Price Schedule Breakdown.docx

DOCX document 18 KB Posted

Attached to
Y1PZ--884-MR26-007 Repair Sprinkler System Pumps and Motors at Black Hills National Cemetery
Solicitation number
36C78626B0025
Issued by

About this file

This is a Price Schedule Breakdown template for a federal construction solicitation related to repairing sprinkler system pumps and motors at Black Hills National Cemetery. The document is issued by the Department of Veterans Affairs National Cemetery Administration under Solicitation Number 36C78626B0025 for Project Number 884-MR26-007, located at 20901 Pleasant Valley Drive, Sturgis, South Dakota 57785.

The price schedule template is structured using the Construction Specifications Institute (CSI) MasterFormat divisions and requires contractors to provide cost breakdowns across multiple categories including general conditions, labor costs (Project Manager, Site Superintendent, Quality Control Manager, and Safety Officer with associated hours and rates), and work divisions spanning divisions 0 through 48 covering site work, concrete, masonry, metals, thermal and moisture protection, equipment, fire suppression, plumbing, HVAC, electrical, utilities, and other construction trades. Contractors must complete the pricing template by entering hourly labor rates and total prices for each division, with a final calculation of subtotal, overhead, profit, and total contract price. This is a template document and does not specify response dates, award dates, or contract-specific pricing terms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Price Schedule Breakdown Solicitation Number 36C78626B0025 Project Number 884-MR26-007 Repair Sprinkler System Pumps and Motors at Black Hills NC

Price Schedule Breakdown

Contractor:

RFP Number:

Division #
Division
Price
0
General Conditions
1
General Requirements
Project Manager
Hours
Rate
Total Price
Site Superintendent
Hours
Rate
Total Price
Quality Control Manager
Hours
Rate
Total Price
Safety Officer
Hours
Rate
Total Price
2
Existing Conditions/Site Work
3
Concrete
4
Masonry
5
Metals
6
Wood, Plastics & Composites
7
Thermal and Moisture Protection/Roofing
8
Openings
9
Finishes
10
Specialties
11
Equipment
12
Furnishings
13
Special Construction
14
Conveying Equipment
21
Fire Suppression
22
Plumbing
23
Heating, Ventilating, & Air Conditioning
25
Integrated Automation
26
Electrical
27
Communications
28
Electronic Safety & Security
31
Earthwork
32
Exterior Improvements
33
Utilities
34
Transportation
48
Electrical Power Generation

Misc

Divisions Subtotal

Overhead

Profit

Total

File details come from the government source that posted it. Updated .