402-20-676 AE Supplement B.doc

DOC document 82 KB Posted

Attached to
C1DA--402-20-676 Renovate Emergency Department - Request for Qualification Statements (SF330 Packages)
Solicitation number
36C24122R0033
Issued by

About this file

This document is a request for qualification statements for architectural and engineering services for a project to renovate the emergency department at the VA Maine Healthcare System campus in Augusta, Maine. The project aims to improve patient flow and services at the existing emergency department by renovating approximately 10,245 square feet and designating space for radiology procedures. Qualification statements are due by February 14, 2022 at 4:00 PM EST. The procurement is set aside for verified Service-Disabled Veteran Owned Small Businesses and has a North American Industry Classification System code of 541310 for architectural services with a small business size standard of $8 million in average annual revenue. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1 is the contracting agency.

View the file

Other files

File Type Posted
36C24122R0033 Request for SF330s.docx DOCX document
402-20-676 AE Supplement C.doc DOC document
402-20-676 SOW.doc DOC document
402-20-676 AE Supplement A.doc DOC document
36C24122R0033.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUPPLEMENT “B”

A/E SUBMISSIONS

OF DESIGN REVIEW MATERIAL

FIRST REVIEW

(Conceptual – Preliminary User Group Meetings & Field Surveys)

2 Sets of reduced size and PDF preliminary layout plans with proposed alternates per meeting

2 Sets of conceptual estimates with proposed alternates per meeting

SECOND REVIEW

(30% Submittal – Schematics)

2 Sets of AutoCAD & PDF schematic drawings in accordance with Supplement “A” Item 6 2 Sets of full size bound schematic layout plans/details – 36 inches by 24 inches 2 Sets of reduced size bound schematic layout plans/details

2 Sets of MS Word draft specifications in accordance with Supplement “A” Item 6 2 Sets of spiral bound draft specifications

2 Sets of schematic estimates

2 Sets of draft phasing plans

THIRD REVIEW

(60% Submittal – “DD” Design Development)

2 Sets of AutoCAD & PDF design drawings in accordance with Supplement “A” Item 6 2 Sets of full size bound design development layout plans/details – 36 inches by 24 inches 2 Sets of reduced size bound design development layout plans/details

2 Sets of MS Word design specifications in accordance with Supplement “A” Item 6 2 Sets of spiral bound design specifications 2 Sets of design development estimates

2 Sets of design development phasing plans

FOURTH REVIEW

(90% Submittal – “CD” Construction Documents)

2 Sets of AutoCAD & PDF construction drawings in accordance with Supplement “A” Item 6 2 Sets of full size bound construction documents plans/details – 36 inches by 24 inches 2 Sets of reduced size bound construction documents plans/details

2 Sets of Adobe PDF construction specifications in accordance with Supplement “A” Item 6 2 Sets of spiral bound construction specifications

2 Sets of construction documents estimates

2 Sets of construction documents phasing schedules

FIFTH REVIEW

(100% Submittal – Bid [Final] Documents)

2 Sets of AutoCAD & PDF bid drawings in accordance with Supplement “A” Item 6 2 sets of approved full-size bid documents with PE stamps

2 Sets of approved reduced size bound bid plans/details with PE stamps

2 Sets of MS Word final specification sections in accordance with Supplement “A” Item 6 2 Sets of Adobe PDF final specification sections merged in accordance with Supplement “A”

2 Sets of final specifications boxed on single sided sheets

2Sets of final estimates

2 Sets of final phasing schedules

SIXTH REVIEW

(Project Close Out Submittal – “As-Built” Construction Documents)

2 Sets of AutoCAD & PDF As-Built drawings in accordance with Supplement “A” Item 6 2Sets of approved reduced size As-Built plans/details with PE stamps

ID
Milestone Task Description
Duration
Schedule

Date Actual

Date

1
User Group Preliminary Mtg (Review Scope, Site Survey Investigation)
1 Day
NTP + 15
2
Preliminary Investigation of Existing Conditions
As Needed
3
Submit Conceptual Layout Schemes with Proposed Alternates
---
NTP + 30
4
User Group Mtg (Review Proposed Schemes)
1 Day
5
Submit Revised Conceptual Layout Plans with Proposed Alternates
---
6
User Group Mtg (Review Conceptual Plans)
1 Day
7
Submit Revised Conceptual Layout Design for Approval
---
NTP + 60
8
User Group Mtg (Review/Approve Conceptual Plans)
1 Day
9
Prepare 30% Schematic Design Submissions
---
Survey Existing Conditions, Coordinate Design with Consultants & VA Comments
As Needed
10
Submit 30% Schematic Design Package
---
NTP +120
VA Engineering 30% Review
7 Days (Min)
11
User Group 30% Schematic Design Review Meeting
1 Day
12
Prepare 60% “DD” Design Development Submissions
---
Confirm Existing Conditions, Coordinate Design with Consultants & VA Comments
As Needed
13
Submit 60% “DD” Design Development Package
---
NTP + 240
VA Engineering 60% Review
14 Days (Min)
14
User Group 60% “DD” Review Meeting
1 Day
15
Prepare 90% “CD” Construction Document Submissions
---
Coordinate Design with Consultants, Existing Conditions & VA Comments
As Needed
16
Submit 90% “CD” Construction Documents Package
---
NTP + 300
VA Engineering 90% Review
14 Days (Min)
17
User Group 90% “CD” Review Meeting
1 Day
18
Prepare 100% Bid Final Documents
---
Finalize Coordination with Consultants, Existing Conditions & VA Comments
As Needed
19
Submit 100% Bid Final Documents with PE Stamps
---
NTP + 360
20
Bid Opening Date and/or Negotiate with SBA 8a Contractor
---