4-Addendum No. 1.pdf
PDF 174 KB Posted
- Attached to
- Equalization Basin Gates Upgrade
- Solicitation number
- US.255820
- Issued by
- Northampton County, Pennsylvania
About this file
This addendum document is issued by CP Engineers, LLC on behalf of the Sunbury Municipal Authority for the Equalization Basin Gates Upgrade project (CP Project No. CP-410) located at the Sunbury Wastewater Treatment Plant in Northumberland County, Pennsylvania. The addendum primarily documents the results of a pre-bid meeting held on October 15, 2026, and provides clarifications on project requirements. The base bid scope involves removal and replacement of five aluminum slide gates (two 30" x 30" upward-opening and three 72" x 36" downward-opening weir gates) at the Equalization Tank, with unit price options for up to seven additional gates at other aeration tanks. The project includes minor concrete and metal fabrication work necessary for fully functional gates and associated work to maintain equalization basin operations. The work must be substantially complete by April 30, 2027, to have gates installed before spring rain events. A non-mandatory pre-bid meeting was held on October 15, 2026, with site visits conducted following the meeting. Questions were accepted through October 22, 2026, via PennBid. Nine companies and municipal authority representatives attended the pre-bid meeting.
Key clarifications provided address gate procurement lead times, bolt pattern compatibility, tank dewatering procedures, and site logistics. The existing gates were supplied by North East Technical Sales through sales representative Marc Gradwohl, with replacement gates requiring 8-10 weeks for delivery after approved shop drawings are received. Contractors may use alternative gate manufacturers provided coordination with the Engineer and manufacturer ensures bolt pattern compatibility with existing installations. Tanks will be dewatered and sludge removed by the Authority prior to work, though major wet weather events may prevent dewatering of the Equalization Basin. The project is subject to Pennsylvania public bidding and prevailing wage requirements, with funding provided by the Owner's existing cash reserves. Time extension requests may be submitted if supply chain delays threaten the April 30, 2027 deadline, and any necessary changes to bolt removal procedures will be handled via change order.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2013 Sandy Drive, Suite 101
State College, PA 16803
P: 814.753.4249
Sparta, NJ • Parsippany, NJ • State College, PA www.cpengineers.com
Sunbury Municipal Authority
Addenda No. 1
Issued 10/20/26
The meeting began with a PreBid Meeting that included the following:
Equalization Basin Gates Upgrade
Pre Bid Meeting Minutes
Date: - 10/15/2026
CP Project No. – CP-410
Attendees:
Name Company Email
Derrick Backer SMA dbacker@sunburyma.org
Matt Billman SMA mbillman@sunburyma.org
Brian Book CP Engineers brian.book@cpengineers.com
Danny Long Lobar, Inc. dannyl@lobar.com
Eric Bowen Lobar, Inc. Eric.bowen@lobar.com
Joah Hendrix AIS-Heisey Mechanical Joah.hendrix@ais-york.com
Rick Olson Olson Services olsonsvc@gmail.com
Kevin Reinhard Coastal Engineering kreinhard@c-diving.com
Jeff Picken JP Environmental jpenvironmental@yahoo.com
Oral statements made during this meeting do not modify the contract documents. Any changes, clarifications, or interpretations of the bidding documents will only become binding if issued via a formal, written addendum.
The following was discussed:
Question and Answers/Clarifications:
Q1: A potential bidder raised the concern that they may not have the gates in hand by the April 30th completion date that is in the Project Manual once considering time spent awarding the project, getting approved shop drawings, and the potential lead times associated with the gates.
Answer: The existing gates were supplied by North East Technical Sales. Marc Gradwohl, who can be reached via email at marc.gradwohl@mceautomation.com or via phone at 610-283-4551, is the sales representative for the named gates, which will match the bolt pattern of the existing gates. This is not to say that other manufacturers are unable to supply the replacement gates. We believe that it would be in the contractor’s best interest to use gates that will match the existing bolt pattern, instead of having to install new bolts as would be necessary. The project manual states that if another manufacturer is to be used, coordination will be prerequired between the
Contractor, the Manufacturer, and the Engineer to ensure that the alternative gates will match the bolt pattern of the existing gates.
mailto:marc.gradwohl@mceautomation.com
Sunbury Municipal Authority
Equalization Basin Gates Replacement
Pre Bid Meeting – October 15, 2026
We reached out to Marc Gradwohl to verify that Marc believed that the gates can be ordered and delivered in time to meet the project deadline. Marc subsequently indicated that 8-10 weeks would be required for delivery after receipt of approved Shop Drawings.
If a supply chain issue would cause a delay that would prevent the Contractor from completing this project by the April 30th deadline, a request for a time extension can be submitted from the
Contractor as soon as a time issue is discovered. The Authority would like to have the gates installed by April 30th in order to have the gates in place in time for spring rain events.
Q2: A potential bidder asked for clarification on the Engineer’s request to replace the hardware but use the existing bolt pattern when installing the new gates.
Answer: The Engineer is envisioning using the existing bolt pattern/existing bolts that are currently in the tanks when installing the new gates, and adding new washers and nuts to fasten the new gates to the existing bolts. If it is determined that the bolts must be removed from the tank for some reason during construction, this will be handled by a change order.
Q3: A potential bidder asked if shop drawings for the existing gates can be provided.
Answer: We have reached out to Nort East Technical Sales and Sunbury Municipal Authority is also looking for their file copy. We will provide them if they are found.
Q4: A potential bidder asked for clarification on when to order the gates if only the Base Bid for 5 gates will be awarded.
Answer: The Base Bid is for the 5 gates on the Southernmost Tank. There are additional gates in the next 2 tanks that we are also requesting pricing for. The Contract award will clearly spell out how many gates are to be supplied at award.
Q5: A potential bidder asked if the tanks can be bypassed when working on the gates in a given tank.
Answer: Yes, the tank will be dewatered and sludge will be removed for the Contractor to perform the replacement work, given that enough time is given for the Authority to dewater the requested tank and remove any sludge. In all regards, the Contractor will need to coordinate with Authority staff as this is a working plant.
The Authority will make the tanks as clean as possible in-house before this project begins. If there is a major wet weather event or a flood, this may prevent the Equalization Basin (the southernmost tank) from being dewatered. Two of the tanks also have diffusers in the tanks, as they provide aeration. A cross-section of the tanks will be provided via addendum for clarification.
Other Items:
Sunbury Municipal Authority
Equalization Basin Gates Replacement
Pre Bid Meeting – October 15, 2026
Clarification was provided on the Tank Setup. As portions of the sewer system are a combined sewer system, the 3 gates on the Equalization Basin (the southernmost tank) are what stops the flow from immediately coming into the tank. If there is a flood event, the Equalization Basin will begin filling with water. The 5 gates that are in the Base Bid are in the Equalization Tank, and this tank is typically not in service. The other tanks that have gates are aeration tanks and are typically in service, but can be cycled out of service for this project.
There were no questions posted on PennBid by October 15. Questions will be accepted on PennBId until October 22nd. If there are major issues discovered with these plans or project manual, please notify us as early as possible.
Q6: A site visit of the tanks was held following this pre bid meeting, where a potential bidder asked if the neighboring property on the other side of the fence can be used to operate a crane.
Answer: Maybe. The property on the other side of the fence is owned by the Authority and could be used by the Contractor if coordinated with the Authority & the ACOE’s because it is part of the
Levy system.
Drawing Addenda:
The Attached Sketch is provided for informational purposes, and is added to Sheet C-501.
Specification Addenda:
None.
End of Addendum No. 1