4 Multi Campground Water System Statement of Work.pdf

PDF 133 KB Posted

Attached to
127EAW22R0025 - Stanislaus Multi CG Well Water System
Solicitation number
127EAW22R0025
Issued by

About this file

This statement of work and related solicitation describe a construction project for improvements to water systems at two campgrounds within the Stanislaus National Forest in California. The scope of work involves locating and drilling two new water wells, constructing a new water system at one site, and improvements to the existing system at another. Additional requirements include cleanup and disposal of removed materials. The total value of the contract is estimated between $250,000 and $500,000. The solicitation is a total small business set-aside issued by the Department of Agriculture Forest Service. The response deadline for requests for information is March 23rd, 2022. An organized pre-proposal site visit will be held. The selected contractor must begin work within 10 days of the notice to proceed, estimated for June 15th, 2022.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section C – Construction

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

Scope of Contract

This contract is for the locating, drilling, and development of two new water wells, as well as construction of a new water system at the Utica Union site, and improvements to the existing water system at the Cherry Valley site. The work shall also include cleanup and disposal of all removed building material from Forest Service lands.

Project Location

This project is located within the Stanislaus National Forest in Tuolumne County, California. Cherry

Valley Campground is located along Forest Route 1N04, outside of Buck Meadows, California. The

Utica Union Water System site is located at the junction of Forest Route 7N17 and Forest Route 7N75, off of Forest Route 7N01 outside of Tamarack, California. A map of the site is in the Drawings.

NOTE: Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. In no event shall failure to inspect the site constitute grounds for a claim after contract award. (See Section L, 52.236-27, SITE VISIT.)

Estimated Start Date

June 15, 2022

Contractor must begin work within 10 days of the effective date of the Notice to Proceed. See Section

F for additional information.

Restrictions on Work

1. Work hours are limited to non-holiday week days, Monday – Friday, 07:30 – 19:00

2. In accordance with the fire plan, if included in Section J.

3. When the Contracting Officer (or designated representative) determines that adverse weather has made access too dangerous or that continued vehicular travel would cause unacceptable road damage.

Worker's Compensation Insurance

The Contractor shall provide evidence of Worker's Compensation Insurance or a written explanation as to why the Contractor is exempt from the requirement. NOTE: The Contractor working alone is not required to carry the insurance.

Camping and Housing (see also Section H, Camping Permit Compliance)

Camping is not permitted in US Forest Service campgrounds. Contractor [ ] will [X] will not be permitted to camp elsewhere on US Forest Service land. Camping on Forest Service land is not a right; permission may be revoked for failure to comply with the terms of the permit.

Maps

INCLUDED WITH DRAWINGS

Drawings and Specifications

Project Drawings: The following drawings are part of this solicitation:

1. GAOA Multi Campground Water System Construction Plans

Specifications:

[X] Construction Standard Institute (CSI) specifications

These specifications are physically incorporated in the solicitation.

[ ] Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects

FP-04 (US Customary Units)

This document is incorporated by reference and is available on the web in either MS Word or Acrobat (https://flh.fhwa.dot.gov/resources/specs/)

It is also available as a wire-bound book that can be purchased from the US Government Printing

Office:

Superintendent of Documents

U.S. Government Printing Office

Internet: bookstore.gpo.gov

Phone: (toll free) 866.512.1800

Fax: 202.512.2250

Mail: Stop SSOP, Washington, DC 20402-0001

Stock Number: 050-001-00341-4 (U.S. Customary)

Special Project Specifications are physically incorporated within this solicitation, beginning on the next page.

The following Standard and Special Project Specifications are applicable to this contract:

# Description Date

1 GAOA Multi Campground Water System Construction

Construction Specifications

12/8/2021

The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.

Material Certifications, Testing Reports, & Other Submittals.

Submit the following items to the Contracting Officer for approval.

https://flh.fhwa.dot.gov/resources/specs/ http://bookstore.gpo.gov/

Title

Referenced by Contract clause or Specification No.

Time of

Government

Approval

After

Submittal

Project Schedule Specifications 01 30 00 10 days

Quality Control and Quantity

Measurement: Designation of the

On-The-Job Superintendent

Designation of On-Site Quality

Control Manager

Quality Control Plan

As-Built Drawings

Certificates-of-Compliance

Test Results

Bill-of-Ladings

Specifications 01 41 00 10 days

Demolition Schedule Specifications 02 41 19 10 days

Water Supply Well: Contractors

California C57 license

Subcontractor information

Product Data

Shop Drawings

Project Record Documents

Field Quality-Control Report

Operation and Maintenance Manual

Specifications 02 52 50 10 days

Valves and Enclosures: Technical data for valves

Technical Data for boxes

Product literature valves

Product literature boxes

Specifications 02 64 00 10 days

Water Distribution System: Product

Data

Shop Drawings

Specifications 02 66 00 10 days

Disinfection of Water Distribution

System: Disinfection Agent

Residual test results

Specifications 0267 50 10 days

Concrete Formwork: CO Inspection of Form

Specifications 03 10 00

Concrete Reinforcement: Horizontal and Vertical Reinforcement Plan

Specifications 03 20 10 FIO

Cast-in-Place Concrete: Mix Design, Admixtures, Deliver Tickets

Specifications 03 30 10 FIO

Rough Carpentry: Wood Treatment

Data, Product Data, Maintenance

Instructions, Warranties, Samples

Specifications 06 10 00 FIO

Caulking and Sealants: Product

Data, Maintenance Instructions, Specifications 07 90 00 FIO

Warranties, Samples

Finishes: Product Data, Samples Specifications 09 90 00 FIO

Power Generator: Product Data, Shop Drawings, Mainenance

Manuals

Specifications 11 31 00 10 days

Pressurized Water Storage tanks:

Shop Drawings

Manufacturer’s literature

Manufacturer’s installation instruction

Pressure Switch

Specifications 13 57 00 10 days

Liquified Petroleum Gas System:

Product data, testing information

Specifications 22 11 14 10 days

Low Voltage Electrical Power

Conductors and Cables: Product data, shop drawings

Specifications 26 05 19 10 days

Grounding and Bonding for

Electrical Systems: Product data, shop drawings

Specifications 26 05 26 10 days

Raceways: Product data, shop drawings

Specifications 26 05 33 10 days

Boxes: Product data, shop drawings Specifications 26 05 34 10 days

Identification for Electrical Systems:

Product data, shop drawings

Specifications 26 05 53 10 days

Visual Equipment Inspection

Reports

Specifications 31 31 19 FIO

Trenching and Backfilling:

Certification of place of purchase

Product Data

Weigh tickets

Specifications 31 50 00 10 days

Base Courses: Certification of place of purchase

Product Data

Weigh tickets

Specifications 32 11 00 10 days

Boulder Barriers: Certification of place of purchase

Product Data

Weigh tickets

Specifications 32 33 10 10 days

FIO= “For information only