LANC Q and A 36C78627Q0029.docx
DOCX document 28 KB Posted
- Solicitation number
- 36C78627Q00290002
About this file
This is a consolidated Questions and Answers document for a laundry and dry-cleaning services solicitation for Los Angeles National Cemetery. The VA seeks a single firm fixed-price contractor to provide laundry and dry-cleaning services for all cemetery employees requiring such services, with pricing quoted as a flat monthly rate for the base year and four option years. Services include twice-weekly dry cleaning of blazers, slacks, and ties; monthly cleaning of coats and trench coats (twice yearly); alterations included in the flat rate; and twice-weekly pickup and delivery service with 104 total annual visits. The contractor must provide turnaround of items picked up Monday by Thursday and Thursday pickups by the following Monday, with schedule adjustments for federal holidays to the next business day. Monthly invoicing in arrears will be based on actual quantities serviced, though the monthly payment remains constant regardless of volume fluctuations. Replacement costs for lost or damaged garments must be included in the price proposal.
The solicitation is 100% small business set-aside with tiered preference structure covering SDVOSB, VOSB, WOSB, 8(a), and HUBZone entities. Small business primes may subcontract cleaning, pressing, and alterations to qualified commercial facilities within a 50% subcontracting limit under FAR 52.219-14. No background investigations or PIV badges are required for driver access. No certificates of insurance are required at award. This is a new requirement with no incumbent contractor. Offers are due November 30, 2026 at 5:00 PM PST and should be submitted to anna.sraley@va.gov. The contract begins January 31, 2027. The question period is closed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78627Q0029 0002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Q&A: Laundry and Dry-Cleaning Services Consolidated, de-duplicated, and numbered. Items marked ANSWERED include agency responses already received.
1. Pricing structure. PWS 4.5 still shows Option A (per-item unit prices plus a monthly pickup and delivery charge) and Option B (a single fixed monthly price). Section B.2 lists monthly firm-fixed-price CLINs for the base year and four option years. ANSWER: Option B, a single firm fixed monthly price, quoted as a flat monthly rate.
1. Pricing table format. The package template appears blank. ANSWER: Offerors may submit their own itemized schedule for the base year and each option year.
1. Alteration pricing. ANSWER: Alterations included in flat monthly rate.
1. Replacement cost. Is this a liability value for lost or damaged garments? Should it appear in the price proposal or in a separate statement? How will the Contracting Officer set it under PWS 1.17, and can the Government provide current replacement costs for each uniform item? ANSWER: in the price proposal. I could find a general replacement cost for each item
1. Quantities. Technical Exhibit 3 lists estimates. Are any quantities guaranteed minimums? Are they based on historical usage, and should offerors expect significant fluctuation? Would the monthly payment stay the same if actual quantities vary? Do the quantities cover a pickup cycle, a month, or the full 12-month CLIN? Which quantities govern evaluation? How many employees are covered? ANSWER: Those are the projected quantities and they fluctuate. The monthly payment would remain the same given it is a C type contract. Once a month. All employees that need dry cleaning would be covered, it changes, that is why we wanted to do a C type for all employees that need dry cleaning.
1. Frequency versus volume. PWS 5.1 calls for twice-weekly dry cleaning of blazers, slacks, and ties, but the monthly estimates (16 blazers, 80 slacks, 25 ties) look low for that frequency. Which controls? ANSWER: It varies; this is an estimate.
1. “Coat, 2 each, laundered” line. Technical Exhibit 3 lists this with no PWS reference. What garment is it, and what service is required? ANSWER: Coat is separate from trench coat.
1. Trench coats. Does the estimate of two per month conflict with the twice-per-year cleaning in PWS 5.1? Does it mean two coats serviced twice a year (four cleanings), two total cleanings a year, or two cleanings a month? ANSWER: Twice per year.
1. Bracketed PWS values. Are these final? Option notice (60 days, PWS 1.5), discrepancy resolution (3 business days, 1.15), returns correction (3 business days, 1.16), alteration turnaround (14 business days, 5.3), trench coat frequency (5.1), and the lost-article replacement basis (1.17). ANSWER: See updated SOW.
1. Option and extension periods. ANSWER: The 30-day notice in FAR 52.217-9 applies to option year renewals, and 52.217-8 covers an extension of up to 6 months.
1. Missing attachments. The QASP (Attachment 4), the service deduction formula (Technical Exhibit 1), the COR designation letter, and FAR 52.212-3 and 52.212-5 (listed as attached in Block 27a) are not in the package. ANSWER: See Technical Exhibit. COR designation letter not needed at this time.
1. Wage determination. WD 2015-5613 rev. 34 points laundry occupations to WD 1977-1297, which is not attached. Please provide it and its revision. Does the agency have guidance for applying wage and fringe requirements to commercial laundry employees who spend only part of their time on this contract? The agency has said the federal-hire rates in Section C.4 are informational only. ANSWER: See attached in original solicitation.
1. Technical subfactors. The instructions say “all five subfactors,” but only two are described: the Dry-Cleaning Operations Plan and the Quality Control Plan. Are only those two required? If there are more, please provide them. Are there page limits or format requirements? ANSWER: There are two.
1. Tiered set-aside. Block 10 of the SF 1449 shows a 100% small business set-aside, while the tiered language covers SDVOSB, VOSB, WOSB/8(a), and other small business. Tier 3 mentions both WOSB and HUBZone. ANSWER: Tier 3 includes all of the above.
1. Subcontracting. Would the VA permit a small-business prime to perform pickup, transportation, delivery, inspections, tracking, and contract administration itself while subcontracting the cleaning, pressing, and alterations to a qualified commercial facility, within the subcontracting limit? ANSWER: FAR 52.219-14 applies, with a 50% limit
1. Multiple offers. Can a prime contractor submit multiple offers, each with a different subcontractor? ANSWER: Please see the solicitation. Limitations on subcontracting.
1. Subcontractor past performance. If the offer relies on a subcontractor’s past performance and local pickup, delivery, and cleaning, what must be submitted under VAAR 852.215-71, and will the named subcontractor commitment be binding at award? ANSWER: Please review the solicitation.
1. Pickup and return schedule. Please confirm that items picked up Monday are returned Thursday, items picked up Thursday are returned the following Monday, and each visit combines drop-off and pickup (PWS 5.1 and 5.2). Does the 104 annual pickups and deliveries mean 104 scheduled cemetery visits, each including both pickup and return? What are the preferred pickup and delivery times, and what garment turnaround is expected? ANSWER: This is one pick up and drop off will be. It will vary. 104 total visits.
1. Holidays. When a visit falls on a federal holiday such as Veterans Day, Thanksgiving, or a Monday holiday, should it move to another Monday-through-Thursday day? Is there a preferred time window? How are holiday pickups and returns handled, and which records trigger acceptance? ANSWER: It should be moved to next business day.
1. Invoicing. Section B.1 item 3 leaves the invoicing frequency unchecked, while PWS 4.6 calls for one invoice per month. Please confirm monthly invoicing in arrears, and whether billing is based on actual quantities serviced. ANSWER: Monthly
1. Personnel access. Will drivers need a background investigation or PIV badge under FAR 52.204-9 and VAAR 852.204-70? If so, what is the process and timeline before the January 31, 2027 start date? ANSWER: No
1. Incumbent and history. Is this a new requirement? Is related notice 36C78627Q0015 a prior solicitation for it? If there is an incumbent, please provide the contract number, incumbent name, and awarded price. ANSWER: Yes, it was the Sources Sought Notice. There is no incumbent.
1. Insurance. Are certificates of insurance required at award? ANSWER: No.