The Grange Hall Renovation pre-bid meeting was called to order at 11:03 by Loren Salsman. Present were Glenn Layaou (Milnes Companies), Loren Salsman (Salsman Engineering), Matt Hilstalely (H&G Mechanical), Dan Hineline (Multiscape G. C.), Gary Johnson (D&M Construction), Chris Wodock (Wodock Construction), Mike Valenzano (Mar- Paul Construction), Eric Lewis (Spectrum Electric), Cli ord Reed, Dennis & Rachel Magargal, Lori Raub, Darin DeRose, Stephen Roe, and Alicia Tompkins.
Loren spoke on the grant audit, OSHA 10 training requirement, Sexual Harassment policy, and the scopes o� work being separated into 4 bids. Loren also mentioned that there is a sliding window not mentioned in the plans, as well as a light switch location shown incorrectly on the o ice plans. The light switches should be near the doorways in both o ices. Loren stated that the mini split system in the plans was specified by Hinds Energy in Montrose, the key �ob system was specified by True Blue Security (Eric Saga), and the generator was specified by Lawton power systems (Vicky St Clair).
There were concerns raised that the generator is sized �or double the load needed, it was confirmed that this is the correct.
Loren clarified that the Scope o� Work was provided to di erentiate the work involved with each contract. The Scope o� Work is not necessarily all inclusive o� every item o� work listed on the plans. Also, Loren noted that the Grant �or the Project requires an audit, and the contractors shall include all administrative and other costs required to complete the audit requirements.
It was clarified that the key �ob system is in the electrical package. The scope �or exterior wall was clarified stating it includes stripping the siding, installing zip wall system, Low E wrap and certainty vinyl siding. The “original look” is to be kept as much as possible. The scope �or the roo� was also clarified stating it includes stripping, installing zip roo�, and ra�ter tails need to be replaced on an as needed basis. It was stated that R23 needs to be achieved by whatever means necessary in order to meet code.
Questions regarding light fixtures were raised and it was specified that the lights are to be 2x2 lights in drop ceiling, and 6” LED pucks everywhere else, but the exterior lights still need to be picked.
Questions were also raised regarding the leveling o� the first floor and the load bearing needed �or the floor trusses to the second floor. It was decided that these will be clarified in an addendum.
September 2nd is the deadline �or questions & RFI’s. The bidders were then welcomed to assess the building.