3928-22 - ITB for Aquifer Storage and Recovery ASR 3 Facility - Advertisement.pdf

PDF 170 KB Posted

Attached to
Portable pull behind, trailer-type air curtain burner / incinerator.
Solicitation number
S-24800-00003563
Issued by
Union County, Oregon

About this file

This is a Legal Bid Advertisement for an Invitation to Bid (ITB) issued by the City of Beaverton, Oregon, for the construction of an Aquifer Storage and Recovery (ASR) 3 Facility and associated improvements under CIP projects 4021G, 4197, 4218, and 4220 (Solicitation #3928-22). The project encompasses comprehensive water infrastructure development including construction of a CMU mechanical/electrical building with UV treatment reactors and chlorine generation systems, ASR wellhead improvements with submersible pumps and valve vaults, a mechanically stabilized earth retaining wall, a stormwater treatment system with filtration equipment, installation of purple pipe water mains and connections to existing systems, site clearing and grading, electrical service upgrades, landscaping, fencing with automated vehicle access gates, and site restoration. Bids must be submitted electronically by 2:00 P.M. on August 4, 2022, to Equity Hub's Bid Locker at the specified URL, with First-tier Subcontractor Disclosure Forms due by 4:00 P.M. the same day. A mandatory pre-bid conference will be held remotely via Zoom on July 12, 2022, at 2:00 P.M., with the deadline for submittal questions set for July 25, 2022. Bid opening will occur virtually via Zoom, and failure to attend the mandatory pre-bid meeting will result in the bidder's bid being deemed non-responsive.

The contract is subject to state prevailing wage rates under ORS 279C.800 to 279C.870 and federal prevailing wage rates under the Davis-Bacon Act for specific work items (CIP #4021G and CIP #4197) as identified in Exhibit 2's WIFIA Contract Requirements. All bids must include a statement confirming compliance with applicable prevailing wage provisions. Plans and specifications are available through the Bid Locker registration portal. For project inquiries, contact Brian Diaz, Project Manager, at bdiaz@beavertonoregon.gov or 971-291-2852. The advertisement was published in the Daily Journal of Commerce on June 24, 2022.

View the file

Other files

File Type Posted
RFQ - Air Curtain Incinerator.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LEGAL BID ADVERTISEMENT

INVITATION TO BID

FOR THE CONSTRUCTION OF AQUIFER STORAGE AND RECOVERY (ASR) 3 FACILITY

ASSOCIATED IMPROVEMENTS, CIP 4021G, 4197, 4218, 4220, Solicitation #3928-22

1. DESCRIPTION OF PROJECT.

i. The Work covered under this Contract will be performed under the Aquifer Storage and Recovery (ASR) 3 Facility project. The project location is indicated on the Drawings.

ii. The Work includes, but is not limited to:

1. Selection and installation of temporary construction shoring systems as required;

2. Construction of a CMU architecturally enhanced ASR mechanical/electrical building to include UV treatment reactors, chlorine generation treatment system and water quality monitoring equipment;

3. Construction of ASR wellhead improvements to include furnishing and installing a vertically suspended submersible pumps with pitless adapters, ASR valves and associated valve vaults;

4. Construct mechanically stabilized earth retaining wall at ASR site;

5. Construction of a stormwater treatment system to filter and treat raw stormwater received by the Sterling Park Stormwater Detention Facility to include a preliminary filter, intermediate filter, granular activated carbon pressure filter, pumping and monitoring systems;

6. Installation of new Summer Creek (beneficial water) pipe to existing Sterling Park lower pond outlet structure;

7. Site clearing, including tree removal, grading and earthwork at City’s reservoir site;

8. Excavation for and backfilling of above components as required for a complete installation;

9. Connection of the new purple pipe water main to existing main lines;

10. Connection of purple pipe system to existing City main for supplemental water;

11. Connection of the new sewer line to existing main lines;

12. Coordination for site access of other projects occurring on the project site, as needed;

13. Site access roads, paved and gravel;

14. Landscaping and screening;

15. Site chain-link fencing and automated vehicle access gate;

16. New electrical service and electrical improvements;

17. System integration by City’s system integrator;

18. Site storm drain system; and

19. Restoration of work site area to original or better condition, including grading, temporary and permanent paving, erosion control, and other measures as required.

iii. The above general outline of principal features of the work does not in any way limit the responsibility of the Contractor(s) to perform all work and furnish all equipment, labor and materials required by the specifications and drawings. The drawings and specifications shall be considered and used together. Anything appearing as a requirement of either shall be accepted as applicable to both even though not so stated therein or shown.

iv. No attempt has been made in these specifications or drawings to segregate work covered by any trade or subcontract under one specification. Such segregation and establishment of subcontract limits will be solely a matter of specific agreement between the Contractor and its subcontractors and shall not be based upon any inclusion, segregation, or arrangement in or of these specifications.

2. DEADLINE. Bids must be submitted by 2:00 P.M. on August 4, 2022. First-tier Subcontractor Disclosure Forms for this project are due no later than 4:00 P.M. on August 4, 2022 to Michael Phillips, Purchasing Manager, at the 2nd Floor Finance Utility Billing Counter by fax, (503) 526-2490, or by email, bidmail@BeavertonOregon.gov.

3. DELIVERY METHODS.

The City will only accept bid packets for this project electronically. Hard copies or facsimiles (fax) will not be accepted. Please scan your bid packet in and submit your bid packet as a pdf document to Equity Hub’s Bid Locker at: https://bidlocker.us/details/3035_Itb_For_Aquifer_Storage_And_Recovery_Asr_3_Facility

a. Time stamp is determined by when the email is received. Bids received after the designated time will not be considered.

4. BID OPENING. Bid opening will be virtual on Zoom: Bidders will be able to attend the bid opening by accessing the web version on Zoom at: https://www.zoomgov.com/my/beavertonprocurement

5. MANDATORY PRE-BID CONFERENCE. A mandatory pre-bid conference for this project will be held remotely via Zoom at https://www.zoomgov.com/my/beavertonprocurement at 2:00 P.M. on July 12, 2022. This conference is to provide prospective Bidders with the opportunity to ask questions related to bidding or building the work under the resulting contract. Questions that cannot be addressed by direct reference to the Bid Documents may be answered through an addendum issued to all plan holders. The deadline for questions is July 25, 2022.

A bidder’s failure to attend the mandatory pre-bid meeting shall cause the bidder’s bid to be deemed non-responsive.

6. LOCATION OF SPECIFICATIONS.

Bidders may obtain plans and specifications for the project by visiting:

https://bidlocker.us/details/3035_Itb_For_Aquifer_Storage_And_Recovery_Asr_3_Facility and registering an account.

7. PREVAILING WAGES. The contract expected to be awarded in connection with this solicitation is subject to the state prevailing wage rates under ORS 279C.800 to 279C.870 and/or the federal prevailing wage rates under the Davis-Bacon Act (40 U.S.C. 3141 et seq.). No Bid will be received or considered by the City unless the Bid contains a statement by the Bidder that “Bidder agrees to be bound by and will comply with the provisions of ORS 279C.838, ORS 279C.840 or 40 U.S.C. 3141 to 3148.” Specifically, the following items in the bid form must comply with the WIFIA Contract Requirements in Exhibit 2, which include the federal prevailing wage rates:

"Common Work"(CIP #4021G), Schedule A (CIP #4021G), and Schedule A.1 (CIP #4197). All other items in the bid form are subject to the state prevailing wage rates.

For more information regarding this project contact Brian Diaz, Project Manager, at bdiaz@beavertonoregon.gov or 971-291-2852.

mailto:bidmail@BeavertonOregon.gov https://www.zoomgov.com/my/beavertonprocurement https://www.zoomgov.com/my/beavertonprocurement https://bidlocker.us/details/3035_Itb_For_Aquifer_Storage_And_Recovery_Asr_3_Facility mailto:bdiaz@beavertonoregon.gov

PUBLISH: Daily Journal of Commerce DATE: June 24, 2022

LEGAL BID ADVERTISEMENT
i. The Work covered under this Contract will be performed under the Aquifer Storage and Recovery (ASR) 3 Facility project. The project location is indicated on the Drawings.
ii. The Work includes, but is not limited to:
1. Selection and installation of temporary construction shoring systems as required;
2. Construction of a CMU architecturally enhanced ASR mechanical/electrical building to include UV treatment reactors, chlorine generation treatment system and water quality monitoring equipment;
3. Construction of ASR wellhead improvements to include furnishing and installing a vertically suspended submersible pumps with pitless adapters, ASR valves and associated valve vaults;
4. Construct mechanically stabilized earth retaining wall at ASR site;
5. Construction of a stormwater treatment system to filter and treat raw stormwater received by the Sterling Park Stormwater Detention Facility to include a preliminary filter, intermediate filter, granular activated carbon pressure filter, pumping an...
6. Installation of new Summer Creek (beneficial water) pipe to existing Sterling Park lower pond outlet structure;
7. Site clearing, including tree removal, grading and earthwork at City’s reservoir site;
8. Excavation for and backfilling of above components as required for a complete installation;
9. Connection of the new purple pipe water main to existing main lines;
10. Connection of purple pipe system to existing City main for supplemental water;
11. Connection of the new sewer line to existing main lines;
12. Coordination for site access of other projects occurring on the project site, as needed;
13. Site access roads, paved and gravel;
14. Landscaping and screening;
15. Site chain-link fencing and automated vehicle access gate;
16. New electrical service and electrical improvements;
17. System integration by City’s system integrator;
18. Site storm drain system; and
19. Restoration of work site area to original or better condition, including grading, temporary and permanent paving, erosion control, and other measures as required.
iii. The above general outline of principal features of the work does not in any way limit the responsibility of the Contractor(s) to perform all work and furnish all equipment, labor and materials required by the specifications and drawings. The draw...
iv. No attempt has been made in these specifications or drawings to segregate work covered by any trade or subcontract under one specification. Such segregation and establishment of subcontract limits will be solely a matter of specific agreement betw...

File details come from the government source that posted it. Updated .