41059 - SOW Underground Electrical and Communications Installation.pdf
PDF 216 KB Posted
- Solicitation number
- 41059
- Issued by
- Maricopa County, Arizona
About this file
This is a Scope of Work document for an underground electrical and communications installation project in Arizona. The project involves the installation of underground electrical service and communications infrastructure for a residential property. The contractor must provide comprehensive pricing that includes all equipment, materials, and labor necessary to complete the work. Key project components include supplying and installing a 2-inch rigid riser with no hub at a Square D SC3042M200SPH panel located at the front of the garage, excavating and installing a 2.5-inch DB-120 conduit trench spanning approximately 35 linear feet from the house service entrance to an existing APS wood power pole at the front of the property along Varney Road frontage, and excavating a 3-foot by 3-foot by 3-foot conduit pit at the APS power pole location. Additionally, the scope includes installing a 1-inch Schedule 40 communication conduit that will run approximately 35 feet in a shared trench with appropriate separation, with a stub-up from the house service entrance to an easement at the front, terminating at a 6-inch round junction box installed at grade level.
The contractor must be responsible for all trenching, backfill, and compaction operations using excavated soil, and must contact Arizona 811 prior to commencing any work to ensure utility locating is completed. The pricing structure requires contractors to include all conduit supply, connections, and backfill/compaction costs in their quote. No specific response dates, bid due dates, site visit requirements, bidders' conferences, award dates, contract terms, set-asides, or pricing terms are detailed in this Scope of Work document. Habitat will be responsible for installing the SES panel separately from this contractor's scope of work.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment A – Scope of Work
Lot: 41059 Address: 7958 W. Varney Road
Peoria, AZ. 85345
Service: Underground Electrical and Communications Installation
Summary: The contractor must provide pricing for the installation of underground electrical, and communications as outlined in the project description of the scope of work. The price must include all
| equipment, materials, and labor. | The | Contractor | will | be | responsible | for | contacting | Arizona | 811 | prior | to | any |
| work | being | started. |
Project Description: The project scope includes providing a quote for underground utility trenching, covering all conduit supply, connections, and backfill/compaction using excavated soil. (Habitat will install an SES panel on the house.) The SES panel is a Square D SC3042M200SPH located at the front of the garage. The contractor will need to supply a 2 1⁄2-inch rigid riser with no hub at the panel. The trench will extend from the house SES panel to the existing APS wood power pole at the front of the lot (Varney Road frontage), with a 2.5-inch DB-120 conduit spanning approximately 35 linear feet. A 3 ft x 3 ft x 3 ft conduit pit will be excavated at the APS power pole. Additionally, include 1 ft. of backfill separation for installing a 1-inch Schedule 40 communication conduit sharing a joint trench with APS. The 1-inch communication line will run approximately 35 ft., with a stub-up from the new house SES to the easement at the front, ending at a 6-inch round junction box installed at grade.
Please include a line item if shading with sand is necessary.
ROW APS easement is located at the front of the lot.
See attached – Marked Plot Plan (Sheet A1), site pictures, and power pole location. Distances are scaled from the plot plan; contractor to field verify.
Pricing to include:
| • APS | inspection | coordination | and | installation | of | flat | strap | for | APS. | ||||
| • Haul | off | all | Spoils | and | debris. | ||||||||
| • Compliance | with | all | M.A.G., | AZC, | City | of | Peoria, | APS, | and | Cox | Details | ||
| • Schedule | any | Required | Testing | and | inspections. | ||||||||
| • Proof | of | ROC | License | for | this | SOW | and | SAM.gov | certification. | ||||
| • Safety | Practices | Compliant | with | OSHA | standards, | protection, | and | shoring | equipment | ||||
| • Compliance | with | Maricopa | County | dust | control | practices, | providing | habitat, | and | maintaining | dust | control | log |
| sheets | on-site. | |||||||||||||
| • The | contractor | will | pull | any | required | permits | and | provide | their | own | required | TCP | and | barricades. |
Habitat will pull the Dust Control Permit and provide water meter access.
Work Sequencing and Phasing: Coordination of the project schedule will be determined with the Habitat for Humanity field superintendent after the contract is awarded.