4-MCTA Bid Submittal Checklist GC Rebid.pdf
PDF 147 KB Posted
- Solicitation number
- Not on record
- Issued by
- Monroe County, Pennsylvania
About this file
This is a Bid Submittal Checklist for the Monroe County Transit Authority (MCTA) Transit Facility project located at 134 MCTA Drive, Swiftwater, Pennsylvania. The project encompasses the renovation of an existing maintenance building with six repair bays, construction of a pre-engineered bus storage addition, and expansion of the fuel island with associated site improvements to accommodate Fixed-Route buses, Paratransit shared-ride vehicles, Microtransit buses, and non-revenue vehicles. The General Trades Construction (GTC) rebid is due electronically via the PennBid Program by February 4, 2026 at 3:00pm, with a virtual pre-bid meeting scheduled for January 14, 2026 at 10:00am. The project is designed by Stantec Consulting Services Inc. and managed by WSP USA, Inc., with the Monroe County Transit Authority serving as the owner.
Bidders must submit comprehensive documentation including bid security submitted through PennBid, financial statements or Dun & Bradstreet reports, performance and payment bonds (submitted at award), and multiple certifications and affidavits as attachments. Required submissions include certification of receipt of addenda, non-collusion affidavits, Build America Buy America certifications, debarment certifications for primary and lower-tier participants, Disadvantaged Business Enterprise (DBE) certifications and documentation of good faith efforts, non-discrimination clauses, Americans with Disabilities Act compliance, Title VI Civil Rights Act compliance, lobbying certificates, federal requirements notices, environmental and energy requirements, Pennsylvania Steel Products Procurement Act certification, hold harmless agreements, contractor integrity documentation, Public Works Employment Verification Act forms, prohibited telecommunications equipment certifications, and warranty logs. Failure to return the completed bid submittal checklist may result in the bid being considered non-responsive.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MCTA Transit Facility BID SUBMITTAL CHECKLIST
PROJECT MANUAL 004393 - 1
August 29, 2025
SECTION 004393 - BID SUBMITTAL CHECKLIST
1.1 BID INFORMATION
A. Bidder: ___________________________________________________________.
B. Prime Contract: ____________________________________________________.
C. Project Name: MCTA Transit Facility
D. Project Location: 134 MCTA Drive, Swiftwater, PA 18370
E. Owner: Monroe County Transit Authority (MCTA)
F. Designer: Stantec Consulting Services Inc.
G. Construction Manager: WSP USA, Inc.
1.2 BIDDER'S CHECKLIST
A. In an effort to assist the Bidder in properly completing all documentation required, the following checklist is provided for the Bidder's convenience. The Bidder is solely responsible for verifying compliance with bid submittal requirements per the Bid Documents.
B. This form must be completed and returned with submission of a bid. The Bidder shall use this list to ensure all required certifications, affidavits and miscellaneous documents have been provided. Failure to return this form may be cause for the bid to be considered non-responsive.
MCTA Transit Facility BID SUBMITTAL CHECKLIST
PROJECT MANUAL 004393 - 2
August 29, 2025
Bidder’s Checklist
Bid Security ...................................................................................................... Submitted in PennBid
Bidder’s Qualifications
Financial Statement or Dun & Bradstreet Report Performance Bond .............................................................................................. Submitted at Award
Payment Bond .................................................................................................... Submitted at Award
Attachment A – Certification of Receipt of Addenda
Attachment B – Non-Collusion Affidavit
Attachment C – Build America Buy America Certification
Attachment D – Certification of Primary Participant Regarding Debarment
Attachment E – Certification of Lower-Tier Participant Regarding Debarment
Attachment F – Disadvantage Business Enterprise Certification
Attachment G – Schedule of Disadvantage Business Enterprise Participation
Attachment H – Affidavit of Disadvantaged Business Enterprise
Attachment I – Demonstration of Good Faith Efforts
Attachment J – Commonwealth Non-Discrimination Clause
Attachment K – Americans with Disabilities Act Compliance
Attachment L – Title VI of the Civil Rights Act of 1964
Attachment M – Lobbying Certificate
Attachment N – Notice of Federal Requirements
Attachment O – Environmental, Resource Conservation and Energy Requirements
Attachment P – Pennsylvania Steel Products Procurement Act Certification
Attachment Q – Hold Harmless Agreement
Attachment R – Contractor Integrity
Attachment S – Public Works Employment Verification Act Form
Attachment T – Prohibited Telecommunications Equipment
Attachment U – Build America Buy America Certification
Attachment V – Warranty Log
END OF SECTION 004393