This document is a municipal proposal and contract from the Pennsylvania Department of Transportation for Snow Shoe Township in Centre County, specifically for road improvements on Black Bear Road. The project involves furnishing and placing approximately 1,200 tons of 2A aggregate along Black Bear Road (T711), beginning at its intersection with Kato-Orviston Road (T710) and extending approximately 0.3 miles. The bid proposal is scheduled for submission on June 6, 2025, with bid opening at 9:00 AM, and work is to be completed by June 28, 2025. The contractor will be required to provide all materials, labor, equipment, and supervision to complete the road improvement work in accordance with Pennsylvania Department of Transportation Publication 408 specifications.

The contract includes a 10% bid bond or certified check as a proposal guarantee, with liquidated damages of $1,000 per calendar day for work completed after the June 28, 2025 deadline. The contractor must comply with Pennsylvania and federal labor laws, including provisions for equal opportunity, non-discrimination, and prevailing wage requirements. The project will require performance and payment bonds, and the contractor will be responsible for maintaining permanent pavement repairs for one year after project completion. The scope of work includes full road width preparation, aggregate placement and compaction, traffic control, and adherence to specific technical specifications outlined in the contract documents.

View the file

Other files

File Type Posted
1-Black Bear Road Prevailing Wage Determination.pdf PDF
2-Black Bear Road Location Map.pdf PDF
3-Bidder Acknowledgements (Q-26PW) (6).xlsx XLSX spreadsheet
6-Addendum 1.pdf PDF
5-Black Bear Road Access Map.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MS-944 (7-09)

All envelopes containing Bid proposals shall b

TIME

PROPOSALS MUST BE MAILED OR OTHERWISE

TIME DELIVERED TO THE ABOVE ADDRESS.

and specifications on file at as well as the supplements complete all work within calendar days.

3 Accompanying this proposal is a certified check or bid bond in the amount of made payable to the municipality as a proposal guarantee which, it is understood, will be forfeited in case the contractor fails to comply with the requirements of the proposal.

B. PROPOSAL OF:

1 The only person interested in the proposal as principal (s) is (are):

2 None of the above persons are employees of the municipality.

3 This proposal is made without collusion with any other person, firm or corporation.

The contractor proposes to furnish and deliver all materials ( including Form CS-4171, CERTIFICATE OF COMPLIANCE and/ or TR-465 DAILY BITUMINOUS MIXTURE CERTIFICATION ) and to do and perform all work on the following project as more specifically set forth in the Schedule of Prices (Attachment), in accordance with drawings and special requirements contained herein and/or attached hereto and current PennDOT Specifications (Publication 408), except (a) Volumetric testing of bituminous paving materials is not required (Sec. 409).

INSTRUCTIONS ON PAGE 4

Bids will be opened and read at approximately 9:00 AM , on the above Letting Date.

June 6, 2025 ."

9:00 AM

Snow Shoe Township

MUNICIPALITY (NAME & TYPE)

Tara Guenot

TOWNSHIP SECRETARY

DATE

on the above Letting Date. 268 Old Side Road

If designated as the successful bidder, the contractor will begin work on the date specified in the notice to proceed, or as otherwise provided in the special requirements, and will

10% contract

PennBid

See attachment 1-A

-1-

It is hereby certified as follows:

NAME / ADDRESS OF CONTRACTOR

CONTRACTORS CERTIFICATION

All plans and specifications referred to above and the site of the work have been examined by the contractor. The contractor understands that the quantities indicated herein are approximate and are subject to change as may be required; and that all work is payable on the basis of the unit price listed on the Schedule of Prices. (Page 3).

THIS PROPOSAL INCLUDES

INSTRUCTIONS TO BIDDERS

ADDRESS

A. DEPOSIT OF PROPOSALS.

Proposals will be received on or before be clearly marked "Bid Proposal for Letting of

PROPOSAL AND CONTRACT

( WHEN EXECUTED )

Clarence, PA 16829

BY: DATE:

TITLE:

DATE:

TITLE:

TITLE:

BY:

TITLE:

BY:

TITLE:

TITLE:

TO BE EXECUTED ONLY IN THE EVENT THE ABOVE PROPOSAL IS ACCEPTED

ACCEPTED ON :

MUNICIPALITY

BY:

DATE

Snow Shoe Township

-2-

ATTESTED BY:

WITNESSED OR ATTESTED BY:

The contractor will comply with all requirements of the laws and implementing regulations of the Commonwealth of Pennsylvania and the United States relating to human relations, equal opportunity and non-discrimination in employment, and will pay to workmen employed in the performance of the contract the wages to which they may be entitled.

The contractor will provide the municipality with a performance bond, conditioned upon the faithful performance of the contract in accordance with the plans, specifications and conditions thereof, and a payment bond, conditioned on the prompt payment of all material furnished and labor supplied or performed in the prosecution of the work, in accordance with the Public Works Contractors’ Bond Law of 1967; and an affidavit accepting the provisions of the Workmen’s Compensation Act of 1915, as amended.

CONTRACTOR

SEAL

County:

TON

EACH MUST BE INCLUDED.

- 3 -

Proposal and Contract Centre Municipality: Snow Shoe Township

LOCATION OF WORK:

T H

IS

P

O R

T

IO

N T

O B

E C

O M

P

LE

T E

D B

Y T

H E

M U

N

IC

IP

A

LI

T

Y

Unit

SCHEDULE OF PRICES

*Description

Project Number: Black Bear Road

Black Bear Road (T711) beginning at the intersection of Black Bear Road and Kato-Orviston Road (T710), and extending along Black Bear Road for a length of approximately 0.3 miles. See Attachment 2 for site location map.

Unit 5 Price

Total

2A AGGREGATE (FURNISHED, PLACED, AND COMPACTED)

Work shall include furnishing all materials, labor, equipment, and supervision to perform all operations required to complete the work detailed herein and as evidently necessary to complete the work. All materials shall meet or exceed requirements of Specifications of the Pennsylvania Department of Transportation, Publication 408 and Bulletin 14 or 15. Work shall include but shall not be limited to the following: Furnishing, placement, and compaction of 2A aggregate or approved alternate material.

Item 1 No.

Approximate 2 Quantities

1 1,200

TOTAL BID

* DESCRIPTION:

Must include ADT on wearing surfaces

USE OF CUTBACK ASPHALT IS PROHIBITED

BETWEEN MAY 1st AND OCTOBER 31st, EXCEPT

AS NOTED IN BULLETIN NO. 25.

FOR OPTION OR PHASE BIDS THE TOTALS FOR

Contents:

Bid Form Pages 1 through 3 Special Provisions to Contract Page 4 Proposal and Contract Instructions Page 5 Affidavit Re: Accepting Provisions Page 6 of the Workman's Comp. Act Anti-Collusion Affidavit Page 7 Notice of Completion Page 8 Certificate of Compliance Page 9

Attachments Attachment 1-Prevailing Wage Determination Attachment 2-Location Map Attachment 3-Project Information

Traffic Control and Safety Devices to be provided by the Contractor. Maintain 1 lane of traffic at all times.

X Delivery tickets for all materials.

x CS-4171 Certificate of Compliance and/ or TR-465 Daily Bituminous Mixture Certification required for all materials.

X two (2) working days prior to start of project.

x

Roadway to be power broomed by (contractor )prior to start of project.

x Excess material to be removed by (contractor .)

X Municipality to inspect project.

Need Bill of Lading for each shipment of bituminous material per Section 702.1(c) of Specifications 408.

Tack Coat required per Section 460, or 409 for superpave, of Specifications 408 and is incidental to paving item unless noted otherwise.

Prime Coat required per Section 461 of Specifications 408.

Bituminous Seal on all abutting pavement and curbs required.

Saw cut or Milled Paving Notch required and incidental to paving item unless noted otherwise.

Scratch/ Leveling Courses to be placed at the discretion of appointed inspector(s).

x Municipality reserves the right to limit work completed.

Taper pavement the last 3 feet to curb.

For FOB Source bids, hauling distance will determine selection of bid award.

x Municipality reserves the right to procure material which best suits their requirements after all bids and items are reviewed.

x Incidental Preparation and clean up required. ( Project Construction Materials ) x The municipality reserves the right to make an award on the basis of the aggregate total for all like items on which quotations are received.

Provide design, which meets Specifications Form 408 to the municipality 5 days prior to start of work.

Contractor responsible for defects that occur within one year of applications.

Contractor required to review proposed project with Municipality’s Representative prior to bidding.

Oil Samples required from each distributor truck by contractor (1) one quart : A.M. & P.M. and witnessed by municipality and retained by municipality. (Oil samples must be placed in an approved type container that is compatible with oil sample.)

x At least three random stone samples to be taken by contractor on project site witnessed by municipality and retained by municipality.

Complete all testing in accordance with Specification Form 408 Section 409 except for superpave volumetric testing.

x Notice to Proceed will be the date of Contract acceptance.

x Final Completion Certificate & Notice of Completion required.

x Future award of Contract will be based on quality of work as determined by the municipality.

x Contractor, notify all residents of pending work to be performed.

My signature signifies that I have read and understand the above special provisions to this contract, and by being authorized by this company to act as their authorized representative, and on their behalf hereby agree to adhere to any and all of the provisions pertaining to this contract.

Date

Work to be completed on or before 6/28/2025 . After 6/28/2025 the rate of $ 1000.00 per calendar day.

Snow Shoe Township

Liquidated damages apply at

Full width pavement with one pass required.

Company Municipality

Contractor's Representative Municipality's Representative Date

Notify the Municipality

(5-06) SPECIAL PROVISIONS TO CONTRACT MS-944 ( Attachment 1)

CONTAINS IMPORTANT INFORMATION FOR THE CONTRACTOR

The Prime Contractor and subcontractors must comply with all of the following provisions that are marked with an "X".

( Maintenance and Protection of Traffic to comply with current MUTCD, Publication 212 and Publication 213.)

2 If more than one proposal on any project is submitted by an individual, firm or partnership, corporation or association under the same or different names, only one lowest proposal will be considered.

3 Description of Work- - -

A. If additional space is needed, insert appropriately numbered attachment and note “Continued on attached work sheets."

4 Part A of Page 1 to be completed by municipality. Part B of Page 1 to be completed by contractor.

Schedule of Prices - Column #1 (Item), #2 (Approximate quantities), #3 (Unit, i.e., ton, square yard, linear feet, etc.) And #4 (Description, i.e. , bituminous materials - 9.5 mm S & L, 12.5 mm Wearing,

25.0 mm Base Course, etc.) Must be filled in by the municipality to insure equitable bidding.

Columns #5 (Unit Price), #6 (Total) and total amount of bid, must be filled in by the contractor.

If more space is needed, add note at the bottom of the page; “Continued on Attachment No. 1-A”, and add additional sheet designated as Attachment No. 1-A, 1-B, etc.. Repeat for each additional sheet required.

As required by Publication 408, Section 102.06(e),each bidder must submit a completed Form 7126 - Anti-Collusion Affidavit with its bid proposal.

5 If liquidated damages are to be assessed, add the following sentence to Part A #2. If all work is not completed on time, liquidated damages will be assessed at the rate of $870.00 per additional working day.

(OR “. . . as set forth in the attached schedule.”)

6 Payment and Performance bonds are provided only by the successful bidder. Contracts from $4,000.00 up to $5,000.00 in Second Class Townships - performance bond must be not less than 10% or greater than 100% of amount of contract.

Contracts greater than $1,500.00 up to $10,000.00 in First Class Townships, Boroughs and Third Class Cities - bonds must be between 50 % to 100% of the contract amount. Contracts in excess of $5,000.00 in Second Class Townships and in excess of $10,000.00 in First Class Townships, Boroughs and Third Class Cities - bonds must be in 100% of the amount of the contract. Bond Forms MS-944 Attachments 2 and 3 and Workmen’s Compensation Affidavit - Attachment 4 must be submitted by the successful bidder within 20 days of the contract award. Failure to submit the bonds shall constitute grounds to cancel the contract.

7 *Construction projects, where the estimated cost of the total project exceeds $100,000, are subject to the provisions of the Pennsylvania Prevailing Wage Act 442 and amended by Act 89 of 2013. It is the responsibility of the municipality to request the Prevailing Wage Scale for the area and include it in the proposal. If the Prevailing Wage Act applies, this fact shall be noted in the advertisement.

On projects utilizing Federal Revenue Sharing Funds, if the project cost exceeds $2,000 and is financed with 25% or more Federal Revenue Sharing Funds, the Davis Bacon Act applies. Again, it is the responsibility of the municipality to obtain the Davis Bacon Wage Rates, include them in the proposal and note the fact in the advertisement. If both acts are applicable, The Davis Bacon Act has preference over the Pennsylvania Prevailing Wage Act.

8 An ESCALATOR CLAUSE is optional; if used, it must be included in the proposal prepared by the municipality. An escalator clause may not be inserted by the contractor.

*(1961, Aug. 15, P.L. 987; 43 P.S. 165)

-5-

PROPOSAL AND CONTRACT INSTRUCTIONS- FORM 944 (Rev. 1/2014)

The proposal must be typewritten or printed.

Attachment 4

State of ) ) ss:

County of ) he has being duly sworn according to law deposes and says that they have it has accepted the provisions of the Workmen’s Compensation Act of 1915 of the Commonwealth of Pennsylvania, with has his its supplements and amendments, and have insured their liability thereunder in accordance with the terms of said its

Act with .

( TYPE OR PRINT)

BY

day of A.D. 20 .

My Commission Expires

- 6 -

CONTRACTOR

SIGNATURE

Sworn to and subscribed before me this

( DATE )

SIGNATURE

(SURETY COMPANY)

AFFIDAVIT RE

ACCEPTING PROVISIONS OF THE WORKMEN’S COMPENSATION ACT

D-7126 ( 7-09 )

County

Municipality

Project Number

State of Fed. Project No.

( If Applicable )

The undersigned deponent deposes and says that he is the of the

BY

Sworn to and subscribed before me the undersigned notary public this day of , .

Notary Public

My Commission expires

(Contractor) competitive bidding in connection with such contract.

into any agreement, participated in any collusion, or otherwise taken any action in restraint of free

Company; that he is authorized to make this

Publication 408, as amended and that the said company has not, either directly or indirectly, entered affidavit on behalf of said company in compliance with section 102.06 (e) of Department Specifications, County of

ANTI-COLLUSION AFFIDAVIT

Centre

Black Bear Road

Snow Shoe Township

MS-NCP

MUNICIPALITY

Name of Contractor

Performance of work as specified on the above numbered contract is completed and final pavement inspection has been made by the contractor and municipality in accordance with the terms of the contract awarded.

DATE OF AWARD

Both copies of this form to be filled by the Contractor-Municipality on completion of final pavement restoration.

*DATE

period of one year from this date.

* The contractor is responsible for maintenance of permanent pavement repairs for a

By the affixing of my signature I hereby certify that final

NOTICE OF COMPLETION

IN REFERENCE TO PROJECT # Black Bear Road accordance with the above contract # and is hereby accepted inspection has been made and all work has been performed in

FINAL COMPLETION CERTIFICATE

THIS PORTION TO BE COMPLETED BY MUNICIPALITY

Authorized Agent for the Municipality by the municipality as completed.

Snow Shoe Township

Signature of Contractor

Signature of Municipality