4475 Change Order Notice V.25.1.09042026.pdf

PDF 1 MB Posted

Attached to
CHANGE ORDER NOTICE I-19-4475 Widening over CSX and B OCT Railroad Bridge and I-57 Restriping
Solicitation number
27-557THA-ENGCO-B-53876
Issued by
Illinois

About this file

This is a Change Order Notice issued by the Chief Procurement Office for General Services of the Illinois Toll Highway Authority (THA) for Amendment I-19-4475, I-57 Widening over CSX and B&O CT Railroad Bridges and I-57 Restriping project. The original construction contract was advertised on February 11, 2021, with bids received on March 23, 2021. The contract was awarded to Dunnet Bay Construction Co. on April 22, 2021, via Tollway Board Resolution 22229 in the amount of $20,793,926.70. The contract is currently set to expire on October 28, 2026. The change order requests a one-year amendment extension to accommodate contractor claim processing and potential resulting payments, with no additional funds required.

The project has experienced multiple delays throughout execution, including differing site conditions, utility delays, permit delays, right of way delays, coordination with an adjacent resurfacing construction contract, and an electrical maintenance transfer. The contractor has submitted a claim that is under review by the Construction Manager, Project Manager, Deputy Project Manager, and Claim Administrator. If the claim is found to have merit, an Authorization to Proceed (ATP), Change Order, and/or Extra Work Order will be processed, followed by payment through a pay estimate. The claim review and payment processing can require up to one year to complete. The contract is nearly closed out except for the pending claim, and the one-year amendment extension is necessary to allow sufficient time for full claim resolution and any associated payments.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Please wait...

If this message is not eventually replaced by the proper contents of the document, your PDF viewer may not be able to display this type of document.

You can upgrade to the latest version of Adobe Reader for Windows®, Mac, or Linux® by visiting http://www.adobe.com/go/reader_download.

For more assistance with Adobe Reader visit http://www.adobe.com/go/acrreader.

Windows is either a registered trademark or a trademark of Microsoft Corporation in the United States and/or other countries. Mac is a trademark of Apple Inc., registered in the United States and other countries. Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.

Change Order Notice Chief Procurement Office for General Services Change Order Notice V.25.1 Page of Notice of renegotiated contracts and change orders that increase the cost of a contract by more than $25,000 or the time of completion by a total of 180 days or more shall be posted on the Bulletin/BidBuy for 14 days.

This Change Order Notice provides detail as to why the change order is needed and, pursuant to Section 33E-9 of the Criminal Code, that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed or the change is germane to the original contract as signed. Change orders are defined by Section 1-15.12 of the Procurement Code and Section 1.2067 of the CPO-GS' Administrative Rules.

Detailed explanation for this change order:

11.0.0.20130303.1.892433.887364

CurrentPage:
PageCount:
DropDownList1: THA - Toll Highway Authority
ProcurementTitle: I-19-4475 I-57 Widening over CSX and B&OCT Railroad Bridges and I-57 Restriping
BBREFNO.: 27-557THA-ENGCO-B-53876
thedetails: This construction contract was advertised on 02/11/21, BidBuy# 21-557THA-ENGCO-B-20356. Bids were received on 03/23/21. The contract was awarded by the Tollway Board to Dunnet Bay Construction Co. on 04/22/21 via board resolution 22229 in the amount of $20,793,926.70.

Once a claim is submitted, it is reviewed by the CM, PM, DPM, and the Claim Administrator. If the initial claim is rejected, the contractor may choose to appeal.

In the event of an appeal, a formal claim meeting will be held with the Tollway, and any resulting outcomes will need to be evaluated. Depending on the nature of the claim, this may involve multiple Tollway reviewers, and due to the complexity of certain claims, the review process can take a considerable amount of time.

If the claim, or any portion of the claim, is found to have merit, an ATP will need to be processed, followed by a Change Order and/or an Extra Work Order. Once those documents are approved, the work can be processed and submitted on a pay estimate for payment. Based on the typical timelines associated with these steps, up to one year may be required to fully process the claim and any resulting payment.

The contract is nearly closed out, with the exception of the claim noted above. Several delays occurred throughout the course of the project, including differing site conditions, utility delays, permit delays, right of way delays, coordination with an adjacent resurfacing construction contract, and an electrical maintenance transfer.

The contract is set to expire on 10/28/26. A one-year amendment is requested as the contractor will be submitting a claim, and if there is merit, payment may need to be processed through the contract. No additional funds are required.

CheckBox1: 1
CheckBox2: 1

File details come from the government source that posted it. Updated .