This document is an Amendment (Amendment No. 2) to Solicitation 36C78625Q0091 for the San Joaquin Valley National Cemetery Resurgent Pump & Filter Replacement project. The amendment addresses multiple Requests for Information (RFIs) related to the project, providing clarifications on technical details such as pump installation configuration, crane access, roof removal, and work requirements. Key specifications include: the resurgent pump is located in a wet pit, a ton truck with a multi-stage boom has been used previously for pump removal, and the contractor is responsible for removing and replacing the filter inside the storage lake pumphouse.
Critical project parameters include work hours between 7:00 a.m. and 3:00 p.m. PST, requiring strict coordination with the government to ensure continuous water availability. The offer due date remains June 25, with the prime contractor required to provide onsite supervision for all work, including subcontractor activities. The project involves replacing a pump and filter system, with the government providing a new insertion/removal cable assembly. Contractors are expected to conduct a field survey, provide new electrical service, and coordinate carefully to minimize water system downtime.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Photos - RFI.pdf | ||
| AMENDMENT 1-36C78625Q0091.docx | DOCX document | |
| 36C78625Q0091 RFQ resurgent pump-San Jaoquin.docx | DOCX document | |
| WAGE DETERMINATION.pdf | ||
| VA Notice of Limitations on Subcontracting - Certificate.docx | DOCX document | |
| SOW.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFIs - San Joaquin Valley National Cemetery 913-M&R-FY25-062 Resurgent Pump & Filter Replacement
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
06-24-2025
913-M&R-FY25-062
36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172
36C786 Department of Veterans Affairs National Cemetery Administration Contracting Services 18434 Joplin Road Triangle VA 22172 To all Offerors/Bidders
36C78625Q0091
X x
Amendment No.2 to Solicitation 36C78625Q0091 San Joaquin Valley National Cemetery Resurgent Pump & Filter Replacement
This amendment addresses the RFIs submitted please see attached and photos offer due date remains June 25.
Michael Giaquinto
SEE attached photos for additional information
1. Please specify existing flygt pump installation configuration The resurgent pump is in a wet pit.
2. How was the previous pump lifted from well. Was it a crane? What is approved path and setup area for the crane A ¾ ton truck with a multi-stage boom has been used in the past. Specific coordination will take place regarding the access path upon contract award.
3. Who is responsible for removing the roof of the mechanical building? Per the scope of work, the contractor is responsible for all work to remove, replace the filter inside the SJVNC storage lake pumphouse.
4. Is there a requirement for the size of the required crane? The Government has not specified a crane size. The contractor is responsible to supply an adequate crane. As stated in a prior RFI, a ¾ ton truck with a multi-state boom has been used in the past. Specific coordination will take place upon award regarding the access path.
5. What is the design load of the roof section to be removed? The requested information is unknown. Contractors should conduct a field survey per the work scope prior to providing an offer on the project.
6. What is the allowed time frame that the water system can be down to replace the filter. The work scope requires strict coordination with the Government to ensure the continuous availability of water. Interruption(s) to the delivery of water negatively impacts irrigation so extended down time (more than a few hours approved in advance) is unacceptable.
7. Is the pump removal system in good working order? Per the scope, the Government is providing the insertion/removal cable assembly. It is new and has never been utilized.
8. What is the size of the pump? This is not noted in the Scope. Per the scope, the resurgent pump/motor assembly is specified and includes reference to the emoved brand and part number. Photo of removed pump for information only:
9. What is the length of the existing pump/motor electrical cables? Not applicable. The contractor will provide new electrical service and all other items required by the scope. Dedicated electrical service is located above the wet pit pump location which is approximately 30 feet above an operational pump.
Additional clarification from the cemetery:
Work hours will be between 7:00 a.m. and 3:00 p.m. PST unless otherwise approved by the COR in advance.
The prime contractor will have onsite supervision for all work that takes place, including work by subcontractors. If the prime contractor is not on site, no work shall be done.