This is a post-award schedule attachment for a GSA lease project that outlines the timeline of activities following lease award. The schedule begins within 5 working days of lease award and details the design and construction process through space acceptance.
The schedule specifies key milestones including: Design Kick-Off Meeting (10 days after award), Lessor-Provided Design Intent Drawings (20 days), Construction Documents (15 days), TI and BSAC Price Proposal (20 days), TI Negotiations (50 days), Construction Kick-Off Meeting (10 days), Construction Completion (60 days), Final Inspections (10 days), and Punchlist Completion (10 days). This schedule replaces section 1.05 of the RLP (R100) and relates to section 4.01 of Lease L100.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 3MD0395 AAAP Advertisement 1.17.pdf | ||
| 3MD0395 Boundary.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Design Kick-Off Meeting with Lessor, GSA, & Agency 10 days after lease award
Lessor-Provided Design Intent Drawings 20 Days
Lessor Preparation and Submission of Construction Documents 15 Days
Lessor Preparation and Submission of the TI and BSAC Price Proposal
20 Days
TI Negotiations Completed 50 days
Construction Kick Off Meeting 10 days
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
60 days
Final Inspections/Government Acceptance 10 Days
Punchlist Completed 10 Days