CONDUIT, WIRE,
HARDWARE, THERMAL OVERLOAD SWITCHES, STARTERS
PROVIDE AND INSTALL LOCAL SERVICE LOCKABLE SWITCH.
COORDINATE FINAL LOCATION OF SERVICE SWITCH WITH
OWNER TO ENSURE MOST USER AND APPLICATION FRIENDLY
LOCATION.
PROVIDE AND INSTALL NEW CIRCUIT FROM EXISTING PANEL
"RPC" LOCATED IN ELECTRICAL ROOM FOR NEW 120V-1PH
500VA LOW VOLTAGE TRANSFORMER. PROVIDE AND INSTALL
ALL CONDUIT, WIRE, AND HARDWARE AS REQUIRED. REFER
TO SHEET E-502 FOR PANEL LOCATIONS.
RE-INSTALL EXISTING TOUCH SCREEN PHONE. MODIFY
CONDUIT AND WIRE AS REQUIRED.
PROVIDE AND INSTALL NEW SURFACE MOUNT CONDUIT,
HARDWARE, AND BOX TO RELOCATE EXISTING DEVICE SHOWN
ON SHEET E-300. EXTEND WIRE AS REQUIRED.
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y
KEY PLAN
SCALE: NTS
wing 'A' wing 'C'
LOWER LEVEL
PLAN
NORTH
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
D
R K
EL
EC
TR
IC
AL
FL
O O
R P
LA
N
N
EW
P O
W
ER
JF
S
E-
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
FIRST FLOOR PLAN - BUILDING SPRUCE-
AREA C - ELECTRICAL POWER - NEW
SECOND FLOOR PLAN - BUILDING SPRUCE-
AREA D - ELECTRICAL POWER - NEW
FIRST FLOOR PLAN - BUILDING SPRUCE-
AREA A - ELECTRICAL POWER - NEW
SECOND FLOOR PLAN - BUILDING SPRUCE-
AREA B - ELECTRICAL POWER - NEWN N
1. ELECTRICAL CONTRACTOR TO PROVIDE A 3/4" RACEWAY FROM I-CON
SHOWER CONTROLLER TO TOUCH SENSOR LOCATION. THIS
RACEWAY WILL BE USED FOR FISHING LOW VOLTAGE SENSOR
CABLES TO EXACT SENSOR LOCATION. COORDINATE WITH OTHER
TRADES IN FEILD.
GENERAL ELECTRICAL NOTES
TO UPPER LEVEL
TO PANEL 'RPC', CIRCUIT
#41 IN ELECTRICAL ROOM.
REFER TO SHEET E-503 FOR
LOCATION.
(1) 3/4" CND RACEWAY FOR
TOUCH SENSOR CABLE
(2) 3/4" CND FOR TOUCH
SENSOR CABLE
ICON SHOWER CONTROLLER
COORDINATE WITH PLUMBING
CONTRACTOR FOR LOCATION
AND REFER TO P-401 FOR
MODEL NUMBER LOW VOLTAGE
TRANSFORMER
(2) #12
(1) #10 GRD
(1) 3/4" CND
TO LOWER LEVEL
(2) #12 2 CONDUCTOR AWG PLENUM
RATED LOW VOLTAGE CABLES
(1) 3/4" CND
EF-3
120V 1Ø, 1/3HP
RPC-42
(2) #12
(1) #12 GRD
(1) 3/4" CND
TO ELECTRICAL ROOM.
REFER TO SHEET
E-503FOR LOCATION.
TO LOWER LEVEL
(1) 3/4" CND RACEWAY FOR
TOUCH SENSOR CABLE
EF-4
120V 1Ø, 1/3HPRPC-40
(2) #12
(1) #12 GRD
(1) 3/4" CND
TO ELECTRICAL ROOM.
REFER TO SHEET E-503
FOR LOCATION.
TO UPPER LEVEL
TO PANEL 'RPC', CIRCUIT
#39 IN ELECTRICAL ROOM.
REFER TO SHEET E-503 FOR
LOCATION.
(1) 3/4" CND RACEWAY FOR
TOUCH SENSOR CABLE
(2) 3/4" CND FOR
TOUCH SENSOR
CABLE
ICON SHOWER CONTROLLER
COORDINATE WITH PLUMBING
CONTRACTOR FOR LOCATION
AND REFER TO P-401 FOR
MODEL NUMBER
LOW VOLTAGE
TRANSFORMER
(2) #12
(1) #10 GRD
(1) 3/4" CND
ELECTRICAL KEY NOTES
PROVIDE AND INSTALL NEW CIRCUIT FROM EXISTING PANEL
"RPC" LOCATED IN ELECTRICAL ROOM FOR NEW EXHAUST FAN
ON ROOF. PROVIDE AND INSTALL ALL CONDUIT, WIRE,
HARDWARE, THERMAL OVERLOAD SWITCHES, STARTERS
PROVIDE AND INSTALL LOCAL SERVICE LOCKABLE SWITCH.
COORDINATE FINAL LOCATION OF SERVICE SWITCH WITH
OWNER TO ENSURE MOST USER AND APPLICATION FRIENDLY
LOCATION.
PROVIDE AND INSTALL NEW CIRCUIT FROM EXISTING PANEL
"RPC" LOCATED IN ELECTRICAL ROOM FOR NEW 120V-1PH
500VA LOW VOLTAGE TRANSFORMER. PROVIDE AND INSTALL
ALL CONDUIT, WIRE, AND HARDWARE AS REQUIRED. REFER
TO SHEET E-502 FOR PANEL LOCATIONS.
RE-INSTALL EXISTING TOUCH SCREEN PHONE. MODIFY
CONDUIT AND WIRE AS REQUIRED.
PROVIDE AND INSTALL NEW SURFACE MOUNT CONDUIT,
HARDWARE, AND BOX TO RELOCATE EXISTING DEVICE SHOWN
ON SHEET E-300. EXTEND WIRE AS REQUIRED.
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y
KEY PLAN
SCALE: NTS
wing 'A' wing 'C'
LOWER LEVEL
PLAN
NORTH
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
D
R K
JF
S
E-
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
FIRST FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA A - ELECTRICAL NEW
SECOND FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA B - ELECTRICAL NEW
FIRST FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA C - ELECTRICAL NEW
SECOND FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE -
AREA D - ELECTRICAL NEW
EL
EC
TR
IC
AL
FL
O O
R P
LA
N
N
EW
P O
W
ER
N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N NN
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N N
N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N N N
BIRCH MAPLE PINE
PROVIDE WRITTEN AS-CONSTRUCTED DOCUMENTS AS PART
OF CLOSE OUT DOCUMENTS. PROVIDE AND INSTALL
PERMANENTLY FIXED LABELS AND UPDATE PANEL SCHEDULES
ACCORDINGLY. PROVIDE TYPED PANEL SCHEDULES.
INSTALL NEW 20A/1P CIRCUIT BREAKER IN EXISTING BLANK
SPACES, CIRCUITS #39 AND #41 FOR SHOWER CONTROL LOW
VOLTAGE TRANSFORMERS.
INSTALL NEW 20A/1P CIRCUIT BREAKER IN EXISTING BLANK
SPACES, CIRCUITS #40 AND #42 FOR NEW EXHAUST FANS.
ELECTRICAL
ROOM
AREA OF WORK ON
UPPER AND LOWER
LEVELS
AREA OF WORK ON
UPPER AND LOWER
LEVELS
RPA
208/120V 3Ø
RPB
208/120V 3Ø
RPC
208/120V 3Ø
RPD
208/120V 3Ø
RPX
208/120V 3Ø
EMDP
480V 3Ø
D R
K H
O U
SI
N
G U
N
IT
EL
EC
TR
IC
AL
R
O O
M S
JF
S
E-
SECOND FLOOR PLAN - BUILDING SPRUCE -
ELECTRICAL NEW
N
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y R ev ie w D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
SCALE: 1/8" = 1'-0"
0 1 5 10 20
PROVIDE WRITTEN AS-CONSTRUCTED DOCUMENTS AS PART
OF CLOSE OUT DOCUMENTS. PROVIDE AND INSTALL
PERMANENTLY FIXED LABELS AND UPDATE PANEL SCHEDULES
ACCORDINGLY. PROVIDE TYPED PANEL SCHEDULES.
INSTALL NEW 20A/1P CIRCUIT BREAKER IN EXISTING BLANK
SPACES, CIRCUITS #39 AND #41 FOR SHOWER CONTROL LOW
VOLTAGE TRANSFORMERS.
INSTALL NEW 20A/1P CIRCUIT BREAKER IN EXISTING BLANK
SPACES, CIRCUITS #40 AND #42 FOR NEW EXHAUST FANS.
ELECTRICAL
ROOM
AREA OF WORK ON
UPPER AND
LOWER LEVELS
AREA OF WORK ON
UPPER AND
LOWER LEVELS
RPX
208/120V 3Ø
RPA
208/120V 3Ø
RPB
208/120V 3Ø
RPC
208/120V 3Ø
RPD
208/120V 3Ø
D R
K H
O U
SI
N
G U
N
IT
EL
EC
TR
IC
AL
R
O O
M S
JF
S
E-
3SECOND FLOOR PLAN - BUILDING BIRCH, MAPLE, PINE
ELECTRICAL NEW
N
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y R ev ie w D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
SCALE: 1/8" = 1'-0"
0 1 5 10 20
BIRCH MAPLE PINE
NN
GENERAL HVAC NOTES
MECHANICAL SYMBOLS LEGEND
HVAC DUCTWORK
MISCELLANEOUS NOTES
HVAC DUCTWORK SYMBOLS HVAC DUCTWORK & DIFFUSER TAGS
MECHANICAL ABBREVIATIONS
AFF ABOVE FINISH FLOOR
AC AIR COMPRESSOR
AHU AIR HANDLING UNIT
AS AIR SEPARATOR
A.T.C. ARCHITECTURAL TRADES CONTRACTOR
B BOILER
B.A.S. BUILDING AUTOMATION SYSTEM
CAF COMBUSTION AIR FAN
CC COOLING COIL
CFM CUBIC FEET PER MINUTE
CHLR CHILLER
CHP CONSOLE HEAT PUMP
CONV CONVECTOR
CT COOLING TOWER
CU CONDENSING UNIT
CUH CABINET UNIT HEATER
CV CONTROL VALVE
CWP CHILLED WATER PUMP
DB DRY BULB
DFU DUCT FURNACE
DIA DIAMETER
DN DOWN
DPR DAMPER
DS DUCT SILENCER
EAT ENTERING AIR TEMPERATURE
EF EXHAUST FAN
EG EXHAUST GRILLE
E.T.C. ELECTRICAL TRADES CONTRACTOR
EVR EVAPORATOR
EWT ENTERING WATER TEMPERATURE
EXH EXHAUST
EXIST EXISTING
FF FINISH FLOOR
FPM FEET PER MINUTE
FT FEET
FTR FINNED TUBE RADIATION
FU FURNACE
GAL GALLON
GFRH GAS FIRED RADIANT HEATER
GR GRILLE
H HUMIDIFIER
HC HEATING COIL
HD HEAD (FT)
HP HORSE POWER
HHP HORIZONTAL HEAT PUMP
HTG HEATING
HVAC HEATING, VENTILATION, & AIR CONDITIONING
HWP HEATING WATER PUMP
HX HEAT EXCHANGER
ID INSIDE DIAMETER
I.E. INVERT ELEVATION
IAH INTAKE HOOD
LAT LEAVING AIR TEMPERATURE
LH LATENT HEAT (MBH)
LWT LEAVING WATER TEMPERATURE
MAX MAXIMUM
MBH BTU PER HOUR (THOUSAND)
MIN MINIMUM
M.T.C. MECHANICAL TRADES CONTRACTOR
N.C. NOISE CRITERIA
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
NTS NOT TO SCALE
P PUMP
PCR PUMPED CONDENSATE RETURN
PD PRESSURE DROP
RCP RADIANT CEILING PANEL
REQ'D REQUIRED
RG RETURN GRILLE
RH RELATIVE HUMIDITY
RLH RELIEF HOOD
RTU ROOF TOP UNIT
SD SUPPLY DIFFUSER
SF SUPPLY FAN
SG SUPPLY GRILLE
SH SENSIBLE HEAT (MBH)
SM SHEET METAL
SQ. FT. SQUARE FEET
SST SATURATED SUCTION TEMPERATURE
STR STRAINER
TC TOTAL COOLING (MBH)
TCL TEMPERATURE CONTROL
T&P TEMPERATURE & PRESSURE RELIEF VALVE
TYP TYPICAL
UH UNIT HEATER
VAV VARIABLE AIR VOLUME BOX
VRH VARIABLE AIR VOLUME REHEAT BOX
FPVAV FAN POWERED VARIABLE AIR VOLUME BOX
V.F.D VARIABLE FREQUENCY DRIVE
ZD ZONE DAMPER
X-SA EXISTING ITEM (EXISTING SUPPLY AIR DUCT)
ITEM
EXISTING
SUPPLY AIR DUCT
EXIST SUPPLY AIR DUCT
RETURN AIR DUCT
EXIST RETURN AIR DUCT
OUTSIDE AIR DUCT
EXIST OUTSIDE AIR DUCT
EXHAUST AIR DUCT
EXIST EXHAUST AIR DUCT
SUPPLY AIR DUCT RISER
RETURN AIR DUCT RISER
OUTSIDE AIR DUCT RISER (AS NOTED)
EXHAUST AIR DUCT
INSULATED DUCTWORK (AS NOTED)
SUPPLY AIR DIFFUSER (SQUARE)
SUPPLY AIR DIFFUSER (INLINE)
SURFACE MTD. GRILLE
SUPPLY AIR DIFFUSER (ROUND)
DEMOLITION
POINT OF CONNECTION BETWEEN NEW AND
EXISTING
POINT OF EXISTING TO REMAIN AND EXISTING
TO BE REMOVED
INDICATES PLAN NOTE
INDICATES DEMOLITION NOTE
DETAIL BUBBLE
DETAIL NUMBER
PAGE LOCATION INDICATES
DIRECTION OF DETAIL SECTION
X
X
XX
XXXX
XX
XXXX
SA
OA
X-OA
X-EA
EA
X-SA
X-RA
RA
TAG CFM
NECK REMARKS
SIZE
SD-1 250
8"ø ---
PHASING NOTES
GENERAL INFORMATION:
A. EXISTING WATER SERVICE SHALL REMAIN ACTIVE AND
FUNCTIONAL DURING CONSTRUCTION. INDIVIDUAL RISERS CAN
BE SHUTDOWN AS NEEDED, COORDINATE WITH OWNER PRIOR
TO BRANCH SHUTDOWNS.
B. PHASING NOTES ARE INTENDED FOR GENERAL SEQUENCE OF
CONSTRUCTION. CONTRACTOR TO COORDINATE WITH
DRAWINGS FOR SPECIFIC DETAILS FOR DEMOLITION &
INSTALLATION OF ALL NEW EQUIPMENT, PIPING, AND
ACCESSORIES.
C. ALL RISER SHUTDOWNS TO BE CLOSELY COORDINATED WITH
THE OWNER.
D. ONLY ONE SET OF SHOWERS PER HOUSING UNIT SHALL BE
UPGRADED AT A TIME. SIX SHOWERS TO REMAIN IN SERVICE
AT ALL TIMES.
E. THE OWNER WILL PROVIDE A MAXIMUM OF 2 ESCORTS WITH
THE ANTICIPATION THAT WORK IN TWO DIFFERENT HOUSING
UNITS WILL BE HAPPENING SIMULTANEOUSLY.
F. FOR ALL HOUSING UNITS ON THIS PROJECT ONLY ONE
SET/PAIR OF SHOWERS CAN BE SHUT DOWN AND WORKED
ON AT ANY ONE TIME PER HOUSING UNIT, EXCEPT FOR
BIRCH. THE REMAINING THREE SETS/PAIRS OF SHOWERS
ARE TO BE FULLY OPERATIONAL. THE REPLACED SHOWERS
MUST BE FULLY INSPECTED, APPROVED, AND MADE
OPERABLE, BEFORE THE CONTRACTOR CAN MOVE TO THE
NEXT SET/PAIR OF SHOWERS TO BEGIN WORK.
G. CONTRACTOR TO BEGIN CONSTRUCTION IN HOUSING UNIT
BIRCH AS THE HOUSING UNIT IS CURRENTLY UNOCCUPIED.
G.A. HOUSING UNIT BIRCH IS UNOCCUPIED AT THE TIME OF
CONSTRUCTION, THE CONTRACTOR WILL HAVE
ACCESS AND THE ABILITY TO REPLACE ALL THE
SHOWERS AT ONE TIME.
3 ROOF MOUNTED EXHAUST FAN DETAIL
SCALE: NTS
ROOF OPENING FRAMING BY
GENERAL TRADES
SPUN ALUMINUM FAN
HOUSING
ALUMINUM BIRD SCREEN ALL
AROUND
SECURE FAN TO CURB WITH
SHEET METAL SCREWS 12"
O.C. ALL AROUND
REFER TO DRAWINGS FOR
DUCT SIZE
24" HIGH INSULATED PRE-
FAB. ROOF CURB
FAN IMPELLAR
DIRECT DRIVE MOTOR
COUNTER FLASHING
ROOFING MATERIAL BACKDRAFT
DAMPER
FRAME
VANED ELBOW
LOCKING LUG
2-1/4"R
4-1/2"R
TURNING VANE
NOTES:
1. LOCKING LUGS INTEGRAL WITH VANE
2. MAXIMUM UNSUPPORTED VANE LENGTH 48"
3. FRAMES - BOLTED OR RIVETED TO ELBOW
4. VANES AND FRAMES - SAME GAUGE AS ELBOW
2 1/4"
3 1/2"
HANGER STRAPS HANGER RODS
STRAP HANGER TRAPEZE HANGER
NO POP RIVETS ALLOWED,
USE SELF-TAPPING
SHEETMETAL SCREWS ONLY
(TYP)
NOTE:
90° ELBOW SHOWN SIMILAR
RADIUS CONSTRUCTION FOR
ALL ANGLES
R
R
OFFSET
ELBOW
FULL RADIUS
(R=W)
FLOW
AIR
TRANSITION - CONTRACTION FLOW
TRANSITION - DIVERGING FLOW
FLOW
AIR
W
W
R=1/ W
W
TURNING VANES FORSQUARE
ELBOW DETAIL
SCALE: NTS
4 DUCT HANGER DETAIL
SCALE: NTS
RECTANGULAR TRANSITIONS, OFFSETS,
AND ELBOWS
SCALE: NTS
5 DUCT TRANSITION DETAIL
SCALE: NTS
NOTES:
1. "ALTERNATE" FITTINGS SHALL BE
ACCEPTABLE ONLY WHEN DUCT HEIGHT
DOES NOT PERMIT THE USE OF
"PERMITTED" FULL SIZE BELLMOUTH
CONNECTION
2. THIS DETAIL APPLIES TO SINGLE TAKEOFFS
TO DIFFUSER AS WELL AS BRANCH
TAKEOFFS. IT ALSO APPLIES TO TAKEOFFS
IN THE HORIZONTAL AS WELL AS THE
VERTICAL DIRECTION.
DUCT SIZE:
(SEE PLANS)
ALTERNATE 1
TAKE-OFF DETAIL
ALTERNATE 2
TAKE-OFF DETAIL
(WHEN OTHERS DO NOT FIT)
RECTANGULAR TO ROUND
BOOT CONNECTIONMINI-BELLMOUTH CONNECTION
MANUAL VOLUME
DAMPER TYPICAL AT
ALL DUCT
TAKE-OFFS
VDVD
MAIN DUCT
AIR FLOW
6" min.
RADIUS ELBOW
1. LOCATE EXHAUST OUTLETS OF VENTILATION SYSTEMS AT LEAST 10 FEET
FROM OUTDOOR AIR INTAKES.
2. ALL EXISTING SYSTEMS (INCLUDING EXHAUST FANS AIR HANDLING UNITS;
PUMPS) THAT SERVES AREAS BEING RENOVATED SHALL BE REBALANCED AS
REQUIRED.
3. NOTIFY OWNER OF ANY PIPING OR DUCTWORK DEMOLITION THAT MAY
AFFECT NORMAL OPERATION OF OTHER AREAS.
4. FIELD VERIFY LOCATIONS OF EXISTING DUCTWORK OR PIPING THAT MAY
CONFLICT WITH NEW CONSTRUCTION AND NOTIFY ENGINEER .
5. PROVIDE BALANCE DAMPERS FOR EACH DIFFUSER/GRILLE AND BRANCH
DUCT.
6. PROVIDE FLEXIBLE DUCT IN ACCESSIBLE CEILINGS. 6 FT MAX LENGTH. KEEP
BENDS TO A MINIMUM.
7. FIRE DAMPERS & COMBINATION FIRE/SMOKE DAMPERS SHALL MATCH
RATING OF WALL. UNLESS NOTED OTHERWISE.
8. CONTRACTOR SHALL COORDINATE ALL WORK WITH OTHER DISCIPLINES
PRIOR TO CONSTRUCTION TO AVOID CONFLICTS.
9. OFFSET PIPING TO ACCOMMODATE LARGE DUCTWORK.
10. THE CONTRACTOR SHALL FIELD VERIFY THE SIZES, LOCATION, ELEVATIONS,
AND DETAILS OF ALL EXISTING CONDITIONS THAT MAY AFFECT THE WORK.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING THE
INTEGRITY OF ALL EQUIPMENT AND MATERIALS IN A "NEW" CONDITION
DURING CONSTRUCTION.
12. ALL WORK SHALL BE PERFORMED BY LICENSED CONTRACTORS AND
SUBCONTRACTORS AS REQUIRED BY LAW.
13. ALL WORK SHALL CONFORM TO MICHIGAN MECHANICAL CODE, LATEST
APPLICABLE EDITION.
14. CONTRACTOR SHALL USE LOW PRESSURE LOSS DUCT FITTINGS IN
ACCORDANCE WITH SMACNA. (WYES, RADIUSED OR VANED TEES, ETC.)
DUCTWORK SHALL BE GALVANIZED SHEET METAL, MIN. 26 GA.
15. ALL DUCT DIMENSIONS SHOWN ARE INSIDE CLEAR DIMENSION. INCREASE
DUCT SIZE FOR LINING.
16. IF THERE IS CONFLICTING INFORMATION IN THE PLANS OR SPECIFICATIONS
THE MORE STRINGENT AND GREATER COST ITEM SHALL BE USED.
17. DRAWINGS INDICATE REQUIRED SIZES AND POINTS OF TERMINATION OF
PIPES AND DUCTS AND SUGGESTED ROUTES. IT IS NOT INTENTION OF
DRAWINGS TO INDICATE ALL NECESSARY OFFSETS. INSTALL WORK IN
MANNER TO CONFORM TO STRUCTURE, AVOID OBSTRUCTIONS, PRESERVE
HEADROOM AND KEEP OPENINGS AND PASSAGEWAYS CLEAR. DO NOT
SCALE FROM DRAWINGS.
18. ALL AREAS OF WORK MUST BE SECURED AND INACCESSIBLE TO INMATES
DURING CONSTRUCTION. THE CONTRACTOR MUST SECURE EACH AREA OF
WORK AT THE END OF EACH SHIFT.
19. CONTRACTOR TO TRACK AND PROVIDE PAPERWORK TO OWNER OF THE
AMOUNT OF MATERIAL BEING RECYCLED THROUGHOUT THE PROJECT.
20. CONTRACTOR TO PATCH AND PAINT EXISTING CEILINGS AND WALLS AS
NEEDED TO MATCH EXISTING WHERE DEMOLITION AND/OR NEW WORK IS
COMPLETED.
21. ALL FASTENERS USED IN AREAS EXPOSED TO INMATES SHALL USE
TAMPERPROOF SCREWS.
22. CONTRACTOR TO VERIFY WITH I-CON OR PRE-APPROVED SHOWER
ENCLOUSRE MANUFACTURER FOR THE LOCATION OF THE SHOWER
ENCLOSURE BUILT-IN EXHAUST GRILLES.
23. CONTRACTOR TO FIELD VERIFY LOCATIONS WHERE THE NEW EXHAUST
DUCTWORK WILL PENETRATE THE EXISTING BLOCK WALL TO CONNECT TO
THE SHOWER ENCLOSURE EXHAUST GRILLE. CONTRACTOR TO VERIFY THAT
THE NEW EXHAUST DUCTWORK WILL NOT INTERFERE WITH ANY EXISTING
FIELD CONDITIONS OR ANY NEW UTILITIES ROUTED IN THE CHASE SPACE.
24. CONTRACTOR TO NOTIFY THE FACILITY AT LEAST 1 DAY IN ADVANCE FOR
ANY HOT WORK TO ALLOW THE OWNER TO DISABLE THE FIRE ALARM.
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y R ev ie w D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
JL
H
M
EC
H
AN
IC
AL
SY
M
BO
LS
AB
BR
EV
IA
TI
O
N S
N
O
TE
S
BR
H
M -1
X-6x8 SA UP X-6x8 RA UPX-RG ---
10x10 ---
X-RG ---
10x10 ---1
X-SD 50
12x12 ---
X-6x8 RA UP
X-6x8 RA DN
X-8x6 SA UP AND DN X-6x8 RA UP
X-6x8 RA UP AND DN
X-RG ---
10x10 ---
X-RG ---
10x10 ---1
X-SD 50
12x12 ---
X-6x8 RA UP X-6x8 RA DN
X-6x8 SA UP
X-8x6 SA DN
X-RG ---
10x10 ---
X-8x8 RA UP AND DN 1
X-SD 50
12x12 ---
X-RG ---
10x10 ---
X-RG ---
10x10 ---
X-RG ---
10x10 ---
X-6x8 SA UP X-6x8 RA UP
X-SD 50
12x12 ---
DEMOLITION NOTES
DISCONNECT, REMOVE, AND DEMO EXISTING RETURN GRILLE. ALTER EXISTING
DUCTWORK AS REQUIRED TO CONNECT TO NEW RETURN GRILLE.
DISCONNECT, REMOVE, AND DEMO EXISTING SUPPLY DIFFUSER. ALTER EXISTING
DUCTWORK AS REQUIRED TO CONNECT TO NEW SUPPLY DIFFUSER.
DISCONNECT, REMOVE, AND DEMO EXISTING SUPPLY DIFFUSER. CAP EXISTING
DUCTWORK ABOVE NEW CEILING AND ABANDON.
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
FL
O
O R
P
LA
N
BU
IL
D
IN
G
SP
R U
C E
- H
VA
C D
EM
O
LI
TI
O N
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA A - HVAC DEMOLITION
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
N
SECOND FLOOR PLAN - BUILDING
SPRUCE - AREA B - HVAC DEMOLITION
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA C - HVAC DEMOLITION N
SECOND FLOOR PLAN - BUILDING
SPRUCE - AREA D - HVAC DEMOLITION JL
H
BR
H
M -3
X-SD ---
15x15 ---
X-RG ---
12x12 ---
X-12x10 SA UP
X-10x10 RA UP X-12x12 SA UP X-8x6 RA UP
X-SD ---
12x12 ---
X-SA
X-SD ---
15x15 ---
X-RG ---
12x12 ---
X-12x10 SA DN
X-10x10 RA DN X-8x6 RA UP
X-10x10 RA DN
X-SD ---
12x12 ---
X-SA
10x10 RA DN
X-RG ---
12x12 ---
X-12x10 SA DN
X-12x10 RA UP
X-8x6 RA UP
X-SD ---
15x15 ---
X-SD ---
12x12 ---
X-SA
X-12x10 SA UP
X-12x12 SA UP
X-8x6 RA UP X-10x10 RA UP
X-SD ---
15x15 ---
X-RG ---
12x12 ---1
X-SD ---
12x12 ---
X-SA
DEMOLITION NOTES
DISCONNECT, REMOVE, AND DEMO EXISTING RETURN GRILLE. ALTER EXISTING
DUCTWORK AS REQUIRED TO CONNECT TO NEW RETURN GRILLE.
DISCONNECT, REMOVE, AND DEMO EXISTING SUPPLY DIFFUSER. ALTER EXISTING
DUCTWORK AS REQUIRED TO CONNECT TO NEW SUPPLY DIFFUSER.
DISCONNECT, REMOVE, AND DEMO EXISTING SUPPLY DIFFUSER. CAP EXISTING
DUCTWORK ABOVE NEW CEILING AND ABANDON.
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
JL
H
FL
O
O R
P
LA
N
BU
IL
D
IN
G S
BI
R
C H
, M
AP
LE
(A
LT
PI
N E(
AL
T
1)
H
VA
C D
EM
O
LI
TI
O N
BR
H
M -3
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
N
FIRST FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA A - HVAC DEMOLITION
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N N
N N N
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE,
PINE - AREA B - HVAC DEMOLITION
FIRST FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA C - HVAC DEMOLITION
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA D - HVAC DEMOLITION
NN N N
N N N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
BIRCH MAPLE PINE
RG-1 50
10x10 ---
RG-1 50
10x10 ---
X-6x8 SA UP X-6x8 RA UP
10x10 EA UP
SD-1 50
15x15 ---
8x6 EA DN TO
SHOWER EA GRILLE
OPENING (TYP. 2)
EG-1 100
8x6 ---
10x6 EA 2
6x6 EA
10x8 EA 2
RG-1 50
10x10 ---
RG-1 50
10x10 ---
X-6x8 RA UP
X-6x8 RA DN
X-8x6 SA UP AND DN X-6x8 RA UP
X-6x8 RA UP AND DN
12x12 EA UP
TO EF-1
(LOCATED ON
ROOF)
SD-1 50
15x15 ---
8x6 EA DN TO
SHOWER EA GRILLE
OPENING (TYP. 2)
10x6 EA
10x10 EA DN
4EG-1 100
8x6 ---
10x6 EA
RG-1 50
10x10 ---
RG-1 50
12x12 ---
X-6x8 RA UP X-6x8 RA DN
X-6x8 SA UP
X-8x6 SA DN
X-8x8 RA UP AND DN
12x12 EA UP
TO EF-2
(LOCATED ON
ROOF)
SD-1 50
15x15 ---
420x8 EA DN, 16x6 EA DN
THROUGH FLOOR
6x6 EA
8x6 EA DN TO
SHOWER EA GRILLE
OPENING (TYP. 2)
EG-1 100
8x6 ---
10x6 EA 2
20x8 EA
RG-1 50
12x12 ---
RG-1 50
10x10 ---
X-6x8 SA UP X-6x8 RA UP
16x6 EA UP
SD-1 50
15x15 ---
8x6 EA DN TO
SHOWER EA GRILLE
OPENING (TYP. 2)
EG-1 100
8x6 ---
10x6 EA
6x6 EA
HVAC KEY NOTES
INSTALL NEW ROOF MOUNTED EXHAUST FAN, ROOF
CURB, DUCTWORK, CONTROLS, AND ALL ASSOCIATED
ACCESSORIES IN THE LOCATION SHOWN.
CONTRACTOR TO PATCH NEW ROOF PENETRATION
TO MATCH EXISTING, SEAL WATER TIGHT, AND
MAINTAIN ANY EXISTING ROOF WARRANTIES.
COORDINATE WITH THE STRUCTURAL DRAWINGS FOR
LOCATION OF THE NEW PENETRATION. INSTALL
LOCAL ON/OFF SWITCH FOR EXHAUST FAN IN
LOCATION SHOWN.
INSTALL NEW EXHAUST AIR DUCTWORK AND ALL
ASSOCIATED ACCESSORIES IN THE LOCATION
SHOWN.
ROUTE NEW EXHAUST DUCTWORK TO NEW SHOWER
ENCLOSURE. CONNECT THE EXHAUST DUCTWORK TO
SHOWER ENCLOSURE INTEGRATED EXHAUST AIR
GRILLE. EXHAUST CONNECTION LOCATION TO BE
COORDINATED WITH SHOWER ENCLOSURE
MANUFACTURER. CONTRACTOR BALANCE THE
EXHAUST RATE TO 150 CFM FOR EACH SHOWER.
COORDINATE WITH THE STRUCTURAL DRAWINGS FOR
LOCATION OF THE NEW PENETRATION.
INSTALL NEW RETURN GRILLE AT LOCATION SHOWN.
ALTER EXISTING RETURN AIR DUCTWORK AS
REQUIRED TO CONNECT TO NEW EXHAUST GRILLE .
BALANCE TO CFM SHOWN.
INSTALL NEW SUPPLY DIFFUSER AT LOCATION
SHOWN. ALTER EXISTING SUPPLY DUCTWORK AS
REQUIRED TO CONNECT TO NEW SUPPLY GRILLE.
BALANCE TO CFM SHOWN.
BOTTOM EDGE OF EXHAUST GRILL SHALL BE
INSTALLED AT LEAST 6" ABOVE FINISHED FLOOR.
GENERAL HVAC NOTES
1. MODIFY THE EXISTING SPRINKLER PIPING PER NFPA
13 AS REQUIRED TO ACCOMMODATE NEW DUCTWORK,
DOMESTIC WATER PIPING, LIGHTING, AND CEILING.
2. CONTRACTOR TO COORDINATE NEW EXHAUST AIR
DUCT ROUTING TO ACCOMMODATE EXISTING
STRUCTURAL I-BEAM LOCATED IN THE CHASE SPACE
BEHIND SHOWERS.
3. ALL ROOF PENETRATIONS ARE TO BE SEALED WATER
TIGHT, MATCH EXISTING, AND MAINTAIN EXISTING
ROOF WARRANTIES. EXISTING ROOF WARRANTY BY
McGRATH ROOFING (PHONE #: 906-482-7107).
4. CONTRACTOR IS RESPONSIBLE FOR THE REMOVAL
AND PATCHING OF THE EXISTING HARD LID CEILING
AS REQUIRED TO COMPLETE THEIR WORK.
CONTRACTOR TO PATCH, PRIME, AND PAINT CEILING
AS REQUIRED PER THE ARCHITECTURAL DRAWINGS
TO MATCH EXISTING.
5. CONTRACTOR TO COORDINATE ALL DIFFUSER
LOCATIONS AND SIZES PRIOR TO NEW CEILING
INSTALLATION.
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
JL
H
BR
H
M -4
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA A - HVAC NEW
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
N
SECOND FLOOR PLAN - BUILDING
SPRUCE - AREA B - HVAC NEW
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA C - HVAC NEW N
SECOND FLOOR PLAN - BUILDING
SPRUCE - AREA D - HVAC NEW
FL
O
O R
P
LA
N
BU
IL
D
IN
G
SP
R U
C E
- H
VA
C N
EW
SD-1 50
15x15 ---
RG-1 50
12x12 ---5
X-12x10 SA UP
X-10x10 RA UP X-12x12 SA UP X-8x6 RA UP
X-SA
12x8 EA UP
8x6 EA TO SHOWER
EA GRILLE OPENING
(TYP. 2)
2 EG-1 50
12x12 TYP. 2
6x10 EA 2
6x6 EA
CAP
6x6 EA
SD-1 50
15x15 ---
RG-1 50
12x12 ---5
X-12x10 SA DN
X-10x10 RA DN X-8x6 RA UP
X-10x10 RA DN
X-SA
12x12 EA UP TO EF-3
(MOUNTED ON ROOF)
8x6 EA TO SHOWER
EA GRILLE OPENING
(TYP. 2)
12x12 EA UP, 12x8 EA
DN THROUGH FLOOR
6x6 EA
6x10 EA 2
EG-1 50
12x12 TYP. 2
CAP
6x6 EA
SD-1 50
15x15 ---
RG-1 50
12x12 ---
10x10 RA DN
X-12x10 SA DN
X-12x10 RA UP
X-8x6 RA UP
X-SA
12x12 EA UP TO EF-4
(MOUNTED ON ROOF)
8x6 EA TO SHOWER
EA GRILLE OPENING
(TYP. 2)
2EG-1 50
12x12 TYP. 2
12x12 EA UP, 12x8 EA
DN THROUGH FLOOR
6x6 EA
6x10 EA2
6x6 EA 2
CAP
RG-1 50
12x12 ---
X-12x10 SA UP
X-12x12 SA UP
X-8x6 RA UP X-10x10 RA UP
X-SA
SD-1 50
15x15 ---6
12x8 EA UP
8x6 EA TO SHOWER
EA GRILLE OPENING
(TYP. 2)
6x6 EA
6x10 EA2
6x6 EA 2
CAP
EG-1 50
12x12 TYP. 2
HVAC KEY NOTES
INSTALL NEW ROOF MOUNTED EXHAUST FAN, ROOF
CURB, DUCTWORK, CONTROLS, AND ALL ASSOCIATED
ACCESSORIES IN THE LOCATION SHOWN.
CONTRACTOR TO PATCH NEW ROOF PENETRATION
TO MATCH EXISTING, SEAL WATER TIGHT, AND
MAINTAIN ANY EXISTING ROOF WARRANTIES.
COORDINATE WITH THE STRUCTURAL DRAWINGS FOR
LOCATION OF THE NEW PENETRATION. INSTALL
LOCAL ON/OFF SWITCH FOR EXHAUST FAN IN
LOCATION SHOWN.
INSTALL NEW EXHAUST AIR DUCTWORK AND ALL
ASSOCIATED ACCESSORIES IN THE LOCATION
SHOWN.
ROUTE NEW EXHAUST DUCTWORK TO NEW SHOWER
ENCLOSURE. CONNECT THE EXHAUST DUCTWORK TO
SHOWER ENCLOSURE INTEGRATED EXHAUST AIR
GRILLE. EXHAUST CONNECTION LOCATION TO BE
COORDINATED WITH SHOWER ENCLOSURE
MANUFACTURER. CONTRACTOR BALANCE THE
EXHAUST RATE TO 150 CFM FOR EACH SHOWER.
COORDINATE WITH THE STRUCTURAL DRAWINGS FOR
LOCATION OF THE NEW PENETRATION.
INSTALL NEW RETURN GRILLE AT LOCATION SHOWN.
ALTER EXISTING RETURN AIR DUCTWORK AS
REQUIRED TO CONNECT TO NEW EXHAUST GRILLE .
BALANCE TO CFM SHOWN.
INSTALL NEW SUPPLY DIFFUSER AT LOCATION
SHOWN. ALTER EXISTING SUPPLY DUCTWORK AS
REQUIRED TO CONNECT TO NEW SUPPLY GRILLE.
BALANCE TO CFM SHOWN.
GENERAL HVAC NOTES
1. MODIFY THE EXISTING SPRINKLER PIPING PER NFPA
13 AS REQUIRED TO ACCOMMODATE NEW DUCTWORK,
DOMESTIC WATER PIPING, LIGHTING, AND CEILING.
2. CONTRACTOR TO COORDINATE NEW EXHAUST AIR
DUCT ROUTING TO ACCOMMODATE EXISTING
STRUCTURAL I-BEAM LOCATED IN THE CHASE SPACE
BEHIND SHOWERS.
3. ALL ROOF PENETRATIONS ARE TO BE SEALED WATER
TIGHT, MATCH EXISTING, AND MAINTAIN EXISTING
ROOF WARRANTIES. EXISTING ROOF WARRANTY BY
McGRATH ROOFING (PHONE #: 906-482-7107).
4. CONTRACTOR IS RESPONSIBLE FOR THE REMOVAL
AND PATCHING OF THE EXISTING HARD LID CEILING
AS REQUIRED TO COMPLETE THEIR WORK.
CONTRACTOR TO PATCH, PRIME, AND PAINT CEILING
AS REQUIRED PER THE ARCHITECTURAL DRAWINGS
TO MATCH EXISTING.
5. CONTRACTOR TO COORDINATE ALL DIFFUSER
LOCATIONS AND SIZES PRIOR TO NEW CEILING
INSTALLATION.
6. VERIFY LOCATION OF THE NEW DUCTWORK THAT WILL
EXIT STRAIGHT OUT THE BACK OF THE SHOWER
CABINET THROUGH THE EXISTING BLOCK WALL AND
WILL NOT COLLIDE WITH ANY EXISTING PIPES OR
CONDUIT. LOCATION OF THE EXHAUST PERFORATIONS
MAY VARY FROM SHOWER CABINET TO SHOWER
CABINET.
X-12x10 SA UP
X-10x10 RA UP X-12x12 SA UP X-8x6 RA UP
X-SA
SD-1 50
15x15 ---
RG-1 50
12x12 ---5
12x8 EA UP
8x6 EA TO SHOWER
EA GRILLE OPENING
(TYP. 2)
2 EG-1 50
12x12 TYP. 2
6x10 EA 2
6x6 EA2
CAP
6x6 EA
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
JL
H
BR
H
M -4
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
FL
O
O R
P
LA
N
BU
IL
D
IN
G S
BI
R
C H
, M
AP
LE
(A
LT
PI
N E(
AL
T
1)
H
VA
C N
EW
FIRST FLOOR PLAN - BUILDINGS BIRCH & MAPLE -
AREA A - HVAC NEW
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE,
PINE - AREA B - HVAC NEW
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA D - HVAC NEW
FIRST FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA C - HVAC NEW
N
BIRCH MAPLE
(ALT 1)
N
NN N N
N
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
N N
N N N
N
PINE
(ALT 1)
SCALE: 1/4" = 1'-0"
0 1 5 10
FIRST FLOOR PLAN - BUILDING
PINE - AREA A - HVAC NEW
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
PLUMBING ABBREVIATIONS
PLUMBING SYMBOLS LEGEND
PLUMBING PIPING PLUMBING EQUIPMENT
1. ALL PLUMBING WORK SHALL CONFORM TO MICHIGAN
PLUMBING CODE, LATEST APPLICABLE EDITION.
2. INSTALL ALL EQUIPMENT, MATERIALS, AND
ACCESSORIES PER MANUFACTURERS WRITTEN
INSTRUCTIONS.
3. INSTALL ISOLATION BALL VALVES @ ALL FIXTURE
WATER SUPPLY LINES.
4. CONTRACTOR TO VERIFY LOCATIONS OF EXISTING
UNDERGROUND UTILITIES BEFORE BEGINNING WORK.
5. CONTRACTOR SHALL DEMOLISH & REMOVE EXISTING
PIPING, FITTINGS, & EQUIPMENT AS REQUIRED FOR NEW
INSTALLATIONS. VALVE & CAP PIPING TO REMAIN.
6. FIELD VERIFY LOCATIONS OF EXISTING PIPING THAT
MAY CONFLICT WITH NEW CONSTRUCTION AND
RELOCATE AS NEEDED.
7. NOTIFY OWNER OF ANY PIPING DEMOLITION THAT MAY
AFFECT NORMAL OPERATION OF OTHER AREAS.
8. ALL FLOOR DRAINS TO BE EQUIPPED WITH TRAP
PRIMERS OR APPROVED TRAP SEALS.
9. 1% SLOPE FOR ALL SANITARY PIPING.
10. THE CONTRACTOR SHALL FIELD VERIFY THE SIZES,
LOCATION, ELEVATIONS, AND DETAILS OF ALL EXISTING
CONDITIONS THAT MAY AFFECT THE WORK.
11. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
MAINTAINING THE INTEGRITY OF ALL EQUIPMENT AND
MATERIALS IN A "NEW" CONDITION DURING
CONSTRUCTION.
12. ALL WORK SHALL BE PERFORMED BY LICENSED
CONTRACTORS AND SUBCONTRACTORS AS REQUIRED
BY LAW.
13. DESIGN AND CONSTRUCTION SHALL BE IN
ACCORDANCE WITH THE CODES AND REGULATIONS
ENFORCED BY LOCAL BUILDING OFFICIALS.
14. IF THERE IS CONFLICTING INFORMATION IN THE PLANS
OR SPECIFICATIONS THE MORE STRINGENT AND
GREATER COST ITEM SHALL BE USED.
15. DRAWINGS INDICATE REQUIRED SIZES AND POINTS OF
TERMINATION OF PIPES AND SUGGESTED ROUTES. IT IS
NOT INTENTION OF DRAWINGS TO INDICATE ALL
NECESSARY OFFSETS. INSTALL WORK IN MANNER TO
CONFORM TO STRUCTURE, AVOID OBSTRUCTIONS,
PRESERVE HEADROOM AND KEEP OPENINGS AND
PASSAGEWAYS CLEAR. DO NOT SCALE FROM
DRAWINGS.
16. ALL AREAS OF WORK MUST BE SECURED AND
INACCESSIBLE TO INMATES DURING CONSTRUCTION.
THE CONTRACTOR MUST SECURE EACH AREA OF WORK
AT THE END OF EACH SHIFT.
17. SHOWER SUPPLIER SHALL FIELD VERIFY THE EXISTING
HEIGHT, WIDTH, AND DEPTH FOR EACH SHOWER
CABINET LOCATION PRIOR TO SUBMITTING SHOP
DRAWINGS
GENERAL PLUMBING NOTES
MISCELLANEOUS NOTES
PLUMBING VALVES
POINT OF CONNECTION BETWEEN NEW AND
EXISTING
POINT OF EXISTING TO REMAIN AND EXISTING
TO BE REMOVED
INDICATES PLAN NOTE
INDICATES DEMOLITION NOTE
DETAIL BUBBLE
DETAIL NUMBER
PAGE LOCATION INDICATES
DIRECTION OF DETAIL SECTION
AD AREA DRAIN
ASR AUTOMATIC SPRINKLER RISER
BFS BELOW FLOOR SLAB
BWV BACK WATER VALVE
CB CATCH BASIN
CI CAST IRON
CO CLEAN OUT
CV CONTROL VALVE
DF DRINKING FOUNTAIN
DIA DIAMETER
DN DOWN
DWH DOMESTIC WATER HEATER
E.T.C. ELECTRICAL TRADES CONTRACTOR
EWC ELECTRIC WATER COOLER
EXIST EXISTING
FD FLOOR DRAIN
FC FINAL CONNECTIONS
FDC FIRE DEPT. CONNECTION
FF FINISH FLOOR
FHV FIRE HOSE VALVE
FT FEET
GAL GALLON
GD GARBAGE DISPOSAL
GI GREASE INTERCEPTOR
GPH GALLONS PER HOUR
GPM GALLONS PER MINUTE
HB HOSE BIB
HD HEAD (FT)
HP HORSE POWER
ID INSIDE DIAMETER
I.E. INVERT ELEVATION
LAV LAVATORY
LT LAUNDRY TRAY
MA MEDICAL AIR
MAX MAXIMUM
MGC MEDICAL GAS CONSOLE
MH MAN HOLE
MIN MINIMUM
MS MOP SINK
M.T.C. MECHANICAL TRADES CONTRACTOR
NTS NOT TO SCALE
ORD OVERFLOW ROOF DRAIN
OXY OXYGEN
P PUMP
PD PRESSURE DROP
PVC POLY-VINYL-CHLORIDE
RC RAIN CONDUCTOR
RD ROOF DRAIN
RI ROUGH-IN
REQ'D REQUIRED
SAN SANITARY
SHWR SHOWER
SK SINK
SP STAND PIPE
SQ. FT. SQUARE FEET
SS SERVICE SINK
ST STORM
S&W STOP & WASTE
STR STRAINER
SV STACKED VENT
TYP. TYPICAL
UR URINAL
VB VACUUM BREAKER
VS VENT STACK
V.F.D VARIABLE FREQUENCY DRIVE
VTR VENT THRU ROOF
W WASTE
WB WET BULB
WC WATER CLOSET
WH WALL HYDRANT
WS WASTE STACK
W&V WASTE AND VENT
X-CW EXIST. CW PIPING
ITEM
EXISTING
COLD WATER
COLD WATER BELOW FINISH SLAB
TEMPERED WATER
SANITARY WASTE
SANITARY WASTE BELOW FINISH SLAB
VENT PIPING
VENT PIPING BELOW FINISH SLAB
DEMOLITION
GATE VALVE
SOLENOID VALVE
FLOW DIRECTION
PIPING DROP
PIPING RISE
FLOOR CLEANOUT
INLINE PIPING DROP
INLINE PIPING RISE
PIPING TEE
PIPING ELBOW
INLINE CLEANOUT
PLUMBING TRAP
CONNECTION
FLOOR DRAIN & FLOOR SINK
PIPE CAP
PIPE BREAK
X
X
XX
XXXX
XX
XXXX
CW
CW
TW
SAN
SAN
V
V
PHASING NOTES
GENERAL INFORMATION:
A. EXISTING WATER SERVICE SHALL REMAIN ACTIVE AND
FUNCTIONAL DURING CONSTRUCTION. INDIVIDUAL RISERS CAN
BE SHUTDOWN AS NEEDED, COORDINATE WITH OWNER PRIOR
TO BRANCH SHUTDOWNS.
B. PHASING NOTES ARE INTENDED FOR GENERAL SEQUENCE OF
CONSTRUCTION. CONTRACTOR TO COORDINATE WITH
DRAWINGS FOR SPECIFIC DETAILS FOR DEMOLITION &
INSTALLATION OF ALL NEW EQUIPMENT, PIPING, AND
ACCESSORIES.
C. ALL RISER SHUTDOWNS TO BE CLOSELY COORDINATED WITH
THE OWNER.
D. ONLY ONE SET OF SHOWERS PER HOUSING UNIT SHALL BE
UPGRADED AT A TIME. SIX SHOWERS TO REMAIN IN SERVICE
AT ALL TIMES.
E. THE OWNER WILL PROVIDE A MAXIMUM OF 2 ESCORTS WITH
THE ANTICIPATION THAT WORK IN TWO DIFFERENT HOUSING
UNITS WILL BE HAPPENING SIMULTANEOUSLY.
F. FOR ALL HOUSING UNITS ON THIS PROJECT ONLY ONE
SET/PAIR OF SHOWERS CAN BE SHUT DOWN AND WORKED
ON AT ANY ONE TIME PER HOUSING UNIT, EXCEPT FOR
BIRCH. THE REMAINING THREE SETS/PAIRS OF SHOWERS
ARE TO BE FULLY OPERATIONAL. THE REPLACED SHOWERS
MUST BE FULLY INSPECTED, APPROVED, AND MADE
OPERABLE, BEFORE THE CONTRACTOR CAN MOVE TO THE
NEXT SET/PAIR OF SHOWERS TO BEGIN WORK.
G. CONTRACTOR TO BEGIN CONSTRUCTION IN HOUSING UNIT
BIRCH AS THE HOUSING UNIT IS CURRENTLY UNOCCUPIED.
G.A. HOUSING UNIT BIRCH IS UNOCCUPIED AT THE TIME OF
CONSTRUCTION, THE CONTRACTOR WILL HAVE
ACCESS AND THE ABILITY TO REPLACE ALL THE
SHOWERS AT ONE TIME.
X-ICON CONTROLLER
X-WOOD MOUNT
X-SOLENOID
VALVE (TYP.4)
X-1/2" TW
X-3/4" TW
X-3/4" TW
X-1/2" TW TO FIRST
FLOOR X-SHOWER
X-1/2" TW TO FIRST
FLOOR X-SHOWER
X-1/2" TW
X-1/2" TW UP TO
SECOND FLOOR
X-SHOWER
DEMOLISH EXISTING CONTROL
WIRING BACK TO ASSOCIATED
SHOWER BUTTON (TYP.4)
ICON CONTROLLER
X-WOOD MOUNT
SOLENOID
VALVE (TYP.4)
X-1/2" TW
X-3/4" TW
X-1/2" TW UP TO
SECOND FLOOR
X-SHOWER
X-3/4" TW
X-1/2" TW TO FIRST
FLOOR X-SHOWER
X-1/2" TW TO FIRST
FLOOR X-SHOWER
X-1/2" TW
EXTEND I-CON CONTROL
WIRING TO ASSOCIATED
SHOWER BUTTON (TYP.4)
SCALE: NTS
I-CON CONTROLLER SYSTEM PIPING
DETAIL - BUILDINGS ASPEN, BIRCH,
CEDAR, MAPLE, PINE - NEW
SCALE: NTS
SOLENOID
VALVE (TYP.4)
1/2" TW TO FIRST
FLOOR SHOWER
1/2" TW TO SECOND
FLOOR SHOWER
1ST FLOOR
CEILING
CEILING
2ND FLOOR
I-CON CONTROLLER
(REFER TO SHEET P-400
& P-401 FOR LOCATIONS)
X-1" TW
X-1" TW
1" TW
1" TW
2ND FLR
MECHANICAL RM.
1ST FLR
MECHANICAL RM.
EXTEND I-CON CONTROL
WIRING TO ASSOCIATED
SHOWER BUTTON (TYP.4)
I-CON CONTROLLER SYSTEM
PIPING DETAIL - SPRUCE - NEW
SCALE: NTS
I-CON CONTROLLER SYSTEM PIPING
DETAIL - BUILDINGS ASPEN, BIRCH,
CEDAR, MAPLE, PINE - DEMOLITION
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y R ev ie w D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
JL
H
PL
U
M
BI
N G
SY
M
BO
LS
AB
BR
EV
IA
TI
O
N S
N
O
TE
S
BR
H
P-
X-FD
X-1" TW UP AND DN
X-1" CW UP AND DN
X-4" SAN
UP AND DN
X-FD X-FD
X-1" TW
X-1/2" TW X-1/2" TW
1 1
X-FD
X-FD X-FD
X-1" TW UP AND DN
X-2" V UP
X-4" SAN
UP AND DN
X-2" CW UP
X-1" CW UP AND DN
X-1" TW
X-1" TW UP AND DN
X-1" CW UP AND DN
X-4" SAN DN
X-3" VTR
X-MS
X-FDX-FD 1
X-3/4" TW
X-1/2" TW
X-FDX-FD
X-MS
X-1" TW UP AND DN
X-1" CW UP AND DN
X-4" SAN UP
AND DN
X-2" V
X-3/4" TW
2 2
DEMOLITION NOTES
DISCONNECT, REMOVE, AND DEMO EXISTING FLOOR DRAIN. DEMO ASSOCIATED
SANITARY PIPING BACK AS REQUIRED TO CONNECT TO NEW SHOWER DRAIN.
DISCONNECT, REMOVE, AND DEMO EXISTING SHOWER HEAD AND TEMPERED
WATER CONTROLS. DEMO TEMPERED WATER PIPING BACK TO LOCATION SHOWN.
DEMO TEMPERED WATER SUPPLY PIPING BACK TO LOCATION SHOWN.
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
P-
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA A - PLUMBING DEMOLITION N
SECOND FLOOR PLAN - BUILDING SPRUCE -
AREA B - PLUMBING DEMOLITION
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA C - PLUMBING DEMOLITION N
SECOND FLOOR PLAN - BUILDING SPRUCE -
AREA D - PLUMBING DEMOLITION
FL
O
O R
P
LA
N
BU
IL
D
IN
G
SP
R U
C E
- P
LU
M
BI
N G
D
EM
O
LI
TI
O
N
JL
H
BR
H
X-3/4" TW
X-1/2" TW
X-1/2" TW UP
X-FDX-FD
X-FD
X-FD
X-3" SAN UP
AND DOWN
X-3" V UP
AND DN
X-1/2" TW
P100X-I-CON SYSTEM
CONTROLLER
X-1/2" TW DN
X-3" SAN STACK
UP AND DOWN
X-3" V DN
X-FDX-FD
X-FD
X-FD
X-FD
X-FD
X-FD
X-3" SAN STACK
UP AND DOWN
X-3" V DN
X-1/2" TW DNX-1/2" TW UP
X-FD
X-FD
X-FD
X-3/4" TW DN
X-FD
X-3" SAN STACK
UP AND DOWN
X-3" V DN
X-1/2" TW
X-1/2" TW
P100
X-I-CON SYSTEM
CONTROLLER
DEMOLITION NOTES
DISCONNECT, REMOVE, AND DEMO EXISTING FLOOR DRAIN. DEMO ASSOCIATED
SANITARY PIPING BACK AS REQUIRED TO CONNECT TO NEW SHOWER DRAIN.
DISCONNECT, REMOVE, AND DEMO EXISTING SHOWER HEAD, I-CON SYSTEM
CONTROL BUTTON, SOLENOID VALVES, AND ASSOCIATED I-CON SYSTEM
CONTROLLER. DEMO EXISTING TEMPERED WATER SUPPLY PIPING BACK AS
REQUIRED FOR NEW SHOWER HEAD AND I-CON SYSTEM CONTROL BUTTON.
DISCONNECT, REMOVE, AND DEMO EXISTING FLOOR DRAIN. DEMO EXISTING
SANITARY PIPING BACK AS REQUIRED FOR NEW FLOOR DRAIN.
DISCONNECT, REMOVE, AND DEMO EXISTING MOP SINK AND ASSOCIATED FAUCET.
DEMO BACK EXISTING TEMPERED WATER AND SANITARY PIPING AS REQUIRED TO
EXTEND AND CONNECT TO NEW MOP SINK AT LOCATION SHOWN ON SHEET P-401
PINE-A. SALVAGE AND RELOCATE EXISTING MOP RACK TO NEW MOP SINK
LOCATION.
X-3/4" TW
X-1/2" TW
X-1/2" TW UP
X-FDX-FD
X-FD
X-FD
X-3" SAN UP
AND DOWN
X-3" V UP
AND DN
X-1/2" TW
P100X-I-CON SYSTEM
CONTROLLER
X-MS
X-3/4" TW DN
X-TW X-CW UP
AND DN
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
P-
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
JL
H
BR
H
FL
O
O R
P
LA
N
BU
IL
D
IN
G S
BI
R
C H
, M
AP
LE
(A
LT
PI
N E(
AL
T
1)
PL
U
M
BI
N G
D
EM
O
LI
TI
O
N
FIRST FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA C - PLUMBING DEMOLITION
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA D - PLUMBING DEMOLITION
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA B - PLUMBING DEMOLITION
FIRST FLOOR PLAN - BUILDINGS BIRCH & MAPLE - AREA A -
PLUMBING DEMOLITION
N N
N N N
N N N
NN N N
SCALE: 1/4" = 1'-0"
0 1 5 10
FIRST FLOOR PLAN - BUILDING PINE -
AREA A - PLUMBING DEMOLITION
N
BIRCH MAPLE
(ALT 1)
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
PINE
(ALT 1)
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
X-FD
X-1" TW UP AND DN
X-1" CW UP AND DN
X-4" SAN
UP AND DN
1/2" TW
1" TW
P100
SHOWERSHOWER
X-FD
X-1" TW UP AND DN
X-2" V UP
X-4" SAN
UP AND DN
X-2" CW UP
X-1" CW UP AND DN
1/2" TW
1" TW
P100
SHOWER SHOWER
X-1" TW UP AND DN
X-1" CW UP AND DN
X-4" SAN DN
X-3" VTR
X-MS
1" TW
P100
SHOWER
X-MS
X-1" TW UP AND DN
X-1" CW UP AND DN
X-4" SAN UP
AND DN
X-2" V
1" TW
P100
SHOWER
1/2" TW
1/2" TW4
PLUMBING KEY NOTES
MODIFY EXISTING SHOWER SANITARY PIPING AS REQUIRED TO CONNECT TO NEW
SHOWER DRAIN. CONTRACTOR TO COORDINATE EXISTING DRAIN LOCATION WITH
MANUFACTURER PRIOR TO ORDERING.
ROUTE NEW 1/2" TEMPERED WATER PIPING AS SHOWN TO CONNECT TO NEW
SHOWER HEAD/CONTROLS PER THE MANUFACTURERS INSTALLATION
INSTRUCTIONS.
INSTALL NEW I-CON SYSTEM CONTROLLER (NEXUS X12 4, 4 SHOWER CONTROLLER,
STANDALONE) AND ASSOCIATED SOLENOID VALVES IN LOCATION SHOWN.
ROUTE NEW 1/2" TEMPERED WATER PIPING AS SHOWN TO CONNECT TO EXISTING
TEMPERED WATER PIPING.
GENERAL NOTES
1. REFER TO ARCHITECTURAL PLANS FOR SHOWER SPECIFICATIONS.
2. CONTRACTOR TO PURCHASE SHOWER ENCLOSURES, SOLENOID VALVES,
CONTROLLERS, SHOWER BUTTONS, AND SHOWER HEADS FROM I-CON.
3. MODIFY THE EXISTING SPRINKLER PIPING PER NFPA 13 AS REQUIRED TO
ACCOMMODATE NEW DUCTWORK, DOMESTIC WATER PIPING, LIGHTING, AND
CEILING.
4. VERIFY EXISTING DRAIN LOCATIONS TO ENSURE THEY WILL ALIGN WITH THE
FLOOR DRAINS IN THE NEW SHOWER CABINETS.
5. EXISTING MASTER MIXING VALVE IN MECHANICAL ROOM IS A SYMMONS 7
7000 TEMPCONTROL (ASSE 1017 & CSA B125.3-12 RATED).
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
P-
FL
O
O R
P
LA
N
BU
IL
D
IN
G
SP
R U
C E
- P
LU
M
BI
N G
N
EW
JL
H
BR
H
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA A - PLUMBING NEW
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
N
SECOND FLOOR PLAN - BUILDING
SPRUCE - AREA B - PLUMBING NEW
N
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA C - PLUMBING NEW N
SECOND FLOOR PLAN - BUILDING
SPRUCE - AREA D - PLUMBING NEW
X-3/4" TW
X-1/2" TW
X-1/2" TW UP
X-FD
X-3" SAN UP
AND DOWN
X-3" V UP
AND DN
X-1/2" TW
FD-1
SHOWER
P100
X-1/2" TW DN
X-3" SAN STACK
UP AND DOWN
X-3" V DN
X-FD
1 1
FD-1
SHOWER
X-3" SAN STACK
UP AND DOWN
X-3" V DN
X-1/2" TW DN
FD-1
SHOWER
X-1/2" TW UPX-3/4" TW DN
X-FD
X-3" SAN STACK
UP AND DOWN
X-3" V DN
X-1/2" TW
X-1/2" TW
FD-1
SHOWER
P100
PLUMBING KEY NOTES
MODIFY EXISTING SHOWER SANITARY PIPING AS REQUIRED TO CONNECT TO NEW
SHOWER DRAIN. CONTRACTOR TO COORDINATE EXISTING DRAIN LOCATION WITH
MANUFACTURER PRIOR TO ORDERING.
MODIFY EXISTING TEMPERED WATER PIPING AS REQUIRED TO CONNECT TO NEW
SHOWER HEAD.
INSTALL NEW I-CON SYSTEM CONTROLLER (NEXUS X12 4, 4 SHOWER CONTROLLER,
STANDALONE) IN LOCATION SHOWN.
MODIFY EXISTING SANITARY PIPING AS REQUIRED TO INSTALL NEW FLOOR DRAIN
FLUSH WITH NEW FLOORING AT LOCATION SHOWN.
ROUTE NEW 1/2" TEMPERED WATER PIPING AS SHOWN TO CONNECT TO NEW
SHOWER HEAD/CONTROLS PER THE MANUFACTURERS INSTALLATION
INSTRUCTIONS.
INSTALL NEW MOP SINK AND SALVAGED MOP RACK AT LOCATION SHOWN.
CONNECT NEW FAUCET TO 1/2" TEMPERED WATER AND 1/2" COLD WATER.
EXTEND AND CONNECT 1/2" COLD WATER TO EXISTING COLD WATER PIPE IN
MECHANICAL CLOSET ROOM.
GENERAL NOTES
1. REFER TO ARCHITECTURAL PLANS FOR SHOWER SPECIFICATIONS.
2. CONTRACTOR TO PURCHASE SHOWER ENCLOSURES, SOLENOID VALVES,
CONTROLLERS, SHOWER BUTTONS, AND SHOWER HEADS FROM I-CON.
3. MODIFY THE EXISTING SPRINKLER PIPING PER NFPA 13 AS REQUIRED TO
ACCOMMODATE NEW DUCTWORK, DOMESTIC WATER PIPING, LIGHTING, AND
CEILING.
4. VERIFY EXISTING DRAIN LOCATIONS TO ENSURE THEY WILL ALIGN WITH THE
FLOOR DRAINS IN THE NEW SHOWER CABINETS.
5. EXISTING MASTER MIXING VALVE IN MECHANICAL ROOM IS A SYMMONS 7
7000 TEMPCONTROL (ASSE 1017 & CSA B125.3-12 RATED).
X-3/4" TW
X-1/2" TW
X-1/2" TW UP
X-FD
X-3" SAN UP
AND DOWN
X-3" V UP
AND DN
X-TW X-CW UP
AND DN
FD-1
SHOWER
P100
1/2" TW
MS-1 6
1/2" TW
1/2" CW
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
2/
0.
JB
B
AR
C
H
IT
EC
TS
EN
G
IN
EE
R S
M A
T R
I X
SH
O
W
ER
R
EN
O
VA
TI
O
N S
AL
G
ER
C
O R
R
EC
TI
O
N
AL
F
AC
IL
IT
Y wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
R ev ie w
D
AT
E
/1
4/
PL
AN
R
EV
IE
W S
ET
/2
1/
BI
D S
ET
P-
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
SCALE: 1/4" = 1'-0"
0 1 5 10
JL
H
BR
H
FL
O
O R
P
LA
N
BU
IL
D
IN
G S
BI
R
C H
, M
AP
LE
(A
LT
PI
N E(
AL
T
1)
PL
U
M
BI
N G
N
EW
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE,
PINE - AREA B - PLUMBING NEW
FIRST FLOOR PLAN - BUILDINGS BIRCH & MAPLE - AREA A -
PLUMBING NEW
FIRST FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA C - PLUMBING NEW
SECOND FLOOR PLAN - BUILDINGS BIRCH, MAPLE, PINE -
AREA D - PLUMBING NEW
N N
N N N
N N N
N N N
FIRST FLOOR PLAN - BUILDING
PINE - AREA A - PLUMBING NEW
SCALE: 1/4" = 1'-0"
0 1 5 10
BIRCH MAPLE
(ALT 1)
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
PINE
(ALT 1)
BIRCH MAPLE PINE
(ALT 1) (ALT 1)
NEW 12" x 12" OPENING
IN ROOF. REFER TO DETAIL
5/D-200. 8" x 12" OPENING
FOR EXHAUST DUCT WORK
TO FIRST FLOOR.
NEW 12" x 12" OPENING
IN ROOF.REFER TO DETAIL
5/D-200. 8" x 12" OPENING
FOR EXHAUST DUCT WORK
TO FIRST FLOOR.
NEW 8" x 12" OPENING
IN FLOOR ABOVE. REFER
TO DETAIL 5/D-200NEW 8" x 12" OPENING
IN FLOOR ABOVE. REFER
TO DETAIL 5/D-200
D-100
SECOND FLOOR PLAN - BUILDINGS ASPEN, BIRCH,
CEDAR, MAPLE, PINE - AREA B - DEMO PLAN 4
D-100
SECOND FLOOR PLAN - BUILDINGS ASPEN, BIRCH,
CEDAR, MAPLE, PINE - AREA D - DEMO PLAN
D-100
FIRST FLOOR PLAN - BUILDINGS ASPEN, BIRCH,
CEDAR, MAPLE, PINE - AREA A - DEMO PLAN 3
D-100
FIRST FLOOR PLAN - BUILDINGS ASPEN, BIRCH,
CEDAR, MAPLE, PINE - AREA C - DEMO PLAN
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
EN
G
IN
EE
R S
R ev ie w
D
AT
E
SH
O W
ER
R
EN
O
VA
TI
O N
S
AL
G
ER
C O
R R
EC
TI
O N
AL
F
AC
IL
IT
Y
/2
1/
BI
D S
ET
D-100
M A
T R
I X
FA
X:
(5
) 4
-2
PH
O N
E:
(5
) 4
-2
LA
N
SI
N
G , M
I 4
E
. C
ES
AR
C
H
AV
EZ
A
VE
ad m in is tra to r@ m at rix ce in c.
co m M at rix
P ro je ct
N o.
.0
N
WC
H wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
D-200
SECOND FLOOR PLAN - BUILDING SPRUCE -
AREA 'B' - HVAC NEW
D-200
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA 'C' - HVAC NEW
D-200
FIRST FLOOR PLAN - BUILDING SPRUCE -
AREA 'A' - HVAC NEW
D-200
SECOND FLOOR PLAN - BUILDING SPRUCE -
AREA 'D' - HVAC NEW
NEW 10" x 10" OPENING
IN FLOOR ABOVE. REFER
TO DETAIL 5/D-200
NEW 12" x 12" OPENING
IN ROOF. REFER TO DETAIL
5/D-200
NEW 8" x 12" OPENING
IN FLOOR. REFER TO DETAIL
5/D-200
NEW 8" x 12" OPENING
IN FLOOR ABOVE. REFER
TO DETAIL 5/D-200
NEW 10" x 10" OPENING
IN FLOOR. REFER TO DETAIL
5/D-200
NEW 12" x 12" OPENING
IN ROOF. REFER TO DETAIL
5/D-200
ERECTOR NOTE:
DO NOT OVER CUT CORNERS. EXACT LOCATION OF
OPENINGS IS FLEXIBLE. LOCATE IN OPEN CELLS OF
PRECAST PLANK TO MINIMIZE THE AMOUNT OF REBAR
AND WEB MATERIAL TO BE CUT. DRILL SMALL DIAMETER
PILOT HOLE IN EXISTING CONCRETE TO FIND OPEN CELL
LOCATIONS.
D-200
SECTION
CORRECT
INCORRECT
NEW OPEING
NEW OPEING
JC
/E
N G
B Y
IN
D
EX
PC
A
D R
AW
N
B Y
D
ES
IG
N
ED
B
Y
D E
P A
R T
M E
N T
O F
T E
C H
N O
L O
G Y
M
A N
A G
E M
E N
T A
N D
B U
D G
E T
S T
A T
E O
F M
IC
H
IG
A
N
A D
A M
P L
A C
H R
A N
C A
R B
D
IR
E
C T
O R
S T
A T
E F
A C
IL
IT
IE
S
A D
M
IN
IS
T
R A
T
IO
N
D E
S
IG
N A
N D
C O
N S
T R
U C
T
IO
N D
IV
IS
IO
N
PR
O
JE
C
T D
ES
C
R
IP
TI
O
N
PR
O
JE
C T
N O
EN
G
IN
EE
R S
R ev ie w
D
AT
E
SH
O W
ER
R
EN
O
VA
TI
O N
S
AL
G
ER
C O
R R
EC
TI
O N
AL
F
AC
IL
IT
Y
/2
1/
BI
D S
ET
D-200
M at rix P ro je ct N o.
.0
FA
X:
(5
) 4
-2
PH
O N
E:
(5
) 4
-2
LA
N
SI
N
G , M
I 4
E
. C
ES
AR
C
H
AV
EZ
A
VE
ad m in is tra to r@ m at rix ce in c.
co m
M A
T R
I X
N
WC
H wing 'A' wing 'C'
LOWER LEVEL
wing 'B' wing 'D'
UPPER LEVEL
| Sheets and Views |
| Alger Shower_CDs-Legend G001 |
| Alger Shower_CDs-Schedule G002 |
| Alger Shower_CDs-Spruce Demo 101 |
| Alger Shower_CDs-Cedar Demo 102 |
| Alger Shower_CDs-Spruce Floor 103 |
| Alger Shower_CDs-Cedar Floor 104 |
| Alger Shower_CDs-Pine A - 105 |
| Alger Shower_CDs-Spruce RCP 106 |
| Alger Shower_CDs-Cedar RCP 107 |
| Alger Shower_CDs-Pine A RCP 108 |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .