4. RFP Attachment J.3 Schedule of Prices.xlsx

XLSX spreadsheet 42 KB Posted

Attached to
Fleetwide Dockside Repair and Ship Maintenance Indefinite Delivery Indefinite Quantity (IDIQ)
Solicitation number
1305M223RNMAN0005
Issued by

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OP1

Ordering Period 1Labor CategoryQTYUnit of IssueLabor RateTotal
1001Marine Welder40Hour
1002Marine Machinist (Inside)40Hour
1003Marine Machinist (Outside)40Hour
1004Marine Sheet Metal Fabricator40Hour
1005Marine Pipe-Fitter40Hour
1006Marine Boilermaker40Hour
1007Marine Electrician40Hour
1008Marine Rigger40Hour
1009Marine Ship Fiter40Hour
1010Marine Shipwright/Carpenter40Hour
1011Marine Painter/Sandblaster40Hour
1012Marine Lagger/Insulator40Hour
1013Marine Chemist40Hour
1014Marine Scaler/Laborer40Hour
1015Crane Operator40Hour
1016Construction Laborer40Hour
1017Supervisor/Quality Control40Hour
1018Project Engineer40Hour
1019Quality Assurance Manager40Hour
1020Project Lead40Hour

OP1 (AIRS)

ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINGROWTH/LABORQTYUNITUNIT PRICEEXTENDED PRICE
AIRS/Growth (estimated)1LT$________$___________
**Provide breakdown, as follows:
AIRs/Growth Labor Rate
Unit Price: $________; Quantity:hours; Unit of Issue: Hour;
ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINMATERIAL/MARKUPQTYUNITUNIT PRICEEXTENDED PRICE
AIRs/Growth Material Markup/Handling Fee
$10,000.00LT$________$___________
Unit of Issue: Percent ________%;

OP2

Ordering Period 2Labor CategoryQTYUnit of IssueLabor RateTotal
2001Marine Welder40Hour
2002Marine Machinist (Inside)40Hour
2003Marine Machinist (Outside)40Hour
2004Marine Sheet Metal Fabricator40Hour
2005Marine Pipe-Fitter40Hour
2006Marine Boilermaker40Hour
2007Marine Electrician40Hour
2008Marine Rigger40Hour
2009Marine Ship Fiter40Hour
2010Marine Shipwright/Carpenter40Hour
2011Marine Painter/Sandblaster40Hour
2012Marine Lagger/Insulator40Hour
2013Marine Chemist40Hour
2014Marine Scaler/Laborer40Hour
2015Crane Operator40Hour
2016Construction Laborer40Hour
2017Supervisor/Quality Control40Hour
2018Project Engineer40Hour
2019Quality Assurance Manager40Hour
2020Project Lead40Hour

OP2 (AIRS)

ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINGROWTH/LABORQTYUNITUNIT PRICEEXTENDED PRICE
AIRS/Growth (estimated)1LT$________$___________
**Provide breakdown, as follows:
AIRs/Growth Labor Rate
Unit Price: $________; Quantity:hours; Unit of Issue: Hour;
ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINMATERIAL/MARKUPQTYUNITUNIT PRICEEXTENDED PRICE
AIRs/Growth Material Markup/Handling Fee
$10,000.00LT$________$___________
Unit of Issue: Percent ________%;

OP3

Ordering Period 3Labor CategoryQTYUnit of IssueLabor RateTotal
3001Marine Welder40Hour
3002Marine Machinist (Inside)40Hour
3003Marine Machinist (Outside)40Hour
3004Marine Sheet Metal Fabricator40Hour
3005Marine Pipe-Fitter40Hour
3006Marine Boilermaker40Hour
3007Marine Electrician40Hour
3008Marine Rigger40Hour
3009Marine Ship Fiter40Hour
3010Marine Shipwright/Carpenter40Hour
3011Marine Painter/Sandblaster40Hour
3012Marine Lagger/Insulator40Hour
3013Marine Chemist40Hour
3014Marine Scaler/Laborer40Hour
3015Crane Operator40Hour
3016Construction Laborer40Hour
3017Supervisor/Quality Control40Hour
3018Project Engineer40Hour
3019Quality Assurance Manager40Hour
3020Project Lead40Hour

OP3 (AIRS)

ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINGROWTH/LABORQTYUNITUNIT PRICEEXTENDED PRICE
AIRS/Growth (estimated)1LT$________$___________
**Provide breakdown, as follows:
AIRs/Growth Labor Rate
Unit Price: $________; Quantity:hours; Unit of Issue: Hour;
ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINMATERIAL/MARKUPQTYUNITUNIT PRICEEXTENDED PRICE
AIRs/Growth Material Markup/Handling Fee
$10,000.00LT$________$___________
Unit of Issue: Percent ________%;

OP4

Ordering Period 4Labor CategoryQTYUnit of IssueLabor RateTotal
4001Marine Welder40Hour
4002Marine Machinist (Inside)40Hour
4003Marine Machinist (Outside)40Hour
4004Marine Sheet Metal Fabricator40Hour
4005Marine Pipe-Fitter40Hour
4006Marine Boilermaker40Hour
4007Marine Electrician40Hour
4008Marine Rigger40Hour
4009Marine Ship Fiter40Hour
4010Marine Shipwright/Carpenter40Hour
4011Marine Painter/Sandblaster40Hour
4012Marine Lagger/Insulator40Hour
4013Marine Chemist40Hour
4014Marine Scaler/Laborer40Hour
4015Crane Operator40Hour
4016Construction Laborer40Hour
4017Supervisor/Quality Control40Hour
4018Project Engineer40Hour
4019Quality Assurance Manager40Hour
4020Project Lead40Hour

OP4 (AIRS)

ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINGROWTH/LABORQTYUNITUNIT PRICEEXTENDED PRICE
AIRS/Growth (estimated)1LT$________$___________
**Provide breakdown, as follows:
AIRs/Growth Labor Rate
Unit Price: $________; Quantity:hours; Unit of Issue: Hour;
ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINMATERIAL/MARKUPQTYUNITUNIT PRICEEXTENDED PRICE
AIRs/Growth Material Markup/Handling Fee
$10,000.00LT$________$___________
Unit of Issue: Percent ________%;

OP5

Ordering Period 5Labor CategoryQTYUnit of IssueLabor RateTotal
5001Marine Welder40Hour
5002Marine Machinist (Inside)40Hour
5003Marine Machinist (Outside)40Hour
5004Marine Sheet Metal Fabricator40Hour
5005Marine Pipe-Fitter40Hour
5006Marine Boilermaker40Hour
5007Marine Electrician40Hour
5008Marine Rigger40Hour
5009Marine Ship Fiter40Hour
5010Marine Shipwright/Carpenter40Hour
5011Marine Painter/Sandblaster40Hour
5012Marine Lagger/Insulator40Hour
5013Marine Chemist40Hour
5014Marine Scaler/Laborer40Hour
5015Crane Operator40Hour
5016Construction Laborer40Hour
5017Supervisor/Quality Control40Hour
5018Project Engineer40Hour
5019Quality Assurance Manager40Hour
5020Project Lead40Hour

OP5 (AIRS)

ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINGROWTH/LABORQTYUNITUNIT PRICEEXTENDED PRICE
AIRS/Growth (estimated)1LT$________$___________
**Provide breakdown, as follows:
AIRs/Growth Labor Rate
Unit Price: $________; Quantity:hours; Unit of Issue: Hour;
ADDITIONAL ITEM REQUIREMENTS (AIRs):
These items relate to Growth Work. The Unit Price column will be used throughout the life of the contract if growth work is added to the scope of the contract [reference Commerce Acquisition Regulation (CAR) clause 1352.271-72]. If AIRs are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINMATERIAL/MARKUPQTYUNITUNIT PRICEEXTENDED PRICE
AIRs/Growth Material Markup/Handling Fee
$10,000.00LT$________$___________
Unit of Issue: Percent ________%;

File details come from the government source that posted it. Updated .