3MD0395 Post Award Schedule.pdf

PDF 12 KB Posted

Attached to
Lease of Office Space within Region 3. Request for Lease Proposals (RLP) #25REG03 - Office Space
Solicitation number
3MD0395_2
Issued by

About this file

This is a post-award schedule attachment for a GSA lease project that outlines the timeline of activities following lease award. The schedule begins within 5 working days of lease award and details the design and construction process through space acceptance.

The schedule specifies key milestones including: Design Kick-Off Meeting (10 days after award), Lessor-Provided Design Intent Drawings (20 days), Construction Documents (15 days), TI and BSAC Price Proposal (20 days), TI Negotiations (50 days), Construction Kick-Off Meeting (10 days), Construction Completion (60 days), Final Inspections (10 days), and Punchlist Completion (10 days). This schedule replaces section 1.05 of the RLP (R100) and relates to section 4.01 of Lease L100.

View the file

Other files

File Type Posted
3MD0395 AAAP Advertisement 1.17.pdf PDF
3MD0395 Boundary.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Design Kick-Off Meeting with Lessor, GSA, & Agency 10 days after lease award

Lessor-Provided Design Intent Drawings 20 Days

Lessor Preparation and Submission of Construction Documents 15 Days

Lessor Preparation and Submission of the TI and BSAC Price Proposal

20 Days

TI Negotiations Completed 50 days

Construction Kick Off Meeting 10 days

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

60 days

Final Inspections/Government Acceptance 10 Days

Punchlist Completed 10 Days