This document provides details on a federal contract solicitation for the expansion of a patient parking garage at the Cleveland VA Medical Center. The scope of work involves completing the fourth deck of an existing parking garage to provide 132 additional parking spaces, as well as improving lighting, installing a suicide prevention barrier, and matching the exterior of the expanded garage to the larger adjacent structure. The solicitation will be issued as an Invitation for Bid on or about October 18, 2019, with all bids due on the specified date. As a Service-Disabled Veteran-Owned Small Business set-aside, only offers from SDVOSBs will be considered. The contract is valued between $2-5 million and has a period of performance of approximately 280 calendar days from notice to proceed. Liquidated damages of $1,375.43 per calendar day will be assessed for delays in completion, and $2,527 per day for any delay in the 42-day closure of the west portion of the garage.
36E77619B0020 0007 ATTACHMENT 7 - Additional Liquidated Damages.pdf
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT – ADDITIONAL LIQUIDATED DAMAGES INFORMATION
The solicitation currently contains the following clause for Liquidated Damages:
4.2 52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,375.43 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of Clause)
In addition to the information contained in this clause, the following has been added:
In the event that the 42-calendar day closure period of the west portion of the parking garage is exceeded, the following Liquidated Damages will apply for each day these are not completed:
The Government will assess $2,527.00 per day of delay.