- Change Order Notice I-18-4700 Design Corridor Manager Services DCM -EOWA Corridor IL RTE 390/I-490
- Solicitation number
- 26-557THA-ENGCO-B-51603
- Issued by
- Cook County, Illinois
About this file
This is a Change Order Notice issued by the Illinois State Toll Highway Authority (THA) through the Chief Procurement Office for General Services regarding contract I-18-4700 with Jacobs Engineering, Inc. The contract provides Design Corridor Management (DCM) services for the Elgin O'Hare Western Access (EOWA) corridor. The scope of work encompasses coordination and management of design contracts, land acquisition coordination, survey, environmental permitting, tolling implementation coordination, utility coordination, specialized aviation engineering services, design phase agency coordination with local, state, and federal partners, Federal Environmental Impact Statement (EIS) and Major Projects documentation, budget and funding coordination, document control, and cost and schedule tracking. The additional work is germane to the original contract and within project limits, with continued DCM services necessary to oversee design and provide agency coordination and technical support through design completion.
The original contract was solicited under PSB 18-4 on Illinois Procurement Bulletin number 22043022 and approved by the Tollway Board on April 18, 2019 via Board Resolution number 21788 for $29,500,000.00. A first supplement approved on May 25, 2023 increased the contract by $6,500,000.00 for a revised contract amount of $36,000,000.00. This second supplement increases the contract by $4,417,000.00, resulting in a total contract authorization of $40,417,200.00. The increase is necessary due to schedule and timing considerations resulting from ongoing construction and coordination with third parties including Union Pacific Railroad, Canadian Pacific Railway, petrochemical companies, Cook County, Chicago Department of Aviation, and the Federal Aviation Administration. A different procurement method is not recommended because the current team possesses institutional knowledge and established relationships with the FAA and CDA critical for completion of remaining work, and corridor design guidelines, agency coordination records, program administration, and document control procedures have already been developed under the original contract.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Please wait...
If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.
You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.
For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.
Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.
Change Order Notice Chief Procurement Office for General Services Change Order Notice v.23.1 44 Ill. Adm. Code 1.1525(g) requires notice of renegotiated contracts and change orders that increase the cost of a contract by more than $10,000 or the time of completion by a total of 30 days or more to be posted on the Bulletin/BidBuy for 14 days.
This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.
Detailed explanation for this change order:
11.0.0.20130303.1.892433.887364
| DropDownList1: THA - Toll Highway Authority |
| ProcurementTitle: I-18-4700, Elgin O'Hare Western Access, Design Corridor Management Services |
| BBREFNO.: 26-557THA-ENGCO-B-51603 |
| thedetails: The Illinois State Toll Highway Authority is giving notice to supplement contract I-18-4700 with Jacobs Engineering, Inc. This contract provides Design Corridor Management (DCM) services for the Elgin O'Hare Western Access (EOWA) corridor. The scope of work includes coordination and management of design contracts, land acquisition coordination, survey, environmental permitting, tolling implementation coordination, utility coordination, specialized aviation engineering services, design phase agency coordination with local, State and Federal partners, Federal Environmental Impact Statement (EIS) and Major Projects documentation, budget and funding coordination, document control, and tracking of cost and schedules. The contract is being amended to continue to provide desig corridor management services per the contract. The additional work is germane to the original project and within project limits. |
The original contract was solicited on PSB 18-4 on Illinois Procurement Bulletin number 22043022 and approved by the Tollway Board on April 18, 2019 via Board Resolution number 21788 for $29,500,000.00. A first supplement was approved on May 25, 2023 to increase the contract by $6,500,000.00 for a revised contract amount of $36,000,000.00. This second supplement increases the contract by $4,417,000.00, resulting in a total contract authorization of $40,417,200.00.
The existing contract is being amended to provide additional services. A different method for procurement is not recommended because the current team has institutional knowledge and established relationships with the FAA and CDA both of which are critical for completion of the remaining work. Corridor design guidelines, agency coordination records, program administration, and document controls procedures have already been developed under the original contract.
Additional design corridor management services are needed that was not anticipated in the current contract due to schedule and timing considerations resulting from ongoing construction and coordination with third parties including Union Pacific Railroad (UP), Canadian Pacific Railway (CP), petrochemical companies, Cook County, Chicago Department of Aviation, and the Federal Aviation Administration. Continued DCM services are necessary to oversee design and provide agency coordination and technical support through design completion.