4-25-188-B Addendum No. 2 2025-08-04.pdf
PDF 178 KB Posted
- Solicitation number
- 25-188-B
- Issued by
- Collin County, Texas
About this file
This document is an Addendum No. 2 for Request for Bid (RFB) No. 25-188-B issued by the North Texas Municipal Water District (NTMWD), specifically addressing an Outbound Scale Replacement project at the SH121 Regional Disposal Facility. The addendum modifies the original solicitation by revising the Special Conditions section to clarify that the agreement term will be two (2) years, commencing on the date of the last signatory. The document includes a response to a potential bidder's question about estimated cost, to which NTMWD indicated no estimated cost is available.
The addendum requires respondents to acknowledge receipt by signing and returning the document with their submittal. No specific pricing details, funding sources, or additional project specifics are provided in this document. The primary purpose appears to be a procedural update to the contract duration and an opportunity for potential bidders to formally acknowledge the changes to the original solicitation. The document is signed by Adrienne Conyer, Senior Buyer in the Procurement Department of the North Texas Municipal Water District.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-25-188-B Solicitation Packet 2025-07-16.pdf | ||
| 3-25-188-B Addendum No. 1 2025-07-23.pdf | ||
| 5-25-188-B Bid Tab - As Read 2025-08-13.pdf | ||
| 1-25-188-B Bid Pricing Form 2025-07-17.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP No. 25-188-B Page 1 of 1 Addendum No. 2
August 4, 2025
Re: Addendum No. 2
RFB No. 25-188-B Outbound Scale Replacement at SH121 Regional Disposal Facility.
Please be advised of the following change(s) to the above referenced solicitation.
CHANGE 1:
1. Revise Special Conditions, 3. Duration of Agreement, A, to read as follows:
The term of this agreement shall commence on the date of the last signatory and shall be for a period of two (2) years.
QUESTIONS RECEIVED PRIOR TO THE DEADLINE
QUESTION 1: Is an estimated cost available?
ANSWER 1: No, we do not have an estimated cost.
THE ADDITIONS, DELETIONS, MODIFICATIONS, AND/OR CLARIFICATIONS TAKE
PRECEDENCE OVER THE INITIAL SOLICITATION AND SHALL BE MADE TO THE
APPROPRIATE SECTIONS OF THE REFERENCED DOCUMENT AND SHALL BECOME
PART OF THE CONTRACT DOCUMENTS. THE ORIGINAL REQUIREMENTS NOT
AFFECTED BY THIS ADDENDUM SHALL REMAIN IN EFFECT.
RESPONDENTS SHALL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM FOR RFB NO.
25-188-B BY SIGNING BELOW AND RETURNING THIS ADDENDUM WITH THE
SUBMITTAL.
Company Name
Signed Date
Respectfully, Adrienne Conyer Adrienne Conyer Senior Buyer Procurement Department North Texas Municipal Water District
RFB No. 25-188-B