36E77619R0019 ATTACHMENT 2 - FARGO SPEC 01 00 00 - General Requirements - 1-04-2019.docx

View the file

Other files

File Type Posted
36E77619R0019-005.docx DOCX document
36E77619R0019-006.pdf PDF
36E77619R0019-019.pdf PDF
36E77619R0019-008.pdf PDF
36E77619R0019-028.pdf PDF
36E77619R0019-025.zip ZIP file
36E77619R0019-023.docx DOCX document
36E77619R0019-029.pdf PDF
36E77619R0019-022.pdf PDF
36E77619R0019-016.pdf PDF
36E77619R0019-017.pdf PDF
36E77619R0019-014.pdf PDF
36E77619R0019-026.docx DOCX document
36E77619R0019-010.pdf PDF
36E77619R0019-009.pdf PDF
36E77619R0019-015.pdf PDF
36E77619R0019-020.pdf PDF
36E77619R0019-012.pdf PDF
36E77619R0019-007.pdf PDF
36E77619R0019-021.pdf PDF
36E77619R0019-018.pdf PDF
36E77619R0019-013.pdf PDF
36E77619R0019-027.pdf PDF
36E77619R0019-011.pdf PDF
36E77619R0019-030.docx DOCX document
36E77619R0019.docx DOCX document
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

437-18-101 Renovate Pharmacy for USP 800 Compliance – Fargo 1-04-2019

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 GENERAL INTENTION

A. Contractor shall provide design-build services to perform work for Fargo VA Health System, Renovate Pharmacy for USP 800 Compliance – Fargo, 437-18-101, as required by schematic drawings and contract documents.

B. Visits to the site by Contractors, subcontractors, suppliers / vendors will be coordinated with the VA on site Contracting Officer’s Representative (COR). During the solicitation period, site visits are to be made in accordance with the solicitation and Contracting Officer.

C. In connection with this contract, any in-house personnel, subcontractors, and outside associates or consultants will be limited to individuals or firms that were specifically identified in the Contractor's accepted proposal. The Contractor shall obtain the Contracting Officer's written consent before making any substitution for these designated in-house personnel, subcontractors, associates, or consultants. If the Contractor proposes a substitution, it shall submit the same type of information that was submitted in the accepted proposal to the Contracting Officer for evaluation and approval. The level of qualifications and experience submitted in the accepted proposal or that required by the Solicitation, whichever is greater, is the minimum standard for any substitution.

D. The contractor's construction management key personnel shall be actively involved during the design process to effectively integrate the design and construction requirements of this contract. In addition to the typical required construction activities, the Contractor's involvement includes, but is not limited to actions such as: integrating the design schedule into the Master Schedule to maximize the effectiveness of fast-tracking design and construction (within the limits allowed in the contract), ensuring constructability and economy of the design, integrating the shop drawing and installation drawing process into the design, executing the material and equipment acquisition programs to meet critical schedules, effectively interfacing the construction quality control (QC) program with the design QC program, and maintaining and providing the design team with accurate, up-to-date redline and as-built documentation. The Contractor shall require and manage the active involvement of key trade subcontractors in the above activities.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain I.D. Badges from VA.

F. Prior to commencing work, general contractor shall provide proof that a OSHA designated “competent person” (CP) (29 CFR 1926.20(b)(2) will maintain a presence at the work site whenever the general or subcontractors are present.

G. Training:

1. All employees of general contractor or subcontractors shall have the 10-hour General Laborers or 30-hour Supervisors OSHA Construction Safety course and other relevant competency training, as determined by PE/COR acting as the Construction Safety Officer with input from the facility Construction Safety Committee.

2. Submit training records of all such employees for approval before the start of work.

H. VHA Directive 2011-36, Safety and Health during Construction, dated 04/06/2017 in its entirety is made a part of this section

1.2 Statement of Bid Items

A. ITEM I, Design & Construction Documents: Work includes all labor, material, equipment and supervision to furnish the required documents for construction including Drawings, Specifications, construction cost estimates, and other documents as necessary.

B. ITEM II, Construction: Work includes general construction, alterations, necessary removal of existing structures and construction and certain other items.

Work includes all labor, material, equipment and supervision to perform the required electrical construction work including lighting, power, low voltage, equipment and certain other items.
Work includes all labor, material, equipment and supervision to perform the required Plumbing & Mechanical construction work on this project including replacement of ductwork, diffusers, exhaust, plumbing, fire protection and various other items.

1.3 Not USed

1.4 Not used

1.5 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A.AFTER AWARD OF CONTRACT, 0 sets of specifications and drawings will be furnished.
B.Additional sets of drawings may be made by the Contractor, at Contractor's expense, from files downloaded from the projects FedBizOpps.gov Site.

1.6 CONSTRUCTION SECURITY REQUIREMENTS

A.Security Procedures:
1.General contractor’s employees and subcontractors employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2.For working outside the “regular hours” as defined in the contract, the general contractor shall give a minimum of 21 calendar days’ notice to the Contracting Officer so that notice can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3.No photography of VA premises is allowed without written permission of the Contracting Officer.
4.VA reserves the right to close or shut down the project site and order general contractor’s employees off the premises in the event of an emergency. The general contractor may return to the site only with the written approval of the Contracting Officer.
B.Document Control:
1.The general contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
2.These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.
3.All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

1.7 FIRE SAFETY

A.Applicable Publications: Publications listed below form part of this Article to extent referenced. Publications are referenced in text by basic designations only.
1.American Society for Testing and Materials (ASTM):
E84-2009Surface Burning Characteristics of Building Materials
2.National Fire Protection Association (NFPA):
10-2010Standard for Portable Fire Extinguishers
30-2008Flammable and Combustible Liquids Code
51B-2009Standard for Fire Prevention During Welding, Cutting and Other Hot Work
70-2011National Electrical Code
101-2012Life Safety Code
241-2009Standard for Safeguarding Construction, Alteration, and Demolition Operations
3.Occupational Safety and Health Administration (OSHA):
29 CFR 1926Safety and Health Regulations for Construction
4.VHA Directive 2005-007

B. Fire Safety Plan: Establish and maintain a fire protection program in accordance with 29 CFR 1926. Prior to any worker for the Contractor or Sub-Contractor beginning work on site, they shall undergo a safety briefing provided by the general contractor’s competent person per OSHA requirements. This briefing shall include information on the construction limits, VAMC safety guidelines, means of egress, break areas, work hours, locations of restrooms, use of VAMC equipment, infection control, etc. Provide documentation to the Project Engineer/COR that all construction workers have undergone contractor’s safety briefing.

C. Site and Building Access: Maintain free and unobstructed access to facility for Patients, Visitors, Staff, fire, police and other emergency response forces in accordance with NFPA 241.

D. Separate temporary facilities, such as trailers, storage sheds, and dumpsters, from existing buildings and new construction by distances in accordance with NFPA 241. For small facilities with less than 6 m (20 feet) exposing overall length, separate by 3m (10 feet). Placement of all temporary facilities shall be approved by the COR.

E. Temporary Construction Partitions:

1.Install and maintain temporary construction partitions to provide smoke-tight separations between construction areas and adjoining areas. Construct partitions of 5/8” Type ‘C’ Fire Rated gypsum board and steel studs. Extend the partitions through suspended ceilings to floor slab deck or roof. Seal joints and penetrations. At door openings, install Class C, ¾ hour fire/smoke rated doors with self-closing devices and locks that use or accept the Fargo VA Engineering Service Best Corporation 7-pin core system in use at the Fargo VA.
2.Install fire-rated temporary construction partitions to maintain integrity of existing exit stair enclosures, exit passageways, fire-rated enclosures of hazardous areas, horizontal exits, smoke barriers, vertical shafts and openings enclosures.
3.Close openings in smoke barriers and fire-rated construction to maintain fire ratings. Seal penetrations with listed through-penetration firestop materials in accordance with Section 07 84 00, FIRESTOPPING.
F.Temporary Heating and Electrical: Install, use and maintain installations in accordance with 29 CFR 1926, NFPA 241 and NFPA 70.
G.Means of Egress: Do not block exiting for occupied buildings, including paths from exits to roads. Minimize disruptions and coordinate with Project Engineer.
H.Egress Routes for Construction Workers: Maintain free and unobstructed egress. Inspect daily.
I.Fire Extinguishers: Provide and maintain extinguishers in construction areas and temporary storage areas in accordance with 29 CFR 1926, NFPA 241 and NFPA 10.
J.Flammable and Combustible Liquids: Store, dispense and use liquids in accordance with 29 CFR 1926, NFPA 241 and NFPA 30. Remove from job site when not being used.
K.Sprinklers: Install, test and activate new automatic sprinklers prior to removing existing sprinklers.
L.Existing Fire Protection: Do not impair automatic sprinklers, smoke and heat detection, and fire alarm systems.
M.Smoke Detectors: Prevent accidental operation. Remove temporary covers at end of work operations each day. Coordinate with Project Engineer.
N.Hot Work: Perform and safeguard hot work operations in accordance with NFPA 241 and NFPA 51B. Coordinate with Project Engineer. Obtain permits from Project Engineer in advance.
O.Fire Hazard Prevention and Safety Inspections: Inspect entire construction areas daily and correct potential fire hazard situations.
P.Smoking: Smoking is prohibited except in designated smoking rest areas.
Q.Dispose of waste and debris in accordance with NFPA 241. Remove from buildings daily.
R.Perform other construction, alteration and demolition operations in accordance with 29 CFR 1926.

1.8 OPERATIONS AND STORAGE AREAS

A.The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B.The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
C.Working space and space available for storing materials shall be as determined by the Project Engineer.
D.Workmen are subject to rules of Medical Center applicable to their conduct.
E.Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by Project Engineer where required by limited working space. Use of such equipment and tools may also be limited in and around historic buildings and structures by the terms of agreements reached under the National Historic Preservation Act; consult the Project Engineer for the terms of any such agreements.
1.Do not store materials and equipment in other than assigned areas.
2.Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two calendar days. Provide unobstructed access to Medical Center areas required to remain in operation.
3.Where access by Medical Center personnel is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
F.Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Project Engineer. All such actions shall be coordinated with the Project Engineer.
G.Phasing: To insure such executions, Contractor shall furnish the Project Engineer with a schedule of approximate dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the Project Engineer in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such dates to insure accomplishment of this work in successive phases mutually agreeable to Project Engineer and Contractor.
H.All Buildings except Building 2 will be occupied during performance of work.
1.Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through protected construction areas which serve as routes of access to such affected areas and equipment. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.
2.Selected immediate areas of alterations will be temporarily vacated while alterations are performed. Coordinate with Project Engineer. Other areas will not be vacated during construction.
I.NOT USED
J.Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by Project Engineer.
1.No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of Project Engineer. Electrical work shall be accomplished with all affected circuits or equipment de-energized.
2.Contractor shall submit a request to interrupt any such services to Project Engineer, in writing, 48 hours in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption. The contractor is required to collect as much information about the areas that will be affected by the shutdown prior to submitting the request.
3.Contractor will be advised of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours at no additional cost to the Government.
4.Major interruptions of any system must be requested, in writing, at least 25 calendar days prior to the desired time and shall be performed as directed by the Project Engineer.
5.In case of a contract construction emergency, service will be interrupted on approval of Project Engineer. Such approval will be confirmed in writing as soon as practical.
K.Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces. Contractor shall annotate these items on the as-built drawings.
L.To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the Project Engineer.

M. Coordinate the work for this contract with other construction operations as directed by Project Engineer. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

1.9 ALTERATIONS

A.Survey: Before any work is started, the Contractor shall make a thorough survey with the Project Engineer of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1.Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2.Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.

3. Any features of the area of building designated by VA for protection or other special treatment per historic preservation standards or agreements (See 1.33).

4.Shall note any discrepancies between drawings and existing conditions at site.
5.Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and Project Engineer.
6.The Contractor shall take date-stamped photos of all facility existing conditions in areas that are adjacent to work areas to use during re-survey (detailed below) at the end of the project.
B.ReSurvey: Thirty calendar days before expected partial or final inspection date, the Contractor and Project Engineer together shall make a thorough resurvey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1.Resurvey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
C.Protection: Provide the following protective measures:
1.Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2.Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3.Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
4.Protection of any building or site elements identified by VA for special treatment per historic preservation standards or agreements (See 1.33).

1.10 INFECTION PREVENTION MEASURES

A.The Contractor shall contact Engineering Service (239-3760 Ext. 3361 in Building 30 prior to beginning construction in any areas so that a Preconstruction Risk Assessment (PCRA) may be performed and all applicable forms completed. Once completed the Contractor shall obtain a completed and approved copy of the PCRA (ILSM’s), Infection Control Precautions, etc.) as noted in the completed forms. The Contractor shall post a copy of the completed form outside of the construction barrier at each work site in plain view and accessible to VA Staff for verification that requirements noted on PCRA Form are being adhered to.
B.Implement the requirements of VAMC’s Preconstruction Risk Assessment (PCRA) Form. PCRA Group may monitor dust in the vicinity of the construction work and require the Contractor to take corrective action immediately if the safe levels are exceeded. Obtain PCRA Form from PE/COR prior to starting construction and check with PE/COR for new versions when moving to other construction areas.
C.Establish and maintain a dust control program as part of the contractor’s infection preventive measures in accordance with the guidelines provided by PCRA Form. The Contractor shall install pressure differential monitoring devices in temporary construction barriers and shall monitor and maintain negative air pressure in construction areas.
1.All personnel involved in the construction or renovation activity shall be educated and trained in infection prevention measures established by the Medical Center.
D.Medical Center Infection Control personnel shall monitor for airborne disease (e.g. aspergillosis) as appropriate during construction. A baseline of conditions may be established by the Medical Center prior to the start of work and periodically during the construction stage to determine impact of construction activities on indoor air quality. In addition:
1.The Project Engineer and VAMC Infection Control personnel shall review pressure differential monitoring documentation to verify that pressure differentials in the construction zone and in the adjacent rooms are appropriate for their settings. Construction area always negative and corrections required immediately upon discovery or VA notification otherwise work will be stopped immediately.
2.In case of any problem, the Medical Center, along with assistance from the contractor, shall conduct an environmental assessment to find and eliminate the source.
E.In general, following preventive measures shall be adopted during construction to keep down dust and prevent mold.
1.Dampen debris to keep down dust and provide temporary construction partitions in existing structures where directed by Project Engineer. Blank off ducts and diffusers to prevent circulation of dust into occupied areas during construction.
2.Do not perform dust producing tasks within occupied areas without the approval of the Project Engineer. For construction in any areas that will remain jointly occupied by the Medical Center and Contractor’s workers, the Contractor shall:
a.Provide dust proof construction barriers to completely separate construction from the operational areas of the hospital in order to contain dirt debris and dust. Maintain negative air at all times. A fire-retardant polystyrene, 6-mil thick or greater plastic barrier meeting local fire codes may be used where dust control is the only hazard, and an agreement is reached with the Project Engineer.
b.HEPA filtration is required where the exhaust dust may reenter the breathing zone. Contractor shall verify that construction exhaust to exterior is not reintroduced to the Medical Center through intake vents, or building openings. Install HEPA (High Efficiency Particulate Accumulator) filter vacuum system rated at 95% capture of 0.3 microns including pollen, mold spores and dust particles. Insure continuous negative air pressures occurring within the work area. HEPA filters should have ASHRAE 85 or other prefilter to extend the useful life of the HEPA. Provide both primary and secondary filtrations units. Exhaust hoses shall be heavy duty, flexible steel reinforced and exhausted so that dust is not reintroduced to the Medical Center.
c.Adhesive Walk-off/Carpet Walk-off Mats, minimum 600mm x 900mm (24” x 36”), shall be used at all interior transitions from construction area to occupied Medical Center area. These mats shall be changed as often as required to maintain clean work areas directly outside construction area at all times or at a minimum of one hour whichever is less. Contractor shall post a chart indicating when “sticky” mat was changed (individual sheets) with day, time and name of person who changed the “sticky” mat.
d.Vacuum and wet mop all transition areas from construction to the occupied Medical Center at the end of each workday. Vacuum shall utilize HEPA filtration. Maintain surrounding area frequently. Remove debris as they are created. Transport these outside the construction area in containers with tightly fitting lids.
e.The contractor shall not haul debris through patient-care areas without prior approval of the Project Engineer and the Medical Center. When, approved, debris shall be hauled in enclosed dust proof containers or wrapped in plastic and sealed with duct tape. No sharp objects should be allowed to cut through the plastic. Wipe down the exterior of the containers with a damp rag to remove dust. All equipment, tools, material, etc. transported through occupied areas shall be made free from dust and moisture by vacuuming and wipe down.
f.Using a HEPA vacuum, clean inside the barrier and vacuum ceiling tile prior to replacement. Any ceiling access panels opened for investigation beyond sealed areas shall be sealed immediately when unattended.
g.There shall be no standing water during construction. This includes water in equipment drip pans and open containers within the construction areas. All accidental spills must be cleaned up and dried immediately. Remove and dispose of porous materials.

h. At completion, remove construction barriers and ceiling protection carefully, outside of normal work hours. Vacuum and clean all surfaces free of dust after the removal.

F.Final Cleanup:
1.Upon completion of project, or as work progresses, remove all construction debris from above ceiling, vertical shafts and utility chases that have been part of the construction.
2.Perform HEPA vacuum cleaning of all surfaces in the construction area. This includes walls, ceilings, cabinets, furniture (built-in or free standing), partitions, flooring, etc.
3.All new air ducts shall be cleaned prior to final inspection.

1.11 DISPOSAL AND RETENTION

A.Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1.Reserved items which are to remain property of the Government are to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to reinstallation and reuse. Store such items where directed by Project Engineer.
2.Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3.Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government and shall be removed by the Government in advance of work to avoid interfering with Contractor's operation.

(FAR 52.236-9)

B.Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, “Alternation”, “Restoration”, and “Operations and Storage Areas” for additional instructions concerning repair of damage to structures and site improvements.
C.Refer to FAR clause 52.236-7, “Permits and Responsibilities,” which is included in General Conditions.

1.12 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS

A.The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workmen, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a treepruning compound as directed by the Contracting Officer.
B.The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

1.13 RESTORATION

A.Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the Project Engineer. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B.Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C.At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone).

1.14 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.15 WaRRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in three ring binders at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

1. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

1. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

1. A list for each warranted equipment item, feature of construction or system indicating:

1. Name of item.

1. Model and serial numbers.

1. Location where installed.

1. Name and phone numbers of manufacturers and suppliers.

1. Name and phone numbers of manufacturers or suppliers.

1. Names, addresses and phone numbers of sources of spare parts.

1. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

1. Starting point and duration of warranty period.

1. Summary of maintenance procedures required to continue the warranty in force.

1. Cross-reference to specific pertinent Operation and Maintenance manuals.

1. Organizations, names and phone numbers of persons to call for warranty service.

1. Typical response time and repair time expected for various warranted equipment.

1. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

1. Procedure and status of tagging of all equipment covered by extended warranties.

1. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance Bond: The Performance Bond must remain effective throughout the construction warranty period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

1. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

1. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

1. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

1. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

1. The “Construction Warranty Service Priority List” is as follows:

Code 1-Life Safety Systems

1. Fire suppression systems.

1. Fire alarm system(s).

Code 1-Air Conditioning Systems

1. Air conditioning leak in part of the building where new or modifications work was performed under the contract, if causing damage.

1. Air conditioning system not cooling properly where new or modifications work was performed under the contract or the end product provided does not perform to contract document requirements.

Code 1 Doors

1. New interior or exterior doors or hardware installed or modified under the contract not functioning properly, causing security, fire or safety problem.

Code 3-Doors

1. Interior/exterior personnel doors or hardware installed or modified under the contract not functioning properly.

Code 1-Electrical

1. Power failure in new or renovated area under the contract.

1. Security and life safety code required lights.

1. Smoke detectors.

Code 2-Electrical

1. Power failure (no power to a room or part of building that is new or renovated under the contract).

1. Receptacles and lights not operational (in a room or part of building that is new or renovated under the contract).

Code 3-Electrical

1. Exterior lights not operational that were installed or modified under the contract.

Code 1-Heat

1. Power failure affecting heat.

Code 1-Plumbing

1. Leaking water supply pipes that were installed or modified under the contract.

Code 2-Plumbing

1. Flush valves not operating properly that were installed or modified under the contract.

1. Fixture drain, supply line or any water pipe leaking that was installed or modified under the contract.

1. Toilet leaking at base that was installed or modified under the contract.

Code 3- Plumbing

1. Leaky faucets that are part of a fixture installed under the contract.

Code 3-Interior

1. Floors damaged.

1. Paint chipping or peeling.

1. Casework damaged.

Code 1-Roof Leaks

1. Damage to property is occurring.

Code 2-Water (Hot)

1. No hot water in portion of building constructed or modified by contract.

Code 3

1. All work not listed above.

E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout, location and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

1.16 LAYOUT OF WORK

A. The Contractor shall lay out the work and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated.

(FAR 52.23617)

B.Establish and plainly mark such lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established are in accordance with lines and elevations shown on contract drawings.
C.Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1.Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the Project Engineer before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

1.17 AS-BUILT DRAWINGS

A.The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications. These items should be available for inspection by the VA staff at any time during the execution of the project.
B.All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings shall be made available for the Project Engineer's review, as often as requested.
C.Contractor shall deliver two approved completed sets of as-built drawings to the Project Engineer within 15 calendar days after each completed phase and after the acceptance of the project by the Project Engineer.
D.Paragraphs A, B, & C shall also apply to all shop drawings.

1.18 USE OF ROADWAYS

A.For hauling, use only established public roads and roads on Medical Center property and, when authorized by the Project Engineer, such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by wellconstructed bridges.
B.When new permanent roads are to be a part of this contract, Contractor may construct them immediately for use to facilitate building operations. These roads may be used by all who have business thereon within zone of building operations.

1.19 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A.Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to compliance with the following provisions:
1.Permission to use each unit or system must be given by Project Engineer. If the equipment is not installed and maintained in accordance with the following provisions, the Project Engineer will withdraw permission for use of the equipment.
2.Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3.Units shall be properly lubricated, balanced, and aligned. Vibrations must be eliminated.
4.Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freezeup damage.
5.The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6.All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.
B.Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C.This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

1.20 TEMPORARY USE OF EXISTING ELEVATORS

A.Outside type hoist shall be used by Contractor for transporting materials and equipment where feasible.
B.Use of existing elevators for limited handling of building materials and Contractor's personnel will be permitted subject to following provisions:
1.Contractor makes all arrangements with the Project Engineer for use of elevators. The Project Engineer will ascertain that elevators are in proper condition.
2.Contractor covers and provides maximum protection of following elevator components:
a.Entrance jambs, heads soffits and threshold plates.
b.Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c.Finish flooring.
3.Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

1.21 TEMPORARY TOILETS

A.When approved by Project Engineer, provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
B.Contractor may have for use of Contractor's workmen, such toilet accommodations as may be assigned to Contractor by Medical Center. Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workmen. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.22 AVAILABILITY AND USE OF UTILITY SERVICES

A.The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.
B.The Contractor, at Contractor's expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
C.Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1.Obtain heat by connecting to Medical Center heating distribution system.
a.Steam is available at no cost to Contractor.
D.Electricity (for Construction and Testing): Furnish all temporary electric services.
1.Obtain electricity by connecting to the Medical Center electrical distribution system. Electricity is available at no cost to the Contractor.
E.Water (for Construction and Testing): Furnish temporary water service.
1.Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer and obtain approval from the VA Project Engineer prior to making connection. Water is available at no cost to the Contractor.