This Statement of Work (SOW) details a contract for cathodic protection system inspection and testing at the U.S. Coast Guard Training Center in Petaluma, California. The contract covers yearly inspection and testing of five specific tanks (T-180, T-132, T-133, T-135, and T-136), including electrical measurements, potential profiling, rectifier inspection, and system adjustments. The contractor must provide qualified personnel to conduct comprehensive annual assessments and submit detailed reports with data evaluation and performance recommendations.
The contract has a base period from June 23, 2025, through June 22, 2026, with four additional one-year option periods extending through June 22, 2030. Work will be performed at the Petaluma Training Center, primarily during standard business hours (0800-1530 PST, Monday-Friday), with potential for occasional weekend or holiday work. The contractor is responsible for providing all necessary equipment, materials, and services, and must comply with government facility regulations, including wearing proper identification and maintaining professional conduct.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 7m - Wage Determination.pdf | ||
| 7m - WHD-1313.pdf | ||
| 12a - Provisions and Clauses.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #: 61200PR250000120
STATEMENT OF WORK
LAST UPDATED: 05/20/2025 PAGE 1/3
STATEMENT OF WORK (SOW)
FOR
Cathodic Protection System Inspection and Testing
1.0 GENERAL
1.1 BACKGROUND
U.S. Coast Guard (USCG) Training Center (TRACEN) Petaluma located at 599 Tomales Road Petaluma; CA 94952 is the Coast Guard’s largest West Coast Training Center. Our graduates are the latest chefs, medics, storekeepers, yeoman, information systems technicians, electronics technicians, operations specialists, and aviation survival technicians (AST). We are also home to the Coast Guard Leadership Development Center’s Chief Petty Officer Academy.
This project is to inspect and test the cathodic proection system at the TRACEN Petaluma’s site over the next 5 years starting in 2026.
1.2 SCOPE
The contractor must provide inspection and tesing services for Training Center (TRACEN) Petaluma’s cathodic protection system for five (05) tanks.
1.3 OBJECTIVE
The contractor must provide all labor, equipment, materials, vehicles, and appliances necessary to perform all operations in conncection with tank inspection and testing of five (5) government owned tanks at various locations throughout U.S. Coast Guard TRACEN Petaluma located at 599 Tomales Rd, Petaluma, CA 94952. See exhibit one (1) for detailed location and capacities of tanks.
2.0 TASK ONE. YEARLY INSPECTION AND TESTING OF FIVE (5) CATHODIC
PROTECTION SYSTEMS
2.1 The Contractor must conduct the following once a year on the following tanks: T-180, T-132, T-133, T-135 and T-136.
• Tank to water potential profile within tank to monitor and verify effectiveness of system on submerged surface of tank.
• Electrical measurements to test anode and reference cells.
• Inspect, test and clean rectifier, controls, meters, contacts, wiring and connections.
• Replace fuses as required.
• Adjust system for optimum corrosion control on submerged metal surface of tank and submit a report with all data obtained, evaluation of data and recommendations for continues performance.
3.0 CONTRACTOR PERSONNEL
3.1 QUALIFIED PERSONNEL
The Contractor must provide qualified personnel to perform all requirements specified in this
SOW.
3.2 CONTINUITY OF SUPPORT
The Contractor must ensure that the contractually required level of support for this requirement is maintained at all times. The Contractor must ensure that all contract support personnel are present for all hours of the workday. If for any reason the Contractor staffing levels are not https://uscg.sharepoint-mil.us/sites/cg9/ARM/SCOPE%20PARAGRAPHS.doc
LAST UPDATED: 05/20/2025 PAGE 2/3
maintained due to vacation, leave, appointments, etc., and replacement personnel will not be provided, the Contractor must provide e-mail notification to the Government Technical Representative prior to employee absence. Otherwise, the Contractor must provide a fully qualified replacement.
3.3 EMPLOYEE IDENTIFICATION
3.3.1 Contractor employees visiting Government facilities must wear an identification badge that, at a minimum, displays the Contractor name, the employee’s photo, name, clearance-level and badge expiration date. Visiting Contractor employees must comply with all Government escort rules and requirements. All Contractor employees must identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times.
3.3.2 Contractor employees working on-site at Government facilities must wear a Government issued identification badge. All Contractor employees must identify themselves as Contractors when their status is not readily apparent (in meetings, when answering Government telephones, in e-mail messages, etc.) and display the Government issued badge in plain view above the waist at all times.
3.4 EMPLOYEE CONDUCT
3.4.1. Contractor’s employees must comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, wearing of parts of DHS uniforms, and possession of weapons) when visiting or working at Government facilities. The Contractor must ensure Contractor employees present a professional appearance at all times and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Project Manager must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.5 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Government Technical Representative), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons. Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer will provide the Contractor with a written explanation to support any request to remove an employee.
4.0 OTHER APPLICABLE CONDITIONS
4.1 SECURITY
Contractor access to classified information is not currently required under this SOW
4.2 PERIOD OF PERFORMANCE
The period of performance for this contract is a one-year base period with four one-year option periods as follows:
Base Period June 23, 2025 through June 22, 2026 Option Period One June 23, 2026 through June 22, 2027
LAST UPDATED: 05/20/2025 PAGE 3/3
Option Period Two June 23, 2027 through June 22, 2028 Option Period Three June 23, 2028 through June 22, 2029 Option Period Four June 23, 2029 through June 22, 2030
4.3 PLACE OF PERFORMANCE
U.S. Coast Guard (USCG) Training Center (TRACEN) Petaluma located at 599 Tomales Road, Petaluma, CA 94952-4154.
4.4 HOURS OF OPERATION
Contractor employees must generally perform all work between the hours of 0800 through 1530 PST, Monday through Friday (except Federal holidays). However, there may be occasions when Contractor employees must be required to work other than normal business hours, including weekends and holidays, to fulfill requirements under this SOW.
4.5 TRAVEL
Contractor travel must not be required for this requirement.
4.6 GENERAL REPORT REQUIREMENTS
The Contractor must provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).
5.0 GOVERNMENT FURNISHED RESOURCES
The Government will not furnish any resources to the Contractor in support of this contract.
6.0 CONTRACTOR FURNISHED PROPERTY
The Contractor must furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract, except for the Government Furnished Resources specified in SOW 2.0 and SOW 5.0.