About this file

36C78619Q0130 Attachment C - Price Cost List.pdf

View the file

Other files

File Type Posted
36C78619Q0130-0001000.docx DOCX document
36C78619Q0130-0001001.pdf PDF
36C78619Q0130-004.pdf PDF
36C78619Q0130-002.pdf PDF
36C78619Q0130-001.pdf PDF
36C78619Q0130-000.pdf PDF
36C78619Q0130-005.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

LOS ANGELES NATIONAL CEMETERY

SHRINE PROJECT – TURF RENOVATION

May 28, 2019 through 180 calendar days

PRICE/COST SCHEDULE

CLIN

NO. DESCRIPTION EST.

QTY UNIT UNIT PRICE TOTAL PRICE

Work Area Survey:

Professional Land Survey to quantify total square-footage of work area.

1 JB $__________ $__________

Soil Testing:

Agricultural Soil Testing and Recommendations.

3 EA $__________ $__________

Turf Replacement:

Renovate Existing Cemetery Turf With New Sod

1,000,000 See notes (1 & 2)

SF $__________ $__________

Clean Upright Headstones:

Clean Upright Marble Headstones.

10,000 EA $__________ $__________

Clean Flat Markers:

Clean Flat Marker Marble Headstones.

2,200 EA $__________ $__________

Irrigation Sprinkler Head Protectors: Precast concrete collars to protect sprinklers from vehicular damage.

300 EA $__________ $__________

0007 Bonding (2%) 1 LS $__________ $__________

GRAND TOTAL ESTIMATED COST:

PERFORMANCE WORK STATEMENT
LOS ANGELES NATIONAL CEMETERY
SHRINE PROJECT – TURF RENOVATION May 28, 2019 through 180 calendar days