This solicitation requests proposals for a new primary care clinic design-build project at the Minneapolis VA Medical Center. The Department of Veterans Affairs will award a firm-fixed price contract to provide design and construction services. Offerors must be verified as service-disabled veteran-owned small businesses. The contractor shall complete the design and construction within 730 calendar days of receiving notice to proceed. Phase I proposals will be evaluated on past performance, technical approach, and qualifications. The four most qualified offerors will advance to Phase II. Phase II proposals will be assessed on technical solution, project schedule, design concept, and price. The government intends to make award without discussions and select the best value proposal.
36E77619R0008 36E77619R0008_1.docx
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36E77619R0008-0001000.docx | DOCX document | |
| 36E77619R0008-0001001.docx | DOCX document | |
| 36E77619R0008-0001001.docx | DOCX document | |
| 36E77619R0008-0001000.docx | DOCX document | |
| Attachment_2_-_Contractor_Safety_and_Environmental_Record_Evaluation_Form.docx | DOCX document | |
| Attachment_7_-_Section_01_32_16_Project_Schedules.doc | DOC document | |
| Attachment_12_-_Strucutral_Asbuilts.zip | ZIP file | |
| Attachment_3_-_Release_of_Claims.docx | DOCX document | |
| Attachment_13_-_Brand_Name_J_A.pdf | ||
| Attachment_11_-_Supporting_Data.zip | ZIP file | |
| Attachment_1_-_SOW_(1-7-2019).docx | DOCX document | |
| Attachment_6_-_SCA_Wage_Rates_-_Hennepin_-_12-26-18.pdf | ||
| Attachment_5_-_Construction_Wage_Rates_-_Hennepin_-_1-4-19.pdf | ||
| Attachment_4_-_Past_Performance_Questionnaire.docx | DOCX document | |
| Attachment_9_-__Minneapolis_VA_BIM_Management_Plan.zip | ZIP file | |
| Attachment_10_-_Minneapolis_VHA_Campus_Maps.zip | ZIP file | |
| Attachment_8_-_Specs.zip | ZIP file | |
| 36E77619R0008-000.docx | DOCX document | |
| 36E77619R0008-000.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36E77619R0008
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE
DOCUMENTS (
Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36E77619R0008 X 01-07-2019 618-182
PCAC
Megan Dohm Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131 Megan Dohm Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131 Megan Dohm 216-447-8300x49566 IN ACCORDANCE WITH 38 U.S.C 8127 (PUBLIC LAW 109-461), THIS PROJECT IS A COMPETITIVE SERVICE-DISABLED VETERAN-OWNED
SMALL BUSINESS SET-ASIDE
THIS PROJECT WILL BE PROCURED USING THE TWO-PHASE DESIGN-BUILD PROCEDURES
THE CONTRACTOR IS TO PROVIDE DESIGN AND CONSTRUCTION SERVICES FOR THE NEW PRIMARY CARE CLINIC AT THE MINNEAPOLIS VA
MEDICAL CENTER (VAMC). THE LOCATION OF THE PROJECT IS:
1 VETERANS DRIVE
MINNEAPOLIS, MN 55417
NAICS CODE: 236220 ($36.5M)
MAGNITUDE OF CONSTRUCTION: $5,000,000 TO $10,000,000
X X 52.211-10 X
2:00PM ET
02-08-2019 X
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
PCAC
Department of Veterans Affairs Program Contracting Activity Central 6150 Oak Tree Blvd, Suite 300 Independence OH 44131
VAFSC
Department of Veterans Affairs Financial Services Center Invoices to be Submitted Electronically www.ob10.com/us/en/veterans-affairs/ e-Invoice Setup Info Phone 877-489-6135 877-353-9791 512-460-5429 Donald A.
Marsh III
PCAC15L3-1697
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| A.3 PRICE SCHEDULE: | 6 |
| INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS | 7 |
| 1.1 PROPOSAL MATERIAL: | 7 |
| 1.2 BID GUARANTEE: | 7 |
| 1.3 PAYMENT & PERFORMANCE BONDS: | 7 |
| INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS | 8 |
| 2.1 AVAILABILITY OF SOLICITATION DOCUMENTS: | 8 |
| 2.2 SELECTION PROCEDURES: | 8 |
| 2.3 SDVOSB SET-ASIDE: | 8 |
| 2.4 TECHNICAL QUESTIONS: | 9 |
| 2.5 AMENDMENTS: | 9 |
| 2.6 PREPARATION OF PROPOSALS: | 9 |
| 2.7 PROPOSAL REQUIREMENTS: | 9 |
| 2.8 USE OF ADVISORS: | 14 |
| 2.9 DETERMINATION OF RESPONSIBILITY: | 14 |
| 2.10 VETS 4212: | 14 |
| 2.11 SYSTEM FOR AWARD MANAGEMENT (SAM): | 15 |
| 2.12 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR | 15 |
| PERFORMANCE ASSESSMENT SYSTEM (CPARS): | 15 |
| 2.13 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS: | 15 |
| 2.14 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER OR PROJECT MANAGER: | 16 |
| 2.15 52.216-1 TYPE OF CONTRACT (APR 1984) | 16 |
| 2.16 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 16 |
| 2.17 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 16 |
| 2.18 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) | 17 |
| 2.19 52.228-1 BID GUARANTEE (SEP 1996) | 18 |
| 2.20 52.233-2 SERVICE OF PROTEST (SEP 2006) | 19 |
| 2.21 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 19 |
| 2.22 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 20 |
| 2.23 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 20 |
| 2.24 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION (SEP 2018) | 20 |
| 2.25 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (SEP 2018) | 21 |
| 2.26 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008) | 21 |
| 2.27 PARTNERING | 22 |
| REPRESENTATIONS AND CERTIFICATIONS | 23 |
| 3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018) | 23 |
| 3.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 26 |
| 3.3 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018) | 27 |
| GENERAL CONDITIONS | 30 |
| 4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 30 |
| 4.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) | 30 |
| 4.3 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014) | 31 |
| 4.4 52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS (SEP 2013) | 32 |
| 4.5 52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008) | 32 |
| 4.6 52.223-20 AEROSOLS (JUN 2016) | 33 |
| 4.7 52.223-21 FOAMS (JUN 2016) | 33 |
| 4.8 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2016) | 34 |
| 4.9 52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN 1997) | 38 |
| 4.10 SUPPLEMENTAL INSURANCE REQUIREMENTS | 39 |
| 4.11 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 39 |
| 4.12 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018) | 42 |
| 4.13 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 42 |
| 4.14 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 43 |
| 4.15 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008) | 44 |
| 4.16 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 44 |
| 4.17 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (JUL 2002) | 45 |
| 4.18 VAAR 852.236-74 INSPECTION OF CONSTRUCTION (JUL 2002) | 46 |
| 4.19 VAAR 852.236-76 CORRESPONDENCE (APR 1984) | 46 |
| 4.20 VAAR 852.236-77 REFERENCE TO "STANDARDS" (JUL 2002) | 46 |
| 4.21 VAAR 852.236-78 GOVERNMENT SUPERVISION (APR 1984) | 46 |
| 4.22 VAAR 852.236-79 DAILY REPORT OF WORKERS AND MATERIAL (APR 1984) | 47 |
| 4.23 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 1984) | 47 |
| 4.24 VAAR 852.236-84 SCHEDULE OF WORK PROGRESS (NOV 1984) | 47 |
| 4.25 VAAR 852.236-85 SUPPLEMENTARY LABOR STANDARDS PROVISIONS (APR 1984) | 48 |
| 4.26 VAAR 852.236-86 WORKER'S COMPENSATION (JAN 2008) | 48 |
| 4.27 VAAR 852.236-87 ACCIDENT PREVENTION (SEP 1993) | 48 |
| 4.28 VAAR 852.236-88 CONTRACT CHANGES--SUPPLEMENT (JUL 2002) | 48 |
| 4.29 VAAR 852.236-89 BUY AMERICAN ACT (JAN 2008) ALTERNATE I (JAN 2008) | 50 |
| 4.30 VAAR 852.236-90 RESTRICTION ON SUBMISSION AND USE OF EQUAL PRODUCTS (NOV 1986) | 51 |
| 4.31 VAAR 852.236-91 SPECIAL NOTES (JUL 2002) | 51 |
| 4.32 MANDATORY WRITTEN DISCLOSURES | 52 |
| 4.33 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (WITHOUT NAS– CPM) (NOV 2018) | 52 |
| DESIGN BUILD SPECIFICATIONS | 56 |
| 4.34 SCHEDULE OF PAYMENTS FOR DESIGN SERVICES | 56 |
| 4.35 OWNERSHIP OF ORIGINAL DOCUMENTS | 56 |
| 4.36 RETENTION OF REVIEW DOCUMENTS | 56 |
| 4.37 CONTRACT DRAWINGS AND SPECIFICATIONS GOVERNMENT FURNISHED PLANNING INFORMATION | 56 |
| 4.38 COORDINATION WITH MEDICAL CENTER | 57 |
| 4.39 RESPONSIBILITY OF THE DESIGN-BUILD CONTRACTOR | 57 |
| ATTACHMENTS | 58 |
A.3 PRICE SCHEDULE:
*PLEASE NOTE: Pricing will only be required for Phase II of the Design-Build process. NO Pricing is to be submitted as part of Phase I.
The contractor shall complete the entire project not later than 730 calendar days after the contractor receives the NOTICE TO PROCEED.
| CLIN 0001: Design & Construction Documents: Contractor shall provide the complete design of a new primary care clinic of approximately 12,500 – 13,750 square feet, connected to the main facility by a breezeway. |
| Contractor shall furnish all labor, material, equipment, and supervision to provide the required documents for construction including Drawings, Specifications, and other documents as necessary in accordance with the SOW and all Specifications. |
Lump Sum Amount, CLIN 0001: $__________________________________
| CLIN 0002: Construction: Contractor shall provide all construction related activities such as pre-construction, site-prep, general construction, alterations, necessary removal of existing structures, renovations, post-construction services, commissioning, project close-out and any other required elements of work to provide a complete and usable facility. |
| Contractor shall furnish all labor, material, equipment, and supervision to perform all required elements of work in accordance with the SOW, Specifications and all applicable attachments. |
| Lump Sum Amount, CLIN 0002: $__________________________________ |
TOTAL (CLINs 0001 and 0002): $__________________________________
NOTICE
1. The Offeror must submit a proposal based on a 730 Calendar day Schedule. This duration includes, but is not limited to design services, construction, clean-up, acceptance, and submitting final project record drawings.
2. The Offeror shall furnish all plant, labor, material, equipment, etc., necessary to perform all work in strict accordance with the terms and conditions set forth in the contract to include all attachments thereto.
3. Contractor is required to fill in DUNS NUMBER in Block No. 14 on Standard Form (SF) 1442.
4. During Phase Two of the Two-Phase Design Build Process, the Contractor is required to fill in their pricing on the above pricing schedule and in Block No. 17 of the SF 1442. Pricing is not to be submitted in Phase One.
5. PLEASE NOTE: The Contractor agrees to attend any Post Award conference convened by the contracting activity or contract administration in accordance with Federal Acquisition Regulation subpart 42.5.
6. Contractor employees shall not be considered government employees for any purpose under this contract.
Page 1 of Page 1 of
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
1.1 PROPOSAL MATERIAL:
Proposal materials consisting of the statement of work, specifications, other attachments, and contract forms are included and/or attached as part of this Request For Proposal. The VA will not provide printed copies of the specifications or solicitation documents. It is the responsibility of the offeror to obtain the proposal materials in a time and manner sufficient to respond to this solicitation by the specified due date.
1.2 BID GUARANTEE:
A Bid Guarantee, SF 24, is required in an amount not less than 20 percent of the proposal price but shall not exceed $3,000,000. Failure to furnish the required bid (proposal) guarantee in the proper form and amount, by the time set for receipt of proposals, shall result in the rejection of the proposal. Copies of the SF 24 may be obtained from http://www.gsa.gov/portal/forms/type/TOP.
1.3 PAYMENT & PERFORMANCE BONDS:
The offeror to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Solicitation. Copies of SFs 25 and 25A may be obtained from http://www.gsa.gov/portal/forms/type/TOP.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 AVAILABILITY OF SOLICITATION DOCUMENTS:
All solicitation related documents will be published to http://www.fedbizopps.gov except models which are too large to post. There are models in REVIT format that will be made available upon request. To obtain access, please send a request to Megan Dohm at megan.dohm@va.gov and provide an email and contact information by January 18, 2019. The link to view the files will go to the email provided.
2.2 SELECTION PROCEDURES:
This solicitation is issued as a Request For Proposal (RFP) utilizing the two-phase design-build selection procedures in accordance with FAR 36.301. Phase II of the solicitation shall be prepared in accordance with FAR Part 15, with evaluation criteria developed in accordance with FAR 15.304. The Government intends to award a contract resulting from this solicitation to the responsible Offeror whose proposal represents the best value to the Government. It is the intent of the Government to award without discussions; however, the Government reserves the right to conduct discussions if necessary.
All Phase I and Phase II proposals shall be subject to evaluation by a team of Government personnel. The proposals will be evaluated in accordance with the content provided in the solicitation. In Phase I of the Two-Phase Design-Build process, Offerors will submit a proposal in accordance with the three (3) evaluation factors listed below. Upon receipt of Phase I proposals, the VA team will evaluate and determine the highest qualified Offerors based on their Phase I submissions. A maximum of four (4) Offerors will be selected to provide a proposal for Phase II. Offerors not selected to provide a Phase II proposal will be notified that they are no longer being considered for this project. Phase II proposals will be evaluated in accordance with FAR Part 15 and the four (4) evaluation factors listed below for Phase II. Using the tradeoff process to obtain the best value, the Government may consider award to other than the lowest price Offeror or other than highest technically rated Offeror. Technical Solution and Design Concept, when combined, are approximately equal to price. Draft Project Schedule is significantly less important than price.
Evaluations will be based on the following evaluation factors:
Phase I
1. Past Performance
2. Technical Approach
3. Technical Qualifications
a. Key Personnel Experience
b. Capability to Perform Phase II
1. Technical Solution
2. Draft Project Schedule
3. Design Concept
4. Price
2.3 SDVOSB SET-ASIDE:
This procurement is 100% set-aside for Service-Disabled Veteran-Owned Small Business concerns. Offers received from other than Service-Disabled Veteran-Owned Small Business concerns will not be considered. All Service-Disabled Veteran-Owned Small Businesses must be listed as verified by the VA’s Center for Veterans Enterprises (CVE) (http://www.vetbiz.gov). Offerors must be verified by CVE and visible in the Vendor Information Portal (VIP) database at the time proposals are due and at the time of award. Failure to be both visible and verified at the time proposals are due and at the time of award will result in the offeror’s proposal being deemed unacceptable and ineligible for award.
2.4 TECHNICAL QUESTIONS:
Questions of a technical nature must be provided in writing and shall be submitted by the prospective offerors to Megan Dohm. Questions shall be submitted only via e-mail to: megan.dohm@va.gov. The subject line must read: Minneapolis Primary Care Clinic – Technical Questions. Oral questions of a technical nature are not acceptable. The cut-off date and time for questions is January 18, 2019 at 3:00 PM ET.
2.5 AMENDMENTS:
The Government reserves the right to revise the solicitation. Amendments to this solicitation will be posted at http://www.fedbizopps.gov. Paper copies of the amendments will NOT be mailed. No other notification of amendments will be provided. Prospective Offerors are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation in Block 19 of the SF1442. Failure to acknowledge a material amendment shall result in your proposal being considered unacceptable and will not be considered further.
2.6 PREPARATION OF PROPOSALS:
The Government will not pay for any costs incurred in preparation and submission of proposals.
2.7 PROPOSAL REQUIREMENTS:
A. General:
1. Proposals shall be based on solicitation document issued for RFP number 36E77619R0008. Proposals will be in the format stipulated in this document.
2. Proposals shall be received on or before the date and time specified in Block 13 of the SF 1442. There will be no public opening of the proposals.
3. Proposal Submission:
i. Submit proposals via e-mail to: megan.dohm@va.gov.
ii. Emails are limited to five (5) MB.
iii. Only e-mail proposals will be accepted. Hard-copy proposals will not be accepted.
4. Submit the original copy of the Bid Bond (PHASE II ONLY) to:
i. Megan Dohm Veterans Health Administration Program Contracting Activity Central (VHA-PCAC) 6150 Oaktree Blvd., Suite 300 Independence, OH 44131
ii. Bid guarantees can be delivered by mail, commercial delivery services, or hand carried. Delivery hours are 7:00AM – 3:30PM (EST).
iii. Failure to furnish the required bid guarantee on the proper form and for the proper amount, by the time specified in Block 13 of SF 1442, shall result in rejection of the proposal. See FAR Provision 52.228-1, Bid Guarantee, contained in the solicitation.
5. Page size for all proposal documents will be 8.5 x 11 inches, with 1-inch margins around the page perimeter. Pages will be single spaced. Each page shall count as one (1) page. Proposals shall be submitted using Times New Roman, with font no smaller than 11 point with normal proportional spacing.
6. Page formatting restrictions do not apply to drawings but each page does apply to the page count. Submission of the draft project schedule can be submitted utilizing larger paper of 11 x17 inches. Pages submitted in excess of the page count will not be evaluated.
B. Phase I Proposal Format and Evaluation:
1. Format: The offer, including title page, detailed table of contents, and preface for Phase I shall be submitted in one (1) PDF document and shall not exceed a total of THIRTY-FIVE (35) pages. The page limit does not apply for any Past Performance Questionnaires that are submitted directly to the Contract Specialist. The SF 1442, Representations and Certifications, and acknowledged amendments shall all be part of the offer and will not count against the page limitations. Use graphic presentations where such use will contribute to the compactness and clarity of the proposal.
2. Evaluation Factors:
i. Factor 1, Past Performance: Provide a minimum of one (1) and a maximum of three (3) projects completed within the last five years (5) years similar in size, complexity and scope to this project. Projects must demonstrate an offeror’s experience as a prime contractor managing multiple subcontractors to include A-E firms if applicable. If the contractor does not possess Design-Build (D-B) experience, provide a minimum of (1) and a maximum of two (2) projects completed by the A-E firm similar in size, complexity, and scope to this project in addition to the one (1) to three (3) projects submitted for the prime contractor. For purposes of this evaluation, a relevant project is further defined as “design and/or construction completed in a clinical, hospital or other medical related use space similar in size and scope to this project.” Project(s) shall have a minimum value of $3M and be 100% completed for Design-Bid-Build (D-B-B) or D-B. Projects shall have a minimum value of $250,000 and be 100% completed for designs completed by the A-E firm in support of D-B or D-B-B.
For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather Offerors shall submit the work performed under a task order as a project. If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects shall be submitted for each Joint Venture partner. Offerors who fail to submit experience for all Joint Venture partners may be rated lower. The Offeror’s submission should include at a minimum:
· Project Title, Project Location (Physical Address); Contract Type (Example: Design-Build, Design-Bid-Build)
· Project owner name and contact information
· A brief description of the scope of work
· Project prime contractor and major subcontractors
· Project statistics including start and completion dates (original vs actual) and project cost (original vs actual). If original vs actual completion dates and project cost differ, please provide an explanation as to why they differ.
If a completed past performance evaluation is available in the Past Performance Information Retrieval System (PPIRS), it shall be submitted with the proposal for each project referenced for Past Performance. If there is not a completed past performance evaluation available in PPIRS, then the Offeror shall submit a Past Performance Questionnaire (PPQ) (reference Attachment 4) for each project referenced for Past Performance. The Offeror shall notify their client that the PPQ shall be submitted via email to the Government’s point of contact, megan.dohm@va.gov. If the Offeror is unable to obtain a completed PPQ from a client for a project before proposal closing date, the Offeror shall complete and submit with the proposal the first page of the PPQ, which will provide contract and client information for the respective project. The Government may make reasonable attempts to contact the client noted for that project(s) to obtain the PPQ information. However, Offerors should follow-up with clients/references to help ensure timely submittal of questionnaires.
ii. Factor 2, Technical Approach: Provide a brief narrative (page limitation: five (5) pages) describing the Offeror’s method to manage the project to achieve design and construction objectives as described in the solicitation. If the page limits are exceeded, the pages exceeding the limit will not be read or considered. Include at minimum all aspects covered in the scope of work. The following shall be included in the narrative:
· Design Approach: Describe the techniques and methods for an efficient, effective design and;
· Construction Approach: Describe the techniques and methods for this construction project to include coordination with the design packages, projected timelines and coordination of work.
iii. Factor 3, Technical Qualifications:
a. Key Personnel Experience: The Offeror shall provide a resume for each of the following key A-E personnel: Architect, Mechanical Engineer – Plumbing, Mechanical Engineer – HVAC, Electrical Engineer, Civil Engineer, Hospital Planner, Geo-Technical Engineer, and Surveyor.
The Offeror shall also provide a resume for each of the following key construction personnel: Project Manager, Project Engineer, Site Supervisor, and any known major subcontractors. For each resume, include company name; name of individual; relevant listing of experience; qualifications such as specialized training, education, experience, etc. For any subcontractors identified, provide a resume for that company, identify any key personnel that will be assigned to the contract resulting from this solicitation, and the relevant experience of both the company and any key personnel that were identified. Please delineate the approximate percentage of work the prime contractor will perform and the approximate percentage of work the subcontractors (collectively) will perform. The VA will use the information provided to evaluate, among other things, specialized experience and technical competence.
b. Capability to Perform: The Offeror shall provide a letter from their surety demonstrating the offeror’s total bonding capacity and current available bonding capacity. Total bonding capacity and current available bonding capacity must be outlined in a letter dated no earlier than the solicitation release date.
c. Note: If awarded the contract resulting from this solicitation, any deviation from the A-E firm or personnel submitted for evaluation during contract performance must be approved by the Contracting Officer. Substitutions may be approved if a firm or person possesses the same qualifications as the firm or person submitted for evaluation.
3. Evaluation of Offers:
i. Factor 1, Past Performance: Will be evaluated on recent and relevant experience as well as the quality rendered of the projects provided. If D-B experience is not applicable, the construction contractor and the A-E firm will be evaluated on relevant and recent projects to the applicable portion of the project, construction or design respectively. Past performance will be evaluated on the quality of the Offeror’s past performance with respect to the projects provided. When evaluating quality aspects that may be considered are timeliness of contract completion, adherence to contract schedules and timely submission of data deliverables, the contractor’s ability to comply with the terms and conditions of the contract, the overall quality of the work performed on the contract, the Offeror’s managerial performance, and if the reference would enter into a contract with the contractor again. Contractors without relevant past performance or for whom past performance information is not available, will be rated neither favorably nor unfavorably on past performance. In accordance with Procurement Policy Memorandum 2013-03, past performance evaluations may also be conducted using information obtained from CPS or PPIRS and any other sources deemed appropriate by the CO. Other sources may include, but are not limited to, inquiries of owner representatives, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), and any other known sources not provided by the Offeror.
ii. Factor 2, Technical Approach: Will be evaluated based on the Offeror’s proposed technical approach for this design-build project as defined in the solicitation submittal requirements. The assessment of the offeror’s method to manage the project shall be used as a means of evaluating the offeror’s ability to successfully meet the requirements of the solicitation.
iii. Factor 3, Technical Qualifications: Will be evaluated on the Offerors key personnel experience and capability to perform. Key personnel experience will be evaluated by the resumes provided by the Offeror. Capability to perform will be evaluated based on whether the Offeror has adequate total bonding capacity and available bonding capacity to accommodate the design and construction of the project.
C. Phase II Proposal Format and Evaluation:
1. Format: Phase II proposals shall be based on solicitation documents and the instructions provided by the Contracting Officer in the Phase II Notice of Offerors notifying Offerors that they were selected as one of the most qualified Offerors in Phase I. Non-Price and Price sections of the Offerors proposals will be evaluated independently; therefore, the Offeror shall submit the proposal in two (2) Volumes (Volume I: Non-Price and Volume II: Price). The contractor shall include NO price information in Volume I. Both volumes must be labeled with the Offeror's organization, business address, and VA Solicitation Number. Volume 1 including all non-price factors shall not exceed a total of FIFTY (50) pages and Volume II including price only shall not exceed a total of TWENTY (20) pages following the formatting requirements stated in general proposal requirements. The Offeror shall submit Volumes I and II in electronic format as searchable PDF documents. The proposal, in its entirety, shall not exceed two emails of 5MB each. Include page numbers and the company name in the header or footer of each page.
2. Evaluation Factors:
i. Factor 1, Technical Solution: The Offeror shall provide a detailed technical solution to accomplishing the design and construction of the new primary care clinic. The narrative will detail how the contractor intends to design the project, prepare the site, construct the primary care clinic, and connect utility services to the facility within the specified time limits.
ii. Factor 2, Draft Project Schedule: The Offeror shall demonstrate their understanding of the requirement and timeline by submitting a draft project schedule for design and construction that adheres to the requirements outlined in Attachment 7, Project Schedule Specification.
iii. Factor 3, Design Concept: The Offeror shall submit a preliminary design schematic to demonstrate their understanding of the project scope and their plan to accomplish the project. The design schematic shall be based on the information provided in the bridging documents. The intent of the design concept it to show a clear understanding of the bridging documents, as well as allow for creative latitude of the Offerors design team. Acceptable methods of demonstrating design concept include digital design software, architectural sketches/drawings, and/or artistic renderings. Include at a minimum the following:
a. A site layout showing relation of the proposed building to the existing buildings, roads, utilities, etc. as well as future expansion. The layout shall include building entrances and exits, proposed road parking and walk way modifications, and a sampling of proposed plant materials.
b. An architectural floor plan including proposed rooms, corridors, columns, MEP rooms/shafts, stairs, elevators (future), etc. Use of lines between spaces to indicate the centerline of the partition is acceptable. Provide exterior dimensions/total building gross area.
c. Exterior building elevations to show all facades indicating massing, proposed fenestration and the building relationship to adjacent structures and the approximate finish grade. Show all significant building materials, including their colors, architectural screens, skylights, and stacks on the elevation drawings. For building future expansion (vertical and horizontal), delineate elevations with and without the future expansion.
iv. Factor 4, Price: Carefully follow “Instructions, Conditions, and Notices to Offerors”. Standard form (SF) 1442 Solicitation, Offer and Award (Construction, Alteration, or Repair) and the pricing schedule when submitting price offers. The prices shall be Firm Fixed Price. The Offeror shall take care not to include remarks that take exception to the Government’s SOW/Specifications, pricing requirements, or otherwise preclude the Government from evaluating the offer or render the offer as non-responsive or unacceptable. If the Offeror communicates in its proposal any exceptions, exclusions, qualifications, or conditions to the proposed prices not provided for in the Offerors proposal documents, the Contracting Officer shall reject the proposal and exclude the Offeror from further consideration. In addition to the pricing schedule, Offerors shall submit a complete Breakdown of the Division Pricing for CLIN 0001 and CLIN 0002.
3. Evaluation of Offers:
i. Factor 1, Technical Solution: Will be evaluated and used as an aid to help determine that the Offeror understands the complexity and risks performing the required elements. The technical solution will be evaluated for inclusion of the technical areas listed in the criteria. The VA will evaluate Offeror’s specific detail in each of the technical areas regarding design and constructability of design. The Offeror’s narrative should provide enough detail to demonstrate that the scope and complexity of the project requirements are understood and will be successfully completed.
ii. Factor 2, Draft Project Schedule: Will be evaluated and used as an aid to help determine that the Offeror understands and can perform all required elements of the project in the timeframe specified with limited impact, to the greatest extent possible, to the Medical Center. (The draft schedule submitted with the offer should not be construed as the agreed upon schedule as per FAR 52.236-15, the contractor shall, within twenty-one (21) Calendar days after receiving the Notice to Proceed, submit an interim project schedule which will supersede the draft project schedule. The interim project schedule will be subject to VA approval and must show the project being accomplished within the time frame specified on the SF 1442).
iii. Factor 3, Design Concept: Will be evaluated and used as an aid to help determine that the Offeror understands all project requirements and is able to design a complete and usable space. The Offeror’s Design Concept will be evaluated on the incorporation of Patient Aligned Care Team (PACT) requirements, level of innovation, and ability to provide all required areas in the allotted square footage.
iv. Factor 4, Price: Will be evaluated in accordance with the process identified in the Price Schedule. The total evaluated price will be determined by the Offeror’s price for all the CLINs listed. Note: The VA will look at the total evaluated price and non-price factors to determine the best value. “Best Value” means the expected outcome of an acquisition that, in the Government’s estimation, provides the greatest overall benefit in response to the requirements.
4. Safety and Environmental Record:
i. Offerors shall include the Safety or Environmental Violations and Experience Modification Rating Information as part of Volume II, to include Attachment 2. It will not be evaluated as Price, nor will it count against the page limitations. The information must contain a certification that the Offeror has no more than three (3) serious, one (1) repeat, or one (1) willful OSHA or any EPA violation(s) in the past three (3) years. If such certification cannot be made, an Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.
ii. All Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If an Offeror’s EMR is above 1.0, the Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the elevated EMR and the anticipated date the EMR may be reduced to 1.0 or below.
iii. Self-insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self-insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
iv. If the NCCI cannot issue an EMR because the Offeror lacks insurance history, Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Offeror a Unity Rating of 1.0.
v. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.
vi. This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
*If the EMR rating for the subcontracting tiers cannot be provided at time of proposal submission, the prime contractor shall acknowledge this and provide as a submittal with the insurance and bonding requirements.
vii. Failure to provide Attachment 2 containing the above information, may result in a determination that an Offeror is not responsible and therefore ineligible for award.
D. Final Proposal Revisions
1. If determined to be necessary, proposal revisions will be requested from the Offerors determined by the CO to be in the competitive range based on the selection criteria. Discussions may be conducted with those Offerors falling within the competitive range, after which proposal revisions will be requested. Sealed proposal revisions will be submitted as per Section 2.7(A), above, except as noted below and will be due at a time and place to be determined.
2. Offerors submitting proposal revisions will not be requested to re-submit any documents which are unchanged from their initial proposals. Offerors will provide necessary changes to individual paragraphs, as briefly as possible, and include a table of contents, which indicates where within the initial proposal the additional information or changed documents would be placed. Proposal revisions shall include a completed SF 1442 that acknowledges receiving all amendments, by number. A new bid bond shall be submitted only if the final proposal revisions Offeror’s price proposal is greater than its initial price proposal.
2.8 USE OF ADVISORS:
Contractors are advised that VA contractor personnel may assist the Government during the Government’s evaluation of proposals. The individuals shall be authorized access to only those portions of the proposal and discussions that are necessary to enable them to provide specific technical advice on specialized matters or on particular problems. These individuals will be required to protect the confidentiality of any specifically identified trade secrets and/or privileged or confidential commercial or financial information obtained as a result of their participation in this evaluation. They shall be expressly prohibited from scoring, ranking or recommending the selection of an Offeror.
2.9 DETERMINATION OF RESPONSIBILITY:
A responsibility determination will be made in accordance with FAR 9.1 “Responsible Prospective Contractors.” The required information from the proposal, along with other information obtained from Government systems, such as, but not limited to the OSHA and EPA online inspection history databases, as well as any other information the Contracting Officer has determined to be valid, will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines in the proposal may result in a determination of “Non-Responsible” for the Offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility may make the Offeror ineligible for award.
2.10 VETS 4212:
Title 38, USC Section 4212(d), codified at 41 CFR Section 61-300, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS-4212 reporting information can be done electronically at: http://www.dol.gov/vets/vets4212.htm. Award cannot be made unless the awardee has filed their VETS-4212 report. Therefore, all offerors are encouraged to file every year. The Contracting Officer may request a copy of the email confirmation of receipt notification, prior to awarding the project.
2.11 SYSTEM FOR AWARD MANAGEMENT (SAM):
Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at http://www.sam.gov and enter all mandatory information into the system. Award cannot be made until the contractor has registered. Offerors are encouraged to ensure that they are registered in SAM prior to submitting their proposal.
2.12 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR
PERFORMANCE ASSESSMENT SYSTEM (CPARS):
As prescribed in Federal Acquisition Regulation (FAR) Part 42.1502(e), the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $700,000, and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement VA uses an online database, CPARS, which is maintained by the Naval Seal Logistics Center in Portsmouth, Virginia. CPARS has connectivity with the Past Performance Information Retrieval System (PPIRS) database, which is available to all Federal agencies. PPIRS is the system used to collect and retrieve performance assessment reports used in source selection determinations and completed CPARS report cards transferred to PPIRS. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.
Each contractor whose contract award is estimated to exceed $700,000 is required to register with CPARS database at the following web address: http://www.cpars.gov/. Help in registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207- 438-1690. Registration should occur no later than thirty days after contract award, and must be kept current should there be any change to the contractor’s registered representative.
For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.
Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.
2.13 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS:
All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation commensurate with the level of access needed to perform the statement of work is: Low Risk. This requirement is applicable to all subcontractor personnel requiring the same access. As per VA Directive 0710, costs of background investigations will be borne by the contractor.
2.14 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER OR PROJECT MANAGER:
Any reference contained within the solicitation/contract specifications and/or drawings to the “VA Engineer,” “Resident Engineer,” or “Project Manager” or their abbreviations shall be replaced with “Contracting Officer’s Representative (COR).”
2.15 52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.16 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.17 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
| Goals for minority participation for each trade |
| Goals for female participation for each trade |
| 3 % |
| 6.9 % |
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction," and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the—
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Hennepin County - Minneapolis, MN
(End of Provision)
2.18 52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "designated country construction material," "domestic construction material," and…