4. Basis of Estimate Template.docx
DOCX document 38 KB Posted
- Attached to
- FTQW261406 Replace Upper Dgst Compressors
- Solicitation number
- 261406
About this file
This is a Basis of Estimate Template for the FTQW261406 project titled "Replace Upper Digester Compressors 1&2" at Eielson Air Force Base, Alaska. The template is structured to document the 100% design phase cost estimate and provides a standardized framework for capturing project parameters, assumptions, and estimation methodologies. The document identifies the project as a Class 1 Estimate at the Programming level of design planning, with a project number FTQW261406, fiscal year FY26, and no temporary or swing space requirements identified. The template includes sections for documenting construction duration and milestones, key assumptions affecting costs, exclusions and exceptions to standard requirements, and detailed estimation methods including area cost factors, labor productivity markups, overhead calculations, profit margins, contingency factors, and escalation justification.
The template itself does not contain completed cost estimates or specific pricing data, but rather serves as a standardized format for A&E firms to document their basis of estimate for the upper digester compressor replacement project. Related to this template, the 354th Eielson Contracting Squadron is soliciting A&E qualification packages for Title I design services with a 125 calendar day delivery requirement for the complete design package, including 65%, 95%, and 100% design reviews. Interested firms must submit SF-330 (Architect-Engineer Qualification forms), a Past Performance Questionnaire, and an Instructions to Offerors evaluation factors document to the Department of the Air Force Pacific Air Forces.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FTQW261406, REPLACE UPPER DIGESTER COMPRESSORS 1&2, 100% CWE
11/30/25 Page 7 of 7
100% DESIGN BASIS OF ESTIMATE
1. GENERAL
Project Title: Replace Upper Digester Compressors 1&2
Project Number (ABCD NN-NNNN): FTQW261406
Project Location (Installation/State or Country): Eielson AFB, AK
Project Program Year (FY): FY26
Name/rank/role of persons in team writing the estimate:
Organization of person(s) writing the estimate:
Date of estimate (MMM-YY):
2. PROJECT SUMMARY
Time & Duration of Construction: Project Midpoint, Key Milestones:
Estimated Construction Start Date (MMM-YY):
Estimated Number of Months of Construction (MM):
Estimated Midpoint of Construction (MMM-YY):
Temporary or Swing Space Required – Gross Square Feet (GSF)/Gross Square Meters (GSM):
Not identified as needed.
Purpose & Class of Estimate/Level of Design planning (Planning, Programming, Pre-Award): Class 1 Estimate/Programming
Scope:
Facility/building type/uses:
Category Codes:
Floor area – GSM/GSF (Horizontal facilities M/FT):
Height – Number of stories, M/FT:
Facility/Building Systems:
AT/FP considerations and elements:
Cybersecurity:
Environmental mitigation & permits:
Extraordinary elements:
Deviations from AF standard design and/or Unified Facility Criteria corporate standards (list, narrative):
3. KEY ASSUMPTIONS
Effect on costs (summary):
Unusual schedule requirements:
Exclusions (identify what is not in the project but needed for complete work):
Exceptions (e.g., elements or features different from policy):
Demolition required:
Facility special systems, elements or items included/excluded:
Government-furnished, Contractor-installed equipment; Government-furnished, Government-installed equipment:
Extraordinary items:
4. DESCRIPTION OF ESTIMATE
Methods Used & Limitations Sources of Cost Data Used:
Area Cost Factor(s):
Productivity Markup:
Labor Premium Time (Overtime) Markup:
Prime Job Office Overhead (JOOH) Markup:
Prime Home Office Overhead (HOOH) Markup:
Sub JOOH Markup:
Profit:
Bond:
Risk Factor:
Owner’s Contingency:
Changes/Markups to Default Data and Justifications:
Duration and Escalation (Justification):
Contracting Method:
OPR: AFCEC/COSC Ver 2.0 21 March 2025