This Invitation for Bids (IFB) 41684 is issued by the St. Johns River Water Management District for the Burrell Dam Rehabilitation project located on Haines Creek in Florida. The project involves comprehensive rehabilitation of an earth fill dam approximately 500 feet long and 12 feet high, including concrete surface preparation, repair and coating, structural steel repair and coating, gate repairs and seal replacement, electrical and controls installation, new fencing, riprap placement, and construction of a new control building. Contractor responsibilities encompass temporary cofferdam design and installation, dewatering, joint inspection with the District to determine repair scope, concrete repairs via hydro-demolition and patching, six gate refurbishments with new seals, new safety barriers and warning signs with solar lighting, new aluminum fencing, generator and propane tank installation, and site cleanup and demobilization. The non-mandatory pre-bid meeting is scheduled for November 19, 2025, at 10:00 AM. Questions must be submitted by December 8, 2025, at 5:00 PM, with bids due on December 17, 2025, at 10:00 AM. All work must be substantially completed with cofferdams removed by June 30, 2026, and fully completed by August 31, 2026. The contract term extends from the effective date through August 31, 2026, with an initial 155 calendar days allowed for substantial completion and an additional 60 calendar days for final completion.

Respondents must possess a current active General Contractor's license, have a minimum of five years of relevant experience, and have successfully completed at least one similar project in each of three categories: concrete and steel repairs (minimum $500,000), civil works projects (minimum $1,000,000), and electrical/instrumentation/controls (minimum $300,000), all completed within the past ten years. A bid bond of five percent of the total base bid must accompany the submittal. For contracts exceeding $200,000, payment and performance bonds equal to total compensation are required, with the surety rated no less than "Excellent" by A.M. Best Company. Respondents are limited to subcontracting no more than 40 percent of the work, with the remaining 60 percent performed by the contractor's own forces. The District has included a $250,000 Supplemental Work Allowance for unforeseen site conditions, with funds released only through written authorization. The District maintains the upstream water level during construction with discharge routed through Harris Bayou Structure and provides site access, permit coordination, and SCADA equipment reinstallation. Contractor must obtain all required federal, state, and local permits not obtained by the District and provide all necessary labor, equipment, materials, manatee observers, and wildlife trappers. Liquidated damages are assessed at $1,000 per calendar day for delays beyond the completion schedule. The District is exempt from Florida sales tax, and the contract is subject to funding availability from District ad valorem tax revenues, Florida Legislature appropriations, or other agency funding sources.

View the file

Other files

File Type Posted
IFB 41684_ Add_1_Final.pdf PDF
IFB 41684_ Add_2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB 41684 | Page 1 of 57

THE GOVERNING BOARD OF THE

ST. JOHNS RIVER WATER MANAGEMENT DISTRICT

INVITATION FOR BIDS

(IFB) 41684 BURRELL DAM REHABILITATION

The St. Johns River Water Management District (the “District”) is seeking bids (“Submittals”) from qualified, experienced Contractors for the Burrell Dam Rehabilitation project located on Haines Creek. The District intends to award a contract to one Contractor capable of delivering the services outlined in this solicitation.

A bid bond in the amount of five percent (5%) of the total base bid amount, must accompany Respondent’s Submittal.

Contractor shall begin the Work (defined herein) within 15 days of the Agreement effective date. The Effective Date is the date upon which the last party to the Agreement has dated and executed the same.

Interested, qualified Respondents are invited to submit a complete bid package in accordance with the requirements and specifications detailed in this solicitation. Submittals must address all elements of the Scope of Services and comply with the terms and conditions set forth herein.

Further information is available through DemandStar at demandstar.com, Vendor Registry at vendorregistry.com, Central Bidding at centralbidding.com, the state of Florida’s MyFloridaMarketPlace (MFMP) at myfloridamarketplace.com, or the District’s website at sjrwmd.com. Solicitation packages may be obtained from the above portals. Vendors may also request the solicitation package directly from the District.

For all requests or questions relating to this solicitation, please contact:

Kendall Siemiatkoski, Contracts Manager

Phone: 386-312-2324 or E-Mail: ksiemiat@sjrwmd.com

BID DUE DATE

10:00 a.m. Wednesday, December 17, 2025

LAST DAY FOR QUESTIONS – December 8, 2025; 5:00PM On site Non-mandatory PRE-BID MEETING - November 19, 2025: 10:00 AM

It is the responsibility of Respondents who receive this Solicitation from sources other than the portals identified above or St.

Johns River Water Management District to contact the District’s Procurement staff prior to the due date to ensure any updates/addenda are received in order to submit a responsible and responsive offer. If you fail to submit a complete and accurate document, the District may deem the offer non-responsive and reject your Submittal.

ADDENDA ACKNOWLEDGMENT: Prior to submitting my offer, I have verified that all addenda issued to date are considered as part of my offer:

Addendum No. Date Addendum No. Date Addendum No. Date

RESPONDENT NAME: ___________________________________________________________________________________________

STREET ADDRESS: _________________________________________________________________________________________

MAILING ADDRESS (IF DIFFERENT): __________________________________________________________________________

PRIMARY E-MAIL ADDRESS (required) _________________________________________________________________________

SECONDARY E-MAIL ADDRESS (required) ______________________________________________________________________

TELEPHONE: (______) _____________________________ YEAR COMPANY WAS ESTABLISHED _____________

NAME/TITLE OF PERSON SUBMITTING BID: ____________________________________________________________

SIGNATURE OF PERSON SUBMITTING BID: _____________________________________________________________

This document must be completed and returned with your Submittal

IFB 41684 | Page 2 of 57

INVITATION FOR BIDS

(IFB) 41684 BURRELL DAM REHABILITATION

SUBMITTAL ACKNOWLEDGMENT FORM

The undersigned, on behalf of the Respondent, hereby certifies and declares the following:

Authority to Bind: The individual signing this form is authorized to represent and legally bind the Respondent to the terms and conditions of the Invitation for Bids and the Submittal.

Commitment to Contract: If selected, the Respondent agrees to enter into an Agreement with the District based on the terms set forth in the solicitation documents, including the draft Agreement, Instructions to Respondents, all exhibits and attachments, addenda, certifications, affidavits, and the Submittal. The Respondent further agrees to provide all required goods and services in accordance with the stated timeline and to submit proof of the required insurance coverage.

Conflict of Interest: Except as disclosed in any attached addendum, no officer, employee, or agent of the District has any direct or indirect interest in the Respondent’s business or in any agreement that may result from this Submittal. The Respondent affirms that no such interest will exist throughout the term of any awarded Agreement.

Disclosure of Interested Parties: All individuals or entities with a significant interest in this solicitation, whether as principals or key participants in performing the Work, are listed in the form entitled Respondent’s Certificate as to the Entity’s Authority to do Business in Florida. No other party holds any interest in this solicitation or in any resulting Agreement.

Due Diligence: The Respondent affirms that it has reviewed and understands the attached draft Agreement and all related documents, including the specifications, addenda, and conditions related to this solicitation.

The Respondent acknowledges receipt of all issued addenda and confirms it is fully informed regarding the Work to be performed.

Fair Solicitation Submission: This Submittal is made independently, without collusion, connection, or agreement with any other person, company, or organization submitting on this solicitation. It is made in good faith and without any attempt to defraud.

By signing this form, I acknowledge I have read and understand, and my firm complies with all conditions and requirements set forth herein.

RESPONDENT NAME

AUTHORIZED REPRESENTATIVE DATE

PRINTED NAME

TITLE

IFB 41684 | Page 3 of 57

(IFB) 41684 BURRELL DAM REHABILITATION

TABLE OF CONTENTS

Cover Sheet ……….………………………………………………………………… Page 1

Submittal Acknowledgement Form …….…………………………………………. Page 2

Table of Contents …………………………………………………………………… Page 3

PART 1 - Scope of Services ………………………………………………………… Pages 4-5

Bid Form ….……………………………………………………………… Page 6

Required Documents & Forms …………………………………………... Pages 7-13 (NOTE! Additional documents not included in this section may be required)

BID SETS & SPECS (Separate Exhibits will be provided by district upon receipt of signed Non-Disclosure Agreement from Respondent)

EXHIBIT 1 - Burrell Dam As-Built Drawings dated 01/11/1977 prepared by Greiner Engineering Sciences, Inc.

EXHIBIT 2 - Burrell Dam Rehabilitation Civil/Structural Bid Drawings and Specifications dated 09/29/2025 prepared by SJRWMD EXHIBIT 3 - Burrell Dam Rehabilitation Electrical Bid Drawings and Specifications dated 05/19/2025 prepared by Black & Veatch EXHIBIT 4 - Florida Department of Environmental Protection General Permit No. 0462914-001 EXHIBIT 5 - U.S. Army Corps of Engineers Nationwide Permit (Anticipated to be issued prior to start of construction)

PART 2 – Submittal Guidance & General Information …….……………………… Pages 15-21

PART 3 – Draft Agreement …………………………………………………………. Pages 22-61

IFB 41684 | Page 4 of 57

PART 1 – SCOPE OF SERVICES

The St. Johns River Water Management District (the “District”) seeks a qualified Contractor, possessing a current and active General Contractor’s license, for work on the Burrell Dam Rehabilitation project on Haines Creek. Respondent must have a minimum of five (5) years of relevant experience, as described in this solicitation, with demonstrated project history, including descriptions and durations.

Respondent is required to have successfully completed a minimum of one (1) of each of the following similar project types listed hereto, within the last 10 years. (1) Concrete and Steel; (2) Civil Works; (3) Electrical, instrumentation and controls. Work listed for each similar project type must be from a different project, the same project cannot be listed more than once. The criteria for each project type is included in this solicitation under Similar Project Criteria.

All personnel, Subcontractors (defined herein), and agents assigned to the project must be properly trained and meet or exceed the specified qualifications. Respondents must submit a list of key individuals performing work, along with documentation of their experience, training, certifications, and licenses. Contractors must also comply with all applicable laws and provide proof of all required federal, state, and local licenses with their Submittal. If Respondent is doing business as a corporation, partnership, limited liability company or any business entity other than a sole proprietorship, the Respondent must be qualified by a properly licensed individual General Contractor, and the Respondent’s name must appear on the qualifying General Contractor’s license. All Subcontractors must be licensed in the area for which they perform work.

Respondent is limited to utilizing Subcontractors for no more than 40% of the work on the entire project. The remaining balance of the work on the project must be performed by Respondent’s own forces.

1.1 Introduction/Background

The St. Johns River Water Management District maintains the Burrell Dam located on Haines Creek, 900 feet upstream of State Road 44, between Lake Eustis and Lake Griffin, at approximate GPS coordinates of latitude 28°52'17.33"N, longitude 81°46'59.98"W. This location is about 2.3 miles downstream of Lake Eustis and 4.2 miles upstream of Lake Griffin. The drainage area is 648 square miles.

Burrell Dam is an earth fill dam approximately 500 feet long and 12 feet high with a reinforced concrete outlet structure that is approximately 92-ft. wide x 94-ft. long. The structure consists of an intake forebay which discharges into an eight-cell concrete box culvert. The six inside culvert cells are 8-ft wide x 8.5 feet high and the two outside cells are 8-

ft. wide x 6-ft. high. The forebay contains four 14-ft. wide x 4-ft. high overflow weir gates that are adjustable between elevation 60.0 to 64.0 feet NGVD. There are two 14-ft. wide x 5-ft. high vertical lift slide gates located on each side of the forebay. The invert for the two slide gates is 56.0 feet NGVD.

The original Burrell Dam was built by Lake County in 1956 and turned over to Southwest Florida Water Management District (SWFWMD) in 1964. A replacement dam was constructed in 1977 and has been owned and operated by the St.

Johns River Water Management District (District) ever since. This structure was designed to pass 2,350 cubic feet per second (cfs) with a headwater stage of 64.0 feet, NGVD. The structure is operated to maintain a desirable stage between 62.0-63.5 feet NGVD in Lake Eustis. Lakes Eustis, Harris, Dora, Carlton, and Beauclair are interconnected and are affected by the operation of Burrell Dam. Burrell Dam discharges can be affected by backwater from Lake Griffin.

1.2 Objectives

The objective of this project is to repair the damaged and aging concrete, repair and paint the steel components, repair six gates and replace seals, install new fencing, and miscellaneous site work. This work is necessary to ensure the operational readiness of Burrell Dam.

1.3 Scope of Work

Contractor shall provide all materials, labor, and equipment necessary for the rehabilitation of the Burrell Dam as described in this statement of work and as detailed in the contract drawings, specifications, and exhibits as provided (the “Work”). Generally, the scope shall include installing temporary cofferdams and dewatering, joint (District and Contractor) inspection of the structure to determine the extent of repairs required, concrete surface preparation, concrete surface patching, concrete crack repairs, concrete surface coating, surface preparation, repair and coating of structural steel and miscellaneous metals, repair six gates and replace seals, new fencing, new warning signs, placement and repair

IFB 41684 | Page 5 of 57 of riprap, and construction of a new control building with installation of existing control panels, new conduits, and new wiring. A new generator and propane tank will be installed by the Contractor for the new control building.

District Responsibilities:

1. Provide Contractor with access to the site with a temporary lock combination. Coordinate with Contractor on access restrictions or limitations.

2. Review pre-construction submittals within 15 business days of receipt of documents.

3. Maintain the upstream water levels during construction with discharge routed through the Harris Bayou Structure.

4. Coordinate reinstallation of all SCADA equipment associated with dam operations.

5. Attend pre-construction meeting and oversee all aspects of the construction.

Contractor Responsibilities:

1. Schedule a pre-construction meeting with District staff and submit a construction schedule at least 5 days before the meeting. Contractor shall include a reasonable amount of rain delays in the construction schedule and ensure adequate personnel and equipment are available to comply with the timeframes stated herein.

2. Following the pre-construction meeting, prepare and submit work plan and safety plan.

3. Close all construction and storage areas to the public and provide all safety and traffic control necessary for completing the project. Public access across the structure is prohibited. This includes supplying and maintaining barricades, fencing, temporary gates, debris screens, signage, and securing equipment and lay-down areas.

4. If necessary, Contractor shall coordinate with District staff to allow authorized vehicular access across the structure throughout most of the project duration. Notice shall be given by Contractor at least 48 hours in advance for any temporary closures and will be subject to approval by the District.

5. Contractor shall comply with the conditions contained in the following permits, which were obtained by the District: FDEP General Permit and U.S. Army Corp of Engineers (USACE) 404 Authorization and providing a manatee observer.

6. Contractor shall obtain any and all required permits not obtained by the District (NPDES, local government building permits and approvals, temporary power, etc.) for the construction of the project.

7. Contractor shall be responsible for supply of electric power and water needed to complete the Work.

8. Provide construction submittals to the District in a timely manner.

1.4 Task Identification/Equipment Specifications

Contractor shall provide all material, labor, and equipment required to complete the following tasks:

1. Mobilization

Mobilize all labor, equipment, and materials to the site. Establish on-site office and material staging areas.

2. Payment and Performance Bonds

A payment and performance bond equal to the Total Compensation is required for fixed price contracts greater than $200,000. Bonds shall be recorded in the public records of the county where the Work is located. A certified copy of completed and recorded bonds must be sent to the District prior to commencement of the Work. Bond premiums shall be paid by Contractor. Bonds shall be on the form provided by the District and written through a licensed agency that fulfills the requirements of §287.0935, Fla. Stat. The Surety executing a bond must be rated no less than "Excellent” for both financial strength and issuer credit, with a rating outlook of stable or positive for both and must have a financial size rating of VII or better according to the latest information available from A.M. Best Company, Inc.’s, rating and analysis web site.

IFB 41684 | Page 6 of 57

3. Site Prep/Protection and Utility Coordination

Contractor shall locate all utilities, including private lines, prior to digging, trenching, or excavation.

Contractor shall protect all utilities, existing structures, roads, benchmarks, monuments, and other improvements from damage whether or not shown on the drawings. Replacement cost for all damaged or disturbed items shall be borne by Contractor. Provide and maintain all safety, signage, fencing, and traffic control necessary.

4. Manatee Observer and Wildlife Trapper

Contractor shall review all manatee related permit conditions with all onsite project personnel and comply with all conditions. Contractor shall employ a manatee observer onsite during all in-water activities.

Contractor shall be responsible for contacting the District and the local Fish and Wildlife Conservation Commission (FWC) should any problem with nuisance animals arise. Contractor shall provide the services of an wildlife trapper certified by FWC when any laborers enter the water.

5. Erosion and Sediment Control

Supply, install, and maintain all erosion and sediment control and dust control measures, and conduct all construction operations in a manner that does not cause violations of state water quality standards. Provide all temporary erosion and sediment control measures (silt fence, turbidity barrier, temporary stabilization, etc.) as required for compliance with Federal, State, and local laws, rules, and regulations and as shown on the Exhibits.

6. Temporary Cofferdams

Contractor shall design and install the upstream and downstream cofferdams. The design shall be in accordance with applicable regulations and industry best practices to ensure worker safety and structural integrity and signed and sealed by a Florida licensed Professional Engineer. Upon completion of construction, Contractor shall remove the cofferdams.

For purposes of the USACE and FDEP permit application, the cofferdams are depicted as a sheet pile type.

Alternative types of cofferdams will be considered subject to District approval, provided that the environmental impacts are equal to or less than shown and that all permit requirements are satisfied.

Contractor shall monitor the water levels throughout the duration of the project and report to and coordinate with the District in the event water levels or anticipated weather events create alarm or rise to levels of concern. In the event that overtopping of the cofferdam is imminent, Contractor shall pump water into the work area to prevent scour at the base of the cofferdam.

7. Pumping/Dewatering

Provide the pumping means to remove water from the Work area as necessary for completion of the Work.

8. Remove and Store Manatee Screens

Remove the existing manatee screens from the dam forebay structure and store onsite for later reinstallation. Note: Due to the presence of overhead electrical lines, Contractor may need to de-energize the lines prior to removing the screens. If de-energized, Work shall be coordinated closely with the District flood control engineer, Matt Forhan. Power shall be restored promptly after the screens have been removed.

9. Remove and Store Electrical and Operations Control Panels

Disconnect power. Remove and store electrical and operations control panels from the existing control shed and outside panel at the dam structure. Save for later reinstallation. It should be noted that the overhead powerlines will need to stay energized throughout the project.

10. Remove all Electrical Components

Remove all existing electrical conduits and wiring running from the control shed to the dam gates including all electrical outlets located on the dam structure.

11. Remove Control Shed and Foundation

Remove and dispose of the wood frame control shed and foundation blocks.

IFB 41684 | Page 7 of 57

12. Remove Forebay Handrails

Remove and dispose of downstream handrails located at the dam forebay structure.

13. Remove Floating Safety Barriers and Support System

Remove and dispose of upstream and downstream floating safety barriers including concrete center posts and dam warning signs.

14. Removal of Sediment and Debris

Remove and dispose of all sediment and debris from the structure work area, as well as the upstream and downstream channels within the confines of the cofferdams to an offsite location. Disposal methods and location shall be in accordance with all applicable local, state, and federal regulations and requirements.

15. Remove Gates, Gate Frames, and Operators

Remove the dam weir and slide gates and all weir and gate framing/guides. Pressure wash all structural steel, gates, and gate operators. After pressure washing, the District Engineer, Bob Naleway, and/or delegates and Contractor shall perform a joint inspection to determine the full extent and scope of the repair work to each gate. Repair costs to be negotiated upon understanding of all repair work. Remove and replace all neoprene gate seals and bolts as specified on the drawings prior to reinstallation.

16. Replace Gate Operators

Replace all gear boxes, pedestals, linkages and other associated components related to gate operators. Install new gear boxes, pedestals, linkages and other associated components. If required, paint the pedestals and linkages the same color as the actuators.

17. Refurbish Gate Actuators

Refurbish six (6) L-120 actuators to include sandblasting the actuator, disassembly of the unit, thorough cleaning, detailed inspection of all components, reconditioning the motors with all new bearings, seals and leads and testing prior to installation. Reassemble and reinstall with all new gaskets, seals, lubricants, hardware and paint. This Task includes functional testing and detailed documentation in VALVEKEEP software. Replacement parts will be quoted separately (if required). Work shall include a 1-year warranty.

18. Concrete – Hydro-demolition of Eroded Surfaces

Remove deteriorated concrete by high pressure hydro-blasting or other District approved method to achieve a sound concrete surface. The areas to be hydro blasted are shown on the Exhibits (noted as areas requiring TAMMS structural mortar) to a depth of approximately 1/2 to 1 inch. The final extent of the hydro-demolition will be determined and approved by the District Engineer, Bob Naleway, during construction as required by the existing conditions encountered. Contractor shall prepare the concrete surface as specified prior to application of the concrete repair products.

Contractor shall arrange for, and provide, the services of the repair product manufacturer’s technical representative for this meeting to review and discuss the repair scope of work, techniques, and procedures.

19. Concrete – Pressure Washing Surfaces

Pressure wash all remaining concrete surfaces where hydro-demolition is not required. Generally, the areas to be pressure washed will depend upon the final extent of the hydro-demolition area as determined by the existing conditions encountered. Include power washing of embedded steel in this item.

20. Concrete – Isolated Patching (if required)

Identify and patch any isolated spalls with the specified repair products and provide moist curing as specified. Confirm areas to be patched with District Engineer prior to commencing repair work.

21. Concrete – Rebar Repair (if required)

Prepare the surface of exposed rebar and/or splice additional rebar as needed prior to patching. Confirm areas to be repaired with District Engineer, Bob Naleway, prior to commencing repair work.

IFB 41684 | Page 8 of 57

22. Concrete – Crack Repair (if required)

Identify and repair cracks with the specified repair products and provide moist curing as specified. Confirm areas to be repaired with District Engineer, Bob Naleway, prior to commencing repair work.

23. Concrete – Sawcutting

Prior to applying repair mortar, cut concrete along the top of the eroded concrete surface areas to allow for a smooth transition with the adjoining surface.

24. Concrete – Eroded Surface Repair

Apply the specified repair products to all areas where concrete surface is eroded including isolated spalls and areas where hydro-demolition occurred. Provide moist curing as specified.

25. Concrete – Testing Services

Contractor shall retain the services of an independent testing laboratory, approved by the District, for the sampling and testing of the repair mortar. The testing requirements shall be as specified on the drawings.

Test reports shall be signed and sealed by a Florida licensed professional engineer and submitted to the District.

26. Concrete – Surface Coating

Upon completion of all concrete repair work, apply the concrete surface coating to all exposed concrete surfaces as indicated on the drawings. Provide moist curing as specified.

27. New Safety Barrier Steel Piles

Supply and install the upstream and downstream safety barrier steel piles.

28. New Floating Safety Barriers

Supply and install the floating safety barriers by attaching to the two new center steel piles and to the four existing shoreline concrete posts. Provide all stainless-steel hardware for attaching to the piles and posts.

29. New Warning Signs

Supply and install the two new warning signs onto the new steel piles as detailed in the drawings. Attach all signs with stainless steel hardware.

30. New Warning Sign Solar Lights

Supply and install solar lights with stainless steel mounting hardware above the upstream and downstream warning signs.

31. New Solar Marine Beacon Lights

Supply and install solar beacons with stainless steel mounting hardware atop the upstream and downstream warning signs.

32. Sand Backfill and Compaction (if required)

Supply, install, and compact clean sand backfill as specified and directed by District to fill any scour areas.

33. Riprap – Geotextile (if required)

Supply and install geotextile under new riprap. Work under this item shall include access to the required placement areas.

34. Riprap – FDOT Bedding Stone (if required)

Supply and install bedding stone as required for the riprap installation. Work under this item shall include access to the required placement areas.

35. Riprap – FDOT Ditch Lining (if required)

Supply and install additional riprap erosion protection to the existing riprap areas as directed by the District. Work under this item shall include access to the required placement areas.

IFB 41684 | Page 9 of 57

36. Riprap – FDOT Bank and Shore (if required)

Supply and install additional riprap erosion protection to the existing riprap areas as directed by the District. Work under this item shall include access to the required placement areas.

37. FDOT No. 4 Aggregate

Supply and install aggregate behind the downstream wing walls as directed by the District.

38. New Precast Control Building Foundation

Excavate and place subgrade material for the new precast control building as specified and detailed on the drawings.

39. New Precast Control Building

Procure and install the precast concrete control building. The precast building is a delegated design, and Contractor is responsible for any required professional engineer’s certifications required by the local building authority.

Provide and install lightning protection system as shown in the electrical drawings and specifications by Black & Veatch (Exhibit 3).

40. Install New Electric Panels, Conduits, Wiring, and Outlets

Supply and install these items by a Florida licensed electrical contractor and as specified and detailed on the electrical drawings. Contractor is responsible for procuring an engineering and testing firm, acceptable to the Electrical Engineer, to conduct an Arc Flash Hazard analysis and submit a final report to the District, signed and sealed by a Florida licensed professional engineer.

Contractor shall procure an engineering and testing firm, acceptable to the Electrical Engineer, Black and Veatch, to conduct a Protective Device study and submit a final report to the District, signed and sealed by a Florida licensed professional engineer.

41. Propane Tank and Backup Generator

Supply and install the propane tank, including the concrete pad and anchor bolts. Supply and install the backup generator, including all electrical work and connection to the propane tank.

Propane tank and generator must be connected to the existing remote thermal unit (RTU#3) for remote monitoring as specified on the electrical drawings.

42. Reinstall Manatee Screens

Reinstall the existing manatee screens into the dam forebay structure.

43. Reinstall Dam Gates and Perform Dry and Wet Test Operation

Reinstall the dam weir and slide gates and perform dry test operation of the gates and operators, adjust as needed. Fill the forebay with water and test operation of the gates and operators under normal operating conditions, adjust as needed. After successful testing of the gates, remove the cofferdams.

44. New Aluminum Fencing

Supply and install the aluminum fence as detailed on the drawings. Provide all necessary hardware.

45. As-built Drawings and Survey

Contractor shall maintain a complete set of contract documents, including drawings and specifications at the job site clearly marked to reflect all as-built conditions. Upon completion of the project, Contractor shall submit these annotated drawings and specifications to the District. Contractor shall also submit an as-built site survey signed and sealed by a Florida licensed Professional Land Surveyor. Survey datum shall be NAVD 1988. An electronic (dwg and pdf) file and two hard copies are required.

46. Site Cleanup and Demobilization

Demobilize, clean site, and remove all erosion control measures. Restore final grading to original condition including grass. All erodible ground areas and slopes disturbed during construction shall be revegetated with sod, wetland species, or District approved alternate methods within 72 hours after completion of the construction activity. Contractor shall assume all responsibility for repairs to the utilities and other site

IFB 41684 | Page 10 of 57 improvements damaged during construction. Additionally, the Work will be considered complete only after all rubbish and unused material due to or connected with the Work has been removed and the premises left in a condition satisfactory to the District. All property disturbed or damaged during prosecution of the Work shall be restored to its former condition or better at no additional expense to the District. Final payment will be withheld until such cleanup is completed and approved by the District.

47. Daily Overflow Impact Fee

This item represents the maximum daily fee that Contractor will be allowed to charge the District (on a daily basis), in the event that water levels overtop the cofferdam. All costs associated with repair to any existing work affected by the cofferdam overflow, as well as work-related delays, must be included in this daily amount. The Total Compensation includes an amount for ten days of Daily Overflow Impact Fees.

This is an estimate and will be adjusted according to the actual number of days of overflow incurred. To be an authorized expenditure eligible for payment, the District must authorize the “Daily Impact Fee” either through issuance of a District Supplemental Instruction (DSI) form (for the first ten days of Daily Overflow Impact Fees) or Change Order (for any days after the first ten days of Daily Overflow Impact Fees). Contractor is not entitled to receive any unspent or remaining funds in the Daily Impact Fee item.

If at the completion of the Project, fewer than ten days of Daily Impact Fees have been approved by the District, then the remaining amounts allocated in the Schedule of Values for Daily Impact Fees shall be deducted from the Total Compensation.

48. Supplemental Work Allowance The District has included a SWA in the amount of $250,000 to cover Contractor activities not included in the Agreement (i.e., unforeseen site conditions or other unforeseen changes to the Work).

Escalation costs are not considered a compensable cost under this allowance. All escalation costs, if any, will be borne by Contractor. SWA Funds can only be released through issuance of a written and fully executed Supplemental Work Allowance Authorization form (Attachment C). Absent a written and fully executed Supplemental Work Allowance Authorization form, Contractor is not entitled to receive SWA funds.

1.5 Time Frames

1. All Work shall be complete, and the site demobilized in accordance with the plans and scope of work before August 31, 2026. Note the Dam structure shall be fully operational with cofferdams removed by June 30, 2026.

1.6 Insurance

Contractor shall maintain, at its sole expense, insurance coverage meeting the requirements of the Agreement (refer to Attachment D), including workers’ compensation in accordance with Chapter 440, Fla. Stat., commercial general liability insurance, and any additional coverage required by the District. Proof of such coverage shall be furnished prior to commencement of work and shall be maintained for the duration of the Agreement.

1.7 Bid Plans and Specs:

The Bid plans and specs (Exhibits to the solicitation) listed below will be available upon written request via email to the District Procurement staff member listed on the first page of this solicitation. The signed Non-Disclosure Agreement (included in this solicitation) must accompany the request.

Exhibit 1 - Burrell Dam As-Built Drawings dated 01/11/1977 prepared by Greiner Engineering Sciences, Inc Exhibit 2 - Burrell Dam Rehabilitation Civil/Structural Bid Drawings and Specifications dated 09/29/2025 prepared by SJRWMD Exhibit 3 - Burrell Dam Rehabilitation Electrical Bid Drawings and Specifications dated 05/19/2025 prepared by Black & Veatch Exhibit 4 - Florida Department of Environmental Protection General Permit No. 0462914-001 Exhibit 5 - U.S. Army Corps of Engineers Nationwide Permit (Anticipated to be issued prior to start of construction)

IFB 41684 | Page 11 of 57

NON-DISCLOSURE AGREEMENT

The undersigned is an employee, subconsultant, subcontractor, representative, or agent of ____________________________, a Respondent to St. Johns River Water Management District Invitation for Bid (IFB) No. 41684, Burrell Dam Rehabilitation Project. The Respondent intends to submit a bid to perform the work associated with the Burrell Dam Rehabilitation Project. The District possesses certain documents and materials related to this solicitation, as listed below.

1. Burrell Dam As-Built Drawings dated 01/11/1977 prepared by Greiner Engineering Sciences, Inc

2. Burrell Dam Rehabilitation Civil/Structural Bid Drawings and Specifications dated 09/29/2025 prepared by SJRWMD

3. Burrell Dam Rehabilitation Electrical Bid Drawings and Specifications dated 05/19/2025 prepared by

Black & Veatch

4. Florida Department of Environmental Protection General Permit No. 0462914-001

5. U.S. Army Corps of Engineers Nationwide Permit (Anticipated to be issued prior to start of construction)

A request for a copy of the above documents and materials may be submitted via email to Kendall Siemiatkoski at ksiemiat@sjrwmd.com.

The undersigned, in his or her capacity as an individual and as an employee, subconsultant, subcontractor, representative or agent of the Respondent seeks to acquire said documents and materials from the District in order to prepare the Respondent’s submittal, and signs this Non-Disclosure Agreement as a pre-requisite thereto.

In the course of reviewing the documents and materials, the undersigned will unavoidably come into contact with certain types of information which are protected from disclosure by Florida law. The undersigned acknowledges his/her familiarity with the applicable protections, including but not limited to his/her obligation to comply with the following:

Section 119.0725, Fla. Stat. (2024), which requires all District consultants to protect as confidential the following:

• Coverage limits and deductible or self-insurance amounts of insurance or other risk mitigation coverages acquired for the protection of information technology systems, operational technology systems, or data of the District;

• Information relating to critical infrastructure;

• Cybersecurity incident information; and

• Network schematics, hardware and software configurations, or encryption information or information that identifies detection, investigation, or response practices for suspected or confirmed cybersecurity incidents, including suspected or confirmed breaches, if the disclosure of such information would facilitate unauthorized access to or unauthorized modification, disclosure, or destruction of:

o Data or information, whether physical or virtual; or o Information technology resources, which include the District’s existing or proposed information technology systems.

Section 119.071, Fla. Stat. (2024), which requires all District consultants to protect as confidential the following:

• Records, information, photographs, audio and visual presentations, schematic diagrams, surveys, recommendations, or consultations or portions thereof relating directly to the physical security or fire safety of the facility or revealing security or fire safety systems;

• Threat assessments conducted by or for the District;

• Threat response plans;

• Emergency evacuation plans;

• Sheltering arrangements; and mailto:ksiemiat@sjrwmd.com

IFB 41684 | Page 12 of 57

• Manuals for security or fire safety personnel, emergency equipment, or security or fire safety training.

Section 119.071, Fla. Stat. (2024), which requires all District consultants to protect as exempt from public disclosure the following:

• Building plans, blueprints, schematic drawings, and diagrams, including draft, preliminary, and final formats, which depict the internal layout and structural elements of a building, arena, stadium, water treatment facility, or other structure owned or operated by the District.

• Said information may be disclosed to Company as part of its duties and responsibilities, and all persons in receipt of such information shall maintain its exempt status.

The undersigned (1) affirms he/she has undertaken to be familiar with the laws of Florida impacting the contemplated Work; (2) acknowledges that he/she may be subjected to penalties for violating Florida law in relation to the Respondent’s acquiring, possessing and reviewing the documents and materials, including disqualification of submittal and immediate termination of any contract with the District; (3) will not disclose the documents and materials outside Respondent’s Company and will hold same confidential; and (4) understands the restrictions outlined above. In consideration for the opportunity to participate in the solicitation process, the undersigned, on behalf of him/herself and Respondent, agrees to abide by the terms of this Non- Disclosure Agreement.

Respondent:

Company Name

Name:

Print Name of Individual Print Title/Role

Signature:

Signature of Individual Date

IFB 41684 | Page 13 of 57

BID FORM

ITEM

NO. DESCRIPTION ESTIMATED

QTY UNIT UNIT

PRICE TOTAL

1 MOBILIZATION 1 LS

2 PAYMENT & PERFORMANCE BONDS 1 LS

3 SITE PREP AND UTILITY COORDINATION 1 LS

4 MANATEE OBSERVER AND WILDLIFE TRAPPER 1 LS

5 EROSION AND SEDIMENT CONTROL 1 LS

6 TEMPORARY COFFERDAMS 1 LS

7 PUMPING/DEWATERING 1 LS

8 REMOVE AND STORE MANATEE SCREENS 1 LS

9 REMOVE AND STORE OPERATIONS CONTROL

PANELS 1 LS

10 REMOVE ALL ELECTRICAL COMPONENTS 1 LS

11 REMOVE CONTROL SHED AND FOUNDATION 1 LS

12 REMOVE FOREBAY HANDRAILS 1 LS

13 REMOVE FLOATING SAFETY BARRIERS AND

SUPPORT SYSTEM 1 LS

14 REMOVAL OF SEDIMENT AND DEBRIS 50 CY

15 REMOVE GATES, GATE FRAMES AND GATE

OPERATORS 6 EA

16 REPLACE GATE OPERATORS 6 EA

17 REFURBISH GATE ACTUATORS 6 EA

18 CONCRETE - HYDRODEMOLITION OF SURFACES 9,600 SF

19 CONCRETE - PRESSURE WASHING SURFACES 4,900 SF

20 CONCRETE - ISOLATED PATCHING (IF REQUIRED) 50 CF

21 CONCRETE - REBAR REPAIR (IF REQUIRED) 50 LF

22 CONCRETE - CRACK REPAIR (IF REQUIRED) 200 LF

23 CONCRETE - SAWCUTTING 250 LF

24 CONCRETE - ERODED SURFACE REPAIR 9,600 SF

25 CONCRETE - TESTING SERVICES 1 LS

26 CONCRETE - SURFACE COATING 14,500 SF

27 NEW SAFETY BARRIER STEEL PILES 80 LF

28 NEW FLOATING SAFETY BARRIERS 1 LS

29 NEW WARNING SIGNS 2 EA

30 NEW WARNING SIGN SOLAR LIGHTS 2 EA

31 NEW SOLAR MARINE BEACON LIGHTS 2 EA

32 SAND BACKFILL AND COMPACTION (IF REQUIRED) 60 TON

IFB 41684 | Page 14 of 57

BID FORM CONT’D

ITEM

NO. DESCRIPTION ESTIMATED

QTY UNIT UNIT

PRICE TOTAL

33 RIPRAP - GEOTEXTILE (IF REQUIRED) 360 SY

34 RIPRAP - FDOT BEDDING STONE (IF REQUIRED) 170 TON

35 RIPRAP - FDOT DITCH LINING (IF REQUIRED) 80 TON

36 RIPRAP - FDOT BANK AND SHORE (IF REQUIRED) 260 TON

37 FDOT NO. 4 AGGREGATE 4 TON

38 NEW PRECAST CONTROL BUILDING FOUNDATION 1 LS

39 NEW PRECAST CONTROL BUILDING 1 LS

40 INSTALL NEW ELECTRIC PANELS, CONDUITS,

WIRING, AND OUTLETS 1 LS

41 PROPANE TANK AND BACKUP GENERATOR 1 LS

42 REINSTALL MANATEE SCREENS 1 LS

43 REINSTALL DAM GATES AND PERFORM DRY AND

WET TESTS 1 LS

44 NEW ALUMINUM FENCING 330 LF

45 AS-BUILT DRAWINGS AND SURVEY 1 LS

46 SITE CLEANUP AND DEMOBILIZATION 1 LS

47 DAILY OVERFLOW IMPACT FEE 10 DAYS

48 SUPPLEMENTAL WORK ALLOWANCE 1 LS $250,000

TOTAL BID

PUBLIC RECORDS: Florida Statutes provide that sealed submittals or replies received by the District shall remain exempt from disclosure until an intended decision is announced or until 30 days from the opening, whichever is earlier. This means that Respondents will not be able to obtain a copy of their competitors’ Submittals until an intended decision is reached or 30 days has elapsed since the time of the Submittal opening.

UNIT PRICES: Unit prices on the Cost Schedule may be used to correct any extensions, and if adjusted, will be identified on the detailed tabulation as corrected. Unit costs will not be changed. If the Respondents fails to include a unit price and only includes the total, the District reserves the right to mathematically calculate the unit cost and enter to establish a price for the agreement and potential additional purchases of affected line items.

I HEREBY ACKNOWLEDGE, as Respondent’s authorized representative, that I have fully read and understand all terms and conditions as set forth in this IFB, and upon award, shall fully comply with such terms and conditions.

Name of Respondent Firm

Authorized Representative Signature Date

Printed Name/Title

IFB 41684 | Page 15 of 57

GENERAL QUALIFICATION QUESTIONNAIRE

Respondent’s Company/Firm Name ______________________________________________________________

Number of years engaged in business under the present company/firm name. ____________________________

Has Respondent previously been engaged in the same or similar business under another firm or trade name? If so, please describe each such instance.

Total number of years of company/firm experience performing similar work as described in this Solicitation.

Has Respondent ever been adjudicated bankrupt, initiated bankruptcy, or been the subject of bankruptcy proceedings on behalf of the current entity submitting this Bid or a prior entity that Respondent substantially operated or controlled? If yes, please describe the nature and result of those proceedings and the entity involved.

Describe the background/experience of the person or persons who will be primarily responsible for directing the Work that will be performed pursuant to this solicitation. This inquiry is intended to encompass the project manager and/or site manager who will be engaged on a daily basis in directing performance of the Work.

IFB 41684 | Page 16 of 57

SIMILAR PROJECTS CRITERIA

Respondent must have successfully completed a minimum of three (3) similar projects (“Similar Project(s)”) as described below. In addition to the identification of each Similar Project described below, each Similar Project must comply with the following criteria:

i. Each Similar Project listed below must have been successfully completed within the past ten (10) years as of the Submittal due date.

ii. Only where indicated, the Similar Project may have been completed by a Subcontractor named in the Proposed Subcontractor Form.

iii. For each Similar Project submitted, the Respondent must have held overall responsibility for the construction of the specific components identified for that project and must have self-performed the associated work. A Subcontractor may be listed under Similar Projects 1 and 3 to satisfy this requirement.

iv. If the Respondent (or, only where indicated, named Subcontractor) was not the prime contractor on the Similar Project, the “total project value” of the Similar Project shall be determined based upon the component of the Similar Project for which the Respondent or Subcontractor was responsible.

v. Each of the three (3) Similar Projects must be different projects; a project may not be listed more than once as a Similar Project.

Similar Projects 1 – Concrete and Steel: One Similar Project focused on repair and rehabilitation work on existing concrete and structural steel elements associated with dams, water control structures, locks, or bridges.

The total value of the repair and rehabilitation portion of the work of the Similar Project should cost no less than $500,000. This Similar Project should showcase the Respondent’s expertise in concrete and steel repair, as well as its ability to address unique challenges associated with these structures. This work may have been performed by a Respondent’s Subcontractor that is listed on the Proposed Subcontractors form herein.

Similar Project 2 – Civil Works: One Similar Project involving the construction of a civil works project consisting of one or more of the following types: bridges, major utility infrastructure, stormwater management, waterways, reservoirs, dams/levees, or use of temporary cofferdams for maintenance of a water control structure within a water body. The total project value must be no less than $1,000,000. This Similar Project should highlight the Respondent’s experience in managing and executing large-scale civil works projects, showcasing its ability to handle complex logistical challenges and adhere to strict safety and quality standards.

Similar Project 3— Electrical, Instrumentation and Controls: One Similar Project involving the knowledge and installation of electrical and operations control and actuators that operate equipment (manual and remote) and includes the necessary instrumentation and controls. the total project value must be no less than $300,000.

This Similar Project should highlight the Respondent’s experience in familiarity with electrical and controls components for the operation and monitoring of equipment and data. This work may have been performed by a Respondent’s Subcontractor that is listed on the Proposed Subcontractors form herein.

In determining whether a Respondent satisfies the minimum qualifications for similar projects, the District will not consider any additional projects or materials submitted by Respondent beyond the District-provided Similar Projects form.

IFB 41684 | Page 17 of 57

(IFB) 41684 BURRELL DAM REHABILITATION

SIMILAR PROJECTS / REFERENCES

Provide at least three (3) unique projects, similar in size and scope to the Work described in this solicitation, that your company has successfully completed within the last three (3) years. No more than one of the similar projects can be from a project completed for the District.

REFERENCE LETTERS from each project listed below, that answer completion time, manner and scope of work, and budget adherence, are required as part of your responsive submittal. Please ensure provided contact information is current.

If a District project is cited, do not contact District Staff for a reference, simply indicate District’s Contract Number for the similar project you are citing.

District reserves the right to determine whether or not a project shall be considered “similar”.

Similar Project #1 – Project Owner/Administrator:

Point of Contact: E-Mail:

Phone: Project Completion Date:

Project Name:

Describe how the scope of work meets the Concrete & Steel criteria:

Reference Letter included (required) -

Work performed by: Respondent Subcontractor Prime: Yes No Total Project Value

Similar Project #2 – Project Owner/Administrator:

Point of Contact: E-Mail:

Phone: Project Completion Date:

Project Name:

Describe how the scope of work meets the Civil Works criteria:

Reference Letter included (required) -

Work performed only by Respondent Prime: Yes No Total Project Value

Similar Project #3 – Project Owner/Administrator:

Point of Contact: E-Mail:

Phone: Project Completion Date:

Project Name:

Describe how the scope of work meets the Electrical, Instrumentation and Controls criteria:

Reference Letter included (required) -

Work performed by: Respondent Subcontractor Prime: Yes No Total Project Value

IFB 41684 | Page 18 of 57

(IFB) 41684 BURRELL DAM REHABILITATION

PROPOSED SUBCONTRACTORS

RESPONDENT NAME: _____________________________________________________________

Please list all Subcontractors to be used in connection with your performance of the Contract. The District reserves the right to accept or reject any Subcontractor based on past performance, location, or any other grounds that may conflict with the best interests of St. Johns River Water Management District. If Respondent intends to utilize the license of a Subcontractor to obtain any permit to perform the Work, the Subcontractor and license classification must be disclosed in this Proposed Subcontractor form. (Use additional pages, if necessary).

Note: Subcontractor Limitation Respondent is limited to utilizing Subcontractors for no more than 40% of the Work on the entire project. The remaining balance of the work on the project must be performed by Respondent’s own forces.

Check which applies:

Contractor will NOT utilize Subcontractors: ☐

Contractor will utilize the Subcontractors listed below: ☐

1. Name and address of Subcontractor:

Description of work to be performed:

Estimated % of workload/responsibility:

2. Name and address of Subcontractor:

3. Name and address of Subcontractor:

4. Name and address of Subcontractor:

IFB 41684 | Page 19 of 57

CERTIFICATE AS TO ENTITY’S AUTHORITY TO DO BUSINESS IN FLORIDA

The below entity is incorporated/organized/formed under the laws of the State of __________________; is authorized by law to respond to this solicitation and perform all work and furnish materials and equipment required under the Agreement and is authorized to do business in the State of Florida.

Entity name: __________________________________________________________________________________

Address: _____________________________________________________________________________________

Registration No: _______________________________________________________________________________

Registered Agent:…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .