This notice is a pre-solicitation for Architect and Engineering services to support the BLDG 2272 Gold Rush Inn Renovation project located at Eielson Air Force Base in Alaska. The Department of the Air Force Pacific Air Forces is seeking these services, with questions regarding the solicitation due by March 21, 2024 at 2 pm Alaska Daylight Time. Funds have not been allocated for this effort yet, so no award will be made until funding is available. The Government may cancel this notice before or after the closing date without obligation to reimburse any offerors for costs. Interested parties should refer to the attached project attachments for submission instructions and details.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A-18 - 37 OF 228 - DETAILS II
| AF21-01-0030 - A-16 - SHEE - DORMITORY - EXTERIOR WALL SECTIONS I |
| AF21-01-406 - E-1 - DORMITORY LEGEND AND FIXTURE SCHEDULE |
| AF25-22-01 - A-000 - SHEET - FIRE PROTECTION PLAN SECONDTHIRD FLOOR PLANS |
| AF25-22-01 - A-00 - FIRE PROTECTION PLAN FIRST FLOOR PLANS |
| AF25-22-01 - A-0 - 7 - ABBREVIATIONS - SYMBOLS - PARTITION TYPES |
| AF25-22-01 - A-2 - 1 - PHASE II - OVERALL FIRST FLOOR PLAN |
| AF25-22-01 - A-2A - PHASE II - OVERALL SECONDTHIRD FLOOR PLAN |
| AF25-22-01 - A-6 - 2 - PHASE II - NORTH WING FIRST FLOOR PLAN |
| AF25-22-01 - A-6A - PHASE II - SOUTH WING FIRST FLOOR PLAN |
| AF25-22-01 - A-7 - 2 - PHASE II - NORTH WING SECOND FLOOR PLAN |
| AF25-22-01 - A-7A - PHASE II - SOUTH WING SECOND FLOOR PLAN |
| AF25-22-01 - A-8 - 2 - PHASE II - NORTH WING THIRD FLOOR PLAN |
| AF25-22-01 - A-8A - PHASE II - SOUTH WING THIRD FLOOR PLAN |
| AF25-22-01 - A-9 - 2 - ENLARGED PLANS |
| AF25-22-01 - A-10 - ENLARGED STAIR PLANS |
| AF25-22-01 - A-11 - ROOF PLAN AND DETAILS |
| AF25-22-01 - A-13 - PHASE II - PARTIAL EXTERIOR ELEVATIONS - EAST WING |
| AF25-22-01 - A-13A - SHEET - PHASE II - EXTERIOR ELEVATIONS NORTH AND EAST |
| AF25-22-01 - A-14 - BUILDING SECTIONS I |
| AF25-22-01 - A-15 - BUILDING SECTIONS II |
| AF25-22-01 - A-17 - DETAILS I |
| AF25-22-01 - A-19 - DETAILS II |
| AF25-22-01 - A-20C - SHEET - PHASE II - DOOR SCHEDULE - FIRST FLOOR |
| AF25-22-01 - A-20D - SHEET - PHASE II - DOOR SCHEDULE - SECOND FLOOR |
| AF25-22-01 - A-20E - SHEET - PHASE II - DOOR SCHEDULE - THIRD FLOOR |
| AF25-22-01 - A-21 - DORMITORY - DOOR AND WINDOW DETAILS |
| AF25-22-01 - A-23 - PHASE II - ROOM FINISH SCHEDULE |
| AF25-22-01 - A-27 - PHASE II - REFLECTED CEILING PLAN NORTH WING FIRST |
| AF25-22-01 - A-27A - SHEET - PHASE II - REFLECTED CEILING PLAN SOUTH WING FIRST |
| AF25-22-01 - A-28 - PHASE II - REFLECTED CEILING PLAN - NORTH WING SECO |
| AF25-22-01 - A-28A - SHEET - PHASE II - REFLECTED CEILING PLAN - SOUTH WING SECO |
| AF25-22-01 - A-29 - PHASE II - REFLECTED CEILING PLAN - NORTH WING THIR |
| AF25-22-01 - A-29A - SHEET - PHASE II - REFLECTED CEILING PLAN - SOUTH WING THIR |
| AF25-22-01 - A-30 - INTERIOR ELEVATIONS I |
| AF25-22-01 - A-31 - INTERIOR ELEVATIONS II |
| AF25-22-01 - C-4 - 5 - PHASE I AND PHASE II - DETAILS |
| AF25-22-01 - E-2 - 1 - SITE PLAN AND DETAIL |
| AF25-22-01 - E-4 - 1 - PHASE II - POWER ONE-LINE DIAGRAM NORTH AND SOUTH |
| AF25-22-01 - E-11 - PHASE II - LIGHTING PLAN - NORTH WING FIRST FLOOR |
| AF25-22-01 - E-12 - PHASE II - LIGHTING PLAN - SOUTH WING FIRST FLOOR |
| AF25-22-01 - E-13 - PHASE II - LIGHTING PLAN - NORTH WING FIRST FLOOR |
| AF25-22-01 - E-14 - PHASE II - LIGHTING PLAN SOUTH WING SECOND FLOOR P |
| AF25-22-01 - E-15 - PHASE II - LIGHTING PLAN NORTH WING THIRD FLOOR PL |
| AF25-22-01 - E-16 - PHASE II - LIGHTING PLAN SOUTH WING FLOOR PLAN |
| AF25-22-01 - E-23 - POWER PLAN - NORTH WING FIRST FLOOR PLAN |
| AF25-22-01 - E-24 - PHASE II - POWER PLAN SOUTH WING FIRST FLOOR PLAN |
| AF25-22-01 - E-25 - PHASE II - POWER PLAN NORTH WING SECOND FLOOR PLAN |
| AF25-22-01 - E-26 - PHASE II - POWER PLAN SOUTH WING SECOND FLOOR PLAN |
| AF25-22-01 - E-27 - PHASE II - POWER PLAN NORTH WING THIRD FLOOR PLAN |
| AF25-22-01 - E-28 - PHASE II - POWER PLAN SOUTH WING THIRD FLOOR PLAN |
| AF25-22-01 - E-29 - PHASE II - PANEL SCHEDULE N. WING 2ND AND 3RD FLR. |
| AF25-22-01 - E-33 - PHASE II - PANEL SCHEDULE WING 1ST - 2ND AND 3R |
| AF25-22-01 - E-34 - PHASE II - PANEL SCHEDULE SO. WING 1ST - 2ND AND 3R |
| AF25-22-01 - E-45 - PHASE TWO FIRST FLOOR PLAN |
| AF25-22-01 - E-46 - PHASE TWO SECOND FLOOR PLAN |
| AF25-22-01 - E-47 - PHASE TWO THIRD FLOOR PLAN |
| AF25-22-01 - E-48 - FACP AND TYPICAL DETAILS |
| AF25-22-01 - E-51 - PHASE TWO TELEPHONE RISER DIAGRAM |
| AF25-22-01 - E-52 - PHASE TWO CABLE TV RISER DIAGRAM |
| AF25-22-01 - FG-7 - SPRINKLER SYSTEM N. WING 1ST FLOOR |
| AF25-22-01 - FG-7A - SHEET - SPRINKLER SYSTEM N. WING 1ST FLOOR |
| AF25-22-01 - FG-8 - SPRINKLER SYSTEM S. WING 1ST FLOOR |
| AF25-22-01 - FG-8A - SHEET - SPRINKLER SYSTEM BUILDING SECTION |
| AF25-22-01 - FG-9 - SPRINKLER SYSTEM N. WING 2ND FLOOR |
| AF25-22-01 - FG-9A - SHEET - SPRINKLER SYSTEM N. WING 2ND FLOOR |
| AF25-22-01 - FG-10 - SHEET - SPRINKLER SYSTEM S. WING 2ND FLOOR |
| AF25-22-01 - FG-11 - SHEET - SPRINKLER SYSTEM N. WING 3RD FLOOR |
| AF25-22-01 - FG-11A - SHEE - SPRINKLER SYSTEM N. WING 3RD FLOOR |
| AF25-22-01 - FG-12 - SHEET - SPRINKLER SYSTEM S. WING 3RD FLOOR |
| AF25-22-01 - I-4 - 6 - PHASE II - DOOR COLOR SCHEDULE - FIRST FLOOR |
| AF25-22-01 - I-5 - 6 - PHASE II - DOOR COLOR SCHEDULE - FIRST FLOOR |
| AF25-22-01 - I-6 - 6 - PHASE II - DOOR COLOR SCHEDULE - THIRD FLOOR |
| AF25-22-01 - I-9 - 7 - PHASE II - FLOOR 1 - ROOM FINISH COLOR SCHEDULE |
| AF25-22-01 - I-10 - PHASE II - FLOOR 2 AND 3 - ROOM FINISH COLOR SCHED |
| AF25-22-01 - LS-1 - PHASE I AND PHASE II - GRADING PLAN |
| C-1 - 2 OF 228 - PHASE I AND PHASE II - GRADING PLAN |
| C-3 - 4 OF 228 - PHASE I AND PHASE II - SECTIONS |
| C-5 - 6 OF 228 - PHASE I AND PHASE II - UTILIDOR PROFILES |
| CU-1 - 104 OF 228 - UTILIDOR PLAN AND GENERAL NOTES |
| CU-2 - 105 OF 228 - PARTIAL PLANS |
| CU-3 - 106 OF 228 - MISC. SECTIONS AND DETAILS |
| CU-4 - 107 OF 228 - MISC. DETAILS |
| M-1 - 115 OF 228 - LEGEND AND SCHEDULES |
| M-2A - 117 OF 228 - EQUIPMENT SCHEDULE |
| M-3 - 118 OF 228 - FIRST FLOOR HEATING PLAN- NORTH |
| M-4 - 119 OF 228 - FIRST FLOOR HEATING PLAN- SOUTH |
| M-5 - 120 OF 228 - SECOND FLOOR HEATING AND VENTILATION PLAN- NORTH |
| M-6 - 121 OF 228 - SECOND FLOOR HEATING AND VENTILATION PLAN- SOUTH |
| M-7 - 122 OF 228 - THIRD FLOOR HEATING AND VENTILATION PLAN- NORTH |
| M-8 - 123 OF 228 - THIRD FLOOR HEATING AND VENTILATION PLAN- SOUTH |
| M-9 - 124 OF 228 - FIRST FLOOR MECHANICAL ROOM |
| M-10 - 125 OF 228 - FIRST FLOOR MECHANICAL ROOM |
| M-11 - 126 OF 228 - THIRD FLOOR FAN ROOM PLANS AND SECTIONS |
| M-12 - 127 OF 228 - HEATING AND VENTILATION DETAILS |
| M-23 - 138 OF 228 - PHASE I AND II - HEATING SCHEMATIC |
| M-24 - 139 OF 228 - PHASE II - FIRST FLOOR VENTILATION PLAN - SOUTH |
| M-25 - 140 OF 228 - PHASE II - FIRST FLOOR VENTILATION PLAN - NORTH |
| M-28 - 143 OF 228 - CONTROL SCHEMATICS |
| M-29 - 144 OF 228 - CONTROL SCHEMATICS |
| M-30 - 145 OF 228 - HEATING AND VENTILATION DETAILS |
| P-2 - 147 OF 228 - PHASE II - UNDER FLOOR PLUMBING PLAN SOUTH |
| P-5 - 150 OF 228 - PHASE II - SECONDTHIRD PLUMBING PLAN NORTH |
| P-13 - 158 OF 228 - PLUMBING DETAILS AND ISOMETRICS |
| P-14 - 159 OF 228 - PLUMBING DETAILS AND ISOMETRICS |
| S-1 - 72 OF 228 - GENERAL STRUCTURAL NOTES |
| S-8 - 79 OF 228 - PHASE II - PARTIAL FOUNDATION PLAN - WEST WING |
| S-9 - 80 OF 228 - PHASE II - PARTIAL FOUNDATION PLAN - NORTH WING |
| S-10 - 81 OF 228 - PHASE II - PARTIAL 2ND AND 3RD FLOOR PLAN - WEST W |
| S-11 - 82 OF 228 - PHASE II - PARTIAL 2ND AND 3RD FLOOR PLAN - NORTH |
| S-12 - 83 OF 228 - PHASE II - PARTIAL ROOF FRAMING PLAN - WEST WING |
| S-13 - 84 OF 228 - PHASE II - PARTIAL ROOF FRAMING PLAN - NORTH WING |
| S-14 - 85 OF 228 - FOUNDATION DETAILS |
| S-15 - 86 OF 228 - FOUNDATION DETAILS |
| S-16 - 87 OF 228 - FOUNDATION DETAILS |
| S-17 - 88 OF 228 - SECTIONS AND DETAILS |
| S-17A - 89 OF 228 - SECTIONS AND DETAILS |
| S-18 - 90 OF 228 - PRECAST CONCRETE PANELS |
| S-19 - 91 OF 228 - PRECAST CONCRETE PANELS |
| S-19A - 92 OF 228 - PRECAST CONCRETE PANELS |
| S-19B - 93 OF 228 - PRECAST CONCRETE PANELS |
| S-20 - 94 OF 228 - SECTIONS AND DETAILS |
| S-21 - 95 OF 228 - SECTIONS AND DETAILS |
| S-22 - 96 OF 228 - TYPICAL CONNECTION DETAILS |
| S-23 - 97 OF 228 - TYPICAL BEAM CONNECTION DETAILS |
| S-24 - 98 OF 228 - FRAMING SECTIONS AND DETAILS |
| S-25 - 99 OF 228 - FRAMING ELEVATIONS |
| S-26 - 100 OF 228 - STRUCTURAL FRAMING ELEVATIONS |
| S-27 - 101 OF 228 - SECTIONS AND DETAILS |
| S-28 - 102 OF 228 - SECTIONS AND DETAILS |
| S-29 - 103 OF 228 - PHASE I AND PHASE II - CANOPY DETAILS |
| TITLE SHEET |
| U-1 - 108 OF 228 - UTILITIES PLAN |
| U-2 - 109 OF 228 - UTILIDOR PLANS AND PROFILES |
| U-3 - 110 OF 228 - UTILIDOR PLAN AND PROFILES |
| U-4 - 111 OF 228 - MANHOLE PLANS AND SECTIONS |
| U-5 - 112 OF 228 - PHASE I AND PHASE II - MANHOLE PLANS AND SECTIONS |
| U-6 - 113 OF 228 - UTILIDOR SECTIONS |
| U-7 - 114 OF 228 - UTILIDOR DETAILS |