2. Schedule.docx

DOCX document 14 KB Posted

Attached to
127EAW24R0035 - Sardine CG Toilet Replacement
Solicitation number
127EAW24R0035
Issued by

About this file

This document is a Schedule of Items for a construction project to install double vault restrooms on the Inyo National Forest. The schedule lists three key line items: Mobilization, Demolition of Double Vault Restrooms, and Installation of Double Vault Restrooms. Quantities are estimated, and the contractor must field verify to satisfy all requirements. One award will be made, and the contractor must submit pricing for all items. Payment for bond premiums shall not be in addition to the contract price.

The related federal contract opportunity is Solicitation Number 127EAW24R0035 for the Sardine CG Toilet Replacement project on the Tahoe National Forest. This is a total small business set-aside between $100,000 and $250,000 in value. All requests for information must be submitted by June 4, 2024, and there will be no pre-proposal site visit, as the project locations are open to the public.

View the file

Other files

File Type Posted
3. Site Pictures.pdf PDF
4. Project Specifications.pdf PDF
5. Location Map.pdf PDF
6. Davis-Bacon Act WD # CA20240007.pdf PDF
7. RFI Form.docx DOCX document
1. Statement of Work.pdf PDF
127EAW24R0035.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

PROJECT: Inyo NF Vault Toilets

Item
Construction Items
Qty
UNIT
Unit Price
Total Price
00001
Mobilization
1
LS
$___________
$___________
02221
Demolition of Double Vault Restrooms
1
LS
$___________
$___________
00003
Installation of Double Vault Restrooms
1
LS
$___________
$___________
TOTAL:
$___________

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

* One award will be made from this solicitation, contractors must submit pricing for all items.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.