4-Attachment 2 Proposed Schedule DWNL.pdf
PDF 49 KB Posted
- Attached to
- PW - STATEMENT OF QUALIFICATIONS FOR CITY OF FORT WORTH DESIGN SERVICES DOWNTOWN LIBRARY
- Solicitation number
- 26-0325
- Issued by
- Tarrant County, Texas
About this file
This is a Proposed Schedule document for the City of Fort Worth's Downtown Library design and construction project located on the 900 Block of Summit Street in Fort Worth, Texas. The project encompasses the design and construction of approximately 22,000 to 30,000 square feet of library space, including community rooms, storage, and multipurpose areas, with a planned expansion capability. The scope includes demolition of three existing structures, associated retaining walls, and existing parking areas, as well as green site improvements incorporating sustainability, landscape, stormwater management, and pedestrian circulation enhancements. The selected architectural and engineering firm will provide programming, architectural and engineering design services, audio-visual and security drawing coordination, budget estimation, and furniture and equipment recommendations. The project schedule spans from August 2026 through August 2029, with key phases including land acquisition (May-October 2026), design and engineering contracting (September 2026-February 2027), design phase (December 2026-October 2027), permitting (October 2027-January 2028), construction contracting (February-November 2027), and construction (November 2027-August 2029). The design phase includes schematic design (30%), design development (60%), and construction document (95%) milestones, with City Facilities and Workplace reviews following each phase.
The construction budget is approximately $25,000,000, with the City intending to solicit competitive bids from qualified general contractors following selection of the design firm through this Statement of Qualifications process. The project utilizes a Construction Manager at Risk (CMAR) delivery method, with a pre-construction services phase scheduled from April through August 2027, Guaranteed Maximum Price (GMP) receipt by October 2027, and management and coordination processes extending through November 2027. Construction is scheduled to commence November 28, 2027, with substantial completion targeted for May 21, 2029, final inspections and occupancy occurring in July 2029, and close-out activities concluding by August 8, 2029. The detailed schedule accounts for 15-day project initiation, 45-day programming phase, 307-day design phase, 90-day permitting period, 295-day construction contracting phase, and 616-day construction phase with final inspections and green sheet completion.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Task Name Duration Start Finish May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct 1 Project Initiation 15 8/24/2026 9/8/2026
2 Land Acqusition 145 5/20/2026 10/12/2026
3 Design (A&E) Contracting 135 9/17/2026 2/1/2027 4 Advetisement and Selection of A&E 75 9/17/2026 12/1/2026 6 M&C Process 45 12/2/2026 1/16/2027 7 Award Full Contract 15 1/17/2027 2/1/2027
8 Design Phase 307 12/1/2026 10/12/2027 5 Programming (>100k) 45 12/1/2026 1/15/2027 9 Pre-Design Meeting (Issue NTP) 15 1/16/2027 1/31/2027
10 Schematic Design (30%) 60 2/1/2027 4/2/2027 11 CFW Reviews 14 4/3/2027 4/17/2027 12 Design Development (60%) 50 4/18/2027 6/7/2027 13 CFW Reviews 14 6/8/2027 6/22/2027 14 Construction Document (95%) 50 6/23/2027 8/12/2027 15 CFW Reviews 14 8/13/2027 8/27/2027 16 Final Drawings Received 45 8/28/2027 10/12/2027
17 Permitting 90 10/13/2027 1/11/2028
18 Construction Contracting 295 2/1/2027 11/27/2027 19 Advertise and Select CMAR 60 2/1/2027 4/2/2027 21 Award Pre-Con. Contract 15 4/3/2027 4/18/2027
Pre-Construction Services 130 4/19/2027 8/27/2027 22 GMP Received 45 8/28/2027 10/12/2027 23 M&C Process 45 10/13/2027 11/27/2027
24 Construction Phase 616 11/28/2027 8/8/2029 25 Construction 540 11/28/2027 5/21/2029 26 Final Inspections & Completion 45 5/22/2029 7/6/2029 27 Take Occupancy 1 7/7/2029 7/8/2029 28 Green Sheet 30 7/9/2029 8/8/2029