This document is the Project Specifications for the building demolition portion of the 127EAW24R0035 - Sardine CG Toilet Replacement contract opportunity.
The specifications require the complete demolition and removal of existing wood and masonry structures, including vault toilets, at the project site. The contractor must carefully remove and dispose of any asbestos-containing vent pipes, and account for the potential presence of lead-based paint. The contractor is responsible for pumping out the human waste from the existing vault toilets, and for backfilling and compacting the site to specified requirements after demolition. All demolition waste must be legally disposed of at an EPA-approved landfill.
The related federal contract opportunity, Solicitation Number 127EAW24R0035, is for the full replacement of the toilet facilities at the Sardine CG site within the Tahoe National Forest. This is a total small business set-aside opportunity with an estimated project value between $100,000 and $250,000. Requests for Information are due by June 4, 2024, and a pre-proposal site visit will not be held.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3. Site Pictures.pdf | ||
| 5. Location Map.pdf | ||
| 6. Davis-Bacon Act WD # CA20240007.pdf | ||
| 2. Schedule.docx | DOCX document | |
| 7. RFI Form.docx | DOCX document | |
| 1. Statement of Work.pdf | ||
| 127EAW24R0035.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 02221 BUILDING DEMOLITION
PART 1 - GENERAL
1.1 SECTION REQUIREMENTS
A. Action Submittals:
1. Waste Management Plan: Submit plan within 10 days of date established for commencement of the Work.
B. Waste Management Plan: Develop a waste management plan consisting of waste identification and waste disposal plans. Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.
1. The vent pipes of the vault toilets are painted asbestos pipes and much be disposed of carefully.
2. May have lead-based paint based on the age of the building.
C. Landfill and Incinerator Disposal Records: Manifests, weight tickets, receipts, and invoices.
PART 2 - PRODUCTS
2.1 PEFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with EPA regulations and with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.
PART 3 - EXECUTION
3.1 DEMOLITION
A. This includes complete removal of the wood/masonry structures, stools, and anything else that is above the concrete floor slab.
B. The non-friable asbestos vent pipes shall be carefully removed and disposed of according to hazardous waste regulations.
C. Remove demolition waste materials from project site and legally dispose of them in an EPA-approved landfill. Do not burn demolished materials.
D. The human waste in the vault shall be pumped out by the contractor. The restroom vaults are approximately 1000 gal each vault.
3.2 FIELD QUALITY CONTROL
A. Backfill and compact soil to fill hole left by demolition of vault toilet
B. Backfill material: Use the excavated material from the new vault.
C. Backfill Placement: Spread backfill materials over the full width of the cross section of the cavity to a maximum loose thickness of 150 mm (6 inches), and compact as specified in paragraph 5d before the next layer is spread. The Contractor may use any type of compaction equipment except rubber tired or smooth steel wheel rollers to obtain the required degree of compaction. The in place materials shall be free of lenses, pockets, streaks, or layers of materials differing substantially in texture or gradation from the surrounding materials.
D. Moisture Content: During placing and compacting of backfill, the optimum moisture content (4 percent to +2 percent) as determined by AASHTO T 217 or AASHTO T 239, unless otherwise approved, shall be maintained by wetting or drying, as required.
E. Compaction: Compact the backfill to a minimum density of 95 percent of the maximum dry density as determined by AASHTO T 99, Method C