36C78618R0422-007.pdf
PDF 359 KB Posted
- Solicitation number
- 36C78618R0422
About this file
36C78618R0422 Attachment 1 - Replace Flower Watering Stations Proj A.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C78618C0225-000.docx | DOCX document | |
| 36C78618R0422-002.pdf | ||
| 36C78618R0422-003.pdf | ||
| 36C78618R0422-001.docx | DOCX document | |
| 36C78618R0422-008.pdf | ||
| 36C78618R0422-005.pdf | ||
| 36C78618R0422-006.pdf | ||
| 36C78618R0422-009.pdf | ||
| 36C78618R0422-010.docx | DOCX document | |
| 36C78618R0422-004.pdf | ||
| 36C78618R0422-000.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SITE FURNISHINGS
32 30 00-1
PART 1 - GENERAL
1.1 GENERAL PROVISIONS
SECTION 32 30 00
SITE FURNISHINGS
A. Reference specification 010002 “General Requirements”.
1.2 DESCRIPTION
A. Work Included: Provide manpower, materials, tools and equipment necessary to complete the work of this Section, including but not limited to the following:
1. Furnish and install the Flower-watering stations, including trash receptacles, water spigot, and flower vase container and complete any required work necessary to make the water supply equipment operate using the water supply source indicated. Provide indicated drainage facilities to free drain water.
2. Steel Pipe Bollards, Chain and Locks
1.3 RELATED WORK
A. The following items are not included in this Section and will be performed under the designated Sections:
1. Section 03 30 00: CAST-IN-PLACE-CONCRETE
1.4 SUBMITTALS
A. Submit the following in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, AND SAMPLES:
1. General: For each item specified in description of work or Part 2 - Products, provide information showing complete detail, location in the project, material and size of components, method of joining various components and assemblies, finish, and location, size and type of anchors. Mark items requiring field assembly for erection identification and furnish erection drawings and instruction.
2. Provide templates and rough-in measurements as required.
3. Provide samples of full range of colors and finishes available for review and approval, prior to ordering.
32 30 00-2
1.5 REFERENCE STANDARDS
A. The publications listed below form a part of this specification and the work shall comply with pertinent standards of the latest editions as specified below or by industry standards unless designated otherwise herein.
B. American Society for Testing and Materials (ASTM):
B221-08 Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes
A53/A53M-2012 ......................... Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless
A865/A865M-06(2017) ............... Standard Specification for Threaded Couplings, Steel, Black or
Zinc-Coated (Galvanized) Welded or Seamless, for Use in
Steel Pipe Joints
C. American Welding Society (AWS):
D1.2-97 Structural Welding Code Aluminum
D. National Association of Architectural Metal Manufacturers (NAAMM)
PART 2 – PRODUCTS
2.1 FLOWER WATERING STATIONS: GENERAL
A. Flower watering station materials, dimensions, functionality, construction, finishes and colors shall fully comply with the specifications and Contract Drawings or be deemed as approved equal. To achieve approval as an equal, submittal of a point by point comparison of the proposed equal product to the specifications and Contract Drawings is required by the
32 30 00-3 contractor during the submittal process. If the product being submitted for approval as an approved equal has any features that are different than the specifications and Contract
Drawings, they must be identified in the submittal. If the differences result in a product that is deemed by the reviewer as being less than that specified and shown in the Contract
Drawings, then the process for attempting approval as an approved equal shall NOT be performed as a submittals process and the submittal will be returned unapproved Any further attempt to have the product approved for use in the project shall be submitted with a variance request along with explanation of the differences, why they should be accepted and any cost or project completion factors shall be included. The elements included in the flower watering station to which this paragraph is applicable are:
1. TRASH RECEPTACLE (Paragraph 2.2 of this Specification Section)
2. FLOWER VASE RECEPTACLE (Paragraph 2.3 of this Specification Section)
3. WATER SPIGOT ASSEMBLIES (Paragraph 2.4 of this Specification Section)
2.2 TRASH RECEPTACLE
A. Trash receptacles shall completely meet the specifications and Contract Drawings or be approved as an equal.
B. MATERIALS
1. Main body construction shall be 3/8” x 1” vertical solid steel bar; 1/4” x 2-1/2” horizontal solid steel bands; 3/8” x 3” steel support bars; 5/8” solid steel top ring; leveling feet with
3/8” diameter threaded steel shaft. All trash receptacles shall be signed to read “TRASH” as indicated on the details in the Contract Drawings. Sign material, finish, color, font and font size shall be as shown on the Contract Drawings. Mounting of signs shall be as shown on approved Shop Drawings. All joints of steel components shall be fully welded and ground smooth throughout.
2. Unit shall contain one 36-gallon capacity high density plastic inner liner with its weight not to exceed (6 lbs.. The unit manufacturer shall provide the black plastic inner liners which shall be molded on tooling designed for and owned by the unit manufacturer. They inner liner shall offer maximum capacity and strength with lightweight construction using critical molded ribs, integral handholds, and high strength materials. This style of inner liner shall minimizes handling difficulty and facilitate easy emptying and storage while affording long service life.
C. REQUIRED OPTIONS
1. Lids: Units shall be shipped with manufacturer’s standard tapered formed lid with formed dome and with self-closing door. The lids shall be made of the manufacturer’s standard high strength plastic material designed to match the selected manufacturer’s standard
32 30 00-4 color. Each lid shall be provided with a stainless steel aircraft cable and attachments to secure the lid to the unit.
2. Standard colors: Victor Stanley Standard Bronze.
3. Mounting plate: Standard (1) anchor bolt hole.
D. FINISHES
1. All fabricated metal components are steel shotblasted, etched, phosphatized, preheated, and electrostatically powder-coated with TGIC polyester powder coatings. Products are fully cleaned and pretreated, preheated and coated while hot to fill crevices and build coating film. Coated parts are then fully cured to coating manufacturer's specifications where the thickness of the resulting finish averages a minimum of 200-250 microns.
2. Project location has been determined to be a high salt abusive climate. Hot dip galvanizing before powder coating is required. Hot dip galvanizing will provide greater protection in salty climates (or where deicing chemicals possibly containing salt may be used) but yields a slightly less smooth coating finish. All of the fabricated metal components and castings shall be hot dip galvanized.
2.3 FLOWER VASE RECEPTACLE
A. Flower vase receptacles shall completely meet the specifications and Contract Drawings or be approved as an equal.
B. MATERIALS:
1. All fabricated metal components are steel shot blasted, etched, phosphatized, preheated, and electrostatically powder-coated with TGIC polyester powder coatings.
Products are fully cleaned and pretreated, preheated and coated while hot to fill crevices and build coating film. Coated parts are then fully cured to coating manufacturer's specifications where the thickness of the resulting finish averages a minimum of 200-250 microns.
2. Project location has been determined to be a high salt abusive climate. Hot dip galvanizing before powder coating is required. Hot dip galvanizing will provide greater protection in salty climates (or where deicing chemicals possibly containing salt may be used) but yields a slightly less smooth coating finish. All of the fabricated metal components and castings shall be hot dip galvanized.
3. Flower vase receptacles shall or be regularly produced by the manufacturer for use at VA
Cemeteries, with a special light weight hinged lid designed for the VA Cemeteries. Flower vase receptacles shall be of the size indicated on the Contract Drawings, and shall be of the same construction, finish and indicated Victor Stanley color as the trash receptacles, with the following exceptions:
3. All flower vase receptacles shall be signed to read “FLOWER VASES” as indicated on the details in the Contract Drawings.
32 30 00-5
4. The “Floral Regulations” decal shall be as indicated on the Contract Drawings and be factory applied to the top of the receptacle lid. Decal shall be pressure sensitive vinyl designed for outdoor use. The content of the decal, lettering color and background color of decal shall be as approved during the shop drawing process. The materials for the decal shall be regularly used by the manufacturer for flower vase receptacles at VA
National Cemeteries.
2.4 WATER SPIGOT ASSEMBLIES
A. See drawings for requirements, and other specification sections for pipe and other component requirements. Submit for approval.
2.5 STEEL PIPE BOLLARDS AND CHAIN AND LOCK
A. Provide steel pipe bollard, ASTM A-53, Grade B, seamless, galvanized steel, Schedule 40, where shown on the contract drawings. Fittings to meet ASTM A865. See specification
221100 for more information on requirements for bollard pipe/fittings. Minimum pipe bollard requirements are as follows: install a 4” diameter galvanized steel bollard, capped at the top, per above material requirements and bury entire length in an 18” diameter cylindrical concrete foundation which shall be from ground level down to a depth of 48”.
Provide between 1.5-3.0” concrete cover distance from bottom of galvanized steel bollard and the bottom of the concrete foundation. Note this concrete foundation will be installed in close proximity to a stone drain pit for the Water Station drain. Submit a shop drawing showing both the concrete foundation and the stone pit such that both will function as intended.
PART 3 - EXECUTION
3.1 INSPECTION
A. Prior to installation of any of the work in this section, contractor shall inspect the planned installation locations to insure that conditions are not significantly different from those indicated on the contract drawings. All materials shall be inspected prior to installation to insure compliance with the contract documents and to insure there is no damage. Should conditions be different from those indicated on the contract documents, contractor should immediately notify the Resident Engineer.
3.2 PREPARATION
A. Stake alignment and locations for all site furnishings for review and approval by Resident
Engineer. Verify that all elements in this section “fit” within location provided.
B. Install items rigid, plumb and true to lines and levels shown.
32 30 00-6
C. Assemble (if required) and install items as per manufacturer’s printed instructions, or approved shop drawings, unless otherwise specified or shown.
3.3 INSTALLATION
A. Flower Watering Stations:
1. Stake location of flower watering stations and obtain approval from Owner’s
Representative prior to forming concrete pad. Install concrete pad in accordance with
033000 – CAST-IN-PLACE CONCRETE.
2. Anchor trash receptacle and flower vase containers as shown on the Contract Drawings and following the manufacturer’s recommended installation instructions.
3. Install water spigot assemblies according to manufacturer’s recommendations, including pipe, isolation valve, fittings, pressure reducing valve and valve boxes. All anchoring hardware shall be stainless steel. Coordinate all work with other trades.
4. Following installation of water spigot, install washed stone for splash area.
B. Pipe Bollards:
1. Install galvanized steel pipe bollards in concrete footings, 4,000 PSI @ 28 days, conforming to dimensions as indicated in Contract Drawings and in accordance with
SECTION 033000 - CAST-IN-PLACE CONCRETE.
2. Backfill and compact excavation around bollard or sleeve in accordance with SECTION
31 20 00 – EARTH MOVING.
3. Ensure that all bollards are plumb and aligned within a maximum one-fourth inch tolerance of indicated location on plans or by requirement of regulatory requirements, whichever is more stringent.
4. Fill pipe bollard with concrete as shown. Provide rounded smooth, trowel finish top for positive drainage.
5. Clean any excess material from surface of bollard, and apply finish according to specifications.
6. Furnish and install galvanized steel eyebolts with washers and nuts as indicated for the chain and lock attachment. Furnish and install the chain and padlock(s) and provide spare locks and keys to the Resident Engineer.
3.4 CLEAN UP
A. Clean up area of excess material and debris. Clean above ground portions of all receptacles and other site improvements.
- - - E N D - - -
05-10
EARTH MOVING (SHORT FORM)
31 20 11 - 1
SECTION 31 20 11
EARTH MOVING (SHORT FORM)
PART 1 - GENERAL
1.1 DESCRIPTION
This section specifies the requirements for furnishing all equipment, materials, labor and techniques for earthwork including excavation, fill, backfill and site restoration utilizing fertilizer, seed and/or sod.
1.2 DEFINITIONS
A. Unsuitable Materials:
1. Fills: Topsoil, frozen materials; construction materials and materials subject to decomposition; clods of clay and stones larger than 75 mm (3 inches); organic materials, including silts, which are unstable; and inorganic materials, including silts, too wet to be stable.
2. Existing Subgrade (except footings): Same materials as above paragraph, that are not capable of direct support of slabs, pavement, and similar items, with the possible exception of improvement by compaction, proof rolling, or similar methods of improvement.
3. Existing Subgrade (footings only): Same as Paragraph 1, but no fill or backfill.
B. Earthwork: Earthwork operations required within the new construction area. It also includes earthwork required for auxiliary structures and buildings and sewer and other trench work throughout the job site.
C. Degree of Compaction: Degree of compaction is expressed as a percentage of maximum density obtained by the test procedure presented in any of the following: // AASHTO // T99 // T180 // Method A. // ASTM // D698 //
D1557 // Method A. //
D. The term fill means fill or backfill as appropriate.
1.3 RELATED WORK
A. Materials testing and inspection during construction: Section 01 45 29, TESTING LABORATORY SERVICES.
1.4 CLASSIFICATION OF EXCAVATION
A. Unclassified Excavation: Removal and disposal of pavements and other man-made obstructions visible on the surface; utilities, and other items including underground structures indicated to be demolished and removed;
together with any type of materials regardless of character of material and obstructions encountered.
B. Classified Excavation: Removal and disposal of all material not defined as rock.
31 20 11 - 2
C. Rock Excavation:
1. Solid ledge rock (igneous, metamorphic, and sedimentary rock).
2. Bedded or conglomerate deposits so cemented as to present characteristics of solid rock which cannot be excavated without blasting; or the use of a modern power excavator (shovel, backhoe, or similar power excavators) of no less than 0.75 m3 (1 cubic yard) capacity, properly used, having adequate power and in good running condition.
3. Boulders or other detached stones each having a volume of 0.4 m3 (1/2 cubic yard) or more.
1.5 MEASUREMENT AND PAYMENT FOR ROCK EXCAVATION
A. Measurement: Cross section and measure the uncovered and separated materials, and compute quantities by the Registered Professional Land
Surveyor or Registered Civil Engineer, specified in Section 01 00 02, GENERAL REQUIREMENTS. Do not measure quantities beyond the following limits:
1. 300 mm (12 inches) outside of the perimeter of formed footings.
2. 600 mm (24 inches) outside the face of concrete work for which forms are required, except for footings.
3. 150 mm (6 inches) below the bottom of pipe and not more than the pipe diameter plus 600 mm (24 inches) in width for pipe trenches.
4. The outside dimensions of concrete work for which no forms are required (trenches, conduits, and similar items not requiring forms).
1.6 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Rock Excavation Report:
1. Certification of rock quantities excavated.
2. Excavation method.
3. Labor.
4. Equipment.
5. Land Surveyor's or Civil Engineer's name and official registration stamp.
6. Plot plan showing elevations.
C. Furnish to Project Engineer and COR, soil samples, suitable for laboratory tests, of proposed off site or on site fill material.
1.7 APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.
B. American Nursery and Landscape Association (ANLA):
31 20 11 - 3
2004....................American Standard for Nursery Stock
C. American Association of State Highway and Transportation Officials
(AASHTO):
T99-01 (R2004)..........Moisture-Density Relations of Soils Using a 2.5 kg (5.5 lb) Rammer and a 305 mm (12 inch) Drop
T180-01 (2004)..........Moisture-Density Relations of Soils Using a
4.54-kg [10 lb] Rammer and a 457 mm (18 inch)
Drop
D. American Society for Testing and Materials (ASTM):
D698-07.................Laboratory Compaction Characteristics of Soil
Using Standard Effort
D1557-07................Laboratory Compaction Characteristics of Soil
Using Modified Effort
ASTM D6707 / D6707M - 06(2016)e1:
Standard Specification for Circular-Knit Geotextile for Use in
Subsurface Drainage Applications
ASTM D5034 - 09(2017): Standard Test Method for Breaking Strength and
Elongation of Textile Fabrics (Grab Test)
E. Standard Specifications of State Department of Transportation, latest revision.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Fills: Materials approved from on site and off site sources having a minimum dry density of 1760 kg/m3 (110 pcf), a maximum Plasticity Index of 6, and a maximum Liquid Limit of 30.
B. Granular Fill:
1. Under concrete slab, crushed stone or gravel graded from 25 mm (1 inch) to 4.75 mm (No. 4).
2. Bedding for sanitary and storm sewer pipe, crushed stone or gravel graded from 13 mm (1/2 inch) to 4.75 mm (No. 4).
C. Fertilizer: (5-10-5) delivered to site in unopened containers that clearly display the manufacturer's label, indicating the analysis of the contents.
D. Seed: Grass mixture comparable to existing turf delivered to site in unopened containers that clearly display the manufacturer's label, indicating the analysis of the contents.
E. Sod: Comparable species with existing turf. Use State Certified or State
Approved sod where possible. Deliver sod to site immediately after cutting and in a moist condition. Thickness of cut must be 19 mm to 32
31 20 11 - 4 mm (3/4 inch to 1 1/4 inches) excluding top growth. There shall be no broken pads and torn or uneven ends.
F. Crushed Stone: Material conforming to the state’s Standard
Specifications for No. 2 Stone.
G. Subbase Course: Material conforming to the state’s Standard
Specifications for Subbase Course, Type 2.
H. Bedding / Drainage stone (aggregate) for foundation drainage and storm sewer pipe: AASHTO #57 stone.
I. Buried Warning and Identification Tape: Metallic core or metallic-faced, acid- and alkali-resistant polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines. Provide tape on rolls, 3 inch minimum width, color coded as specific below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, “CAUTION, BURIED
(intended service) LINE BELOW” or similar wording. Color and printing shall be permanent, unaffected by moisture or soil. Warning tape color codes:
Red: Electric
Yellow: Gas, Oil, Dangerous Materials
Orange: Telephone and Other Communications
Blue: Water Systems
Green: Sewer Systems
J. Separation Fabric: Fabric shall be non-woven with elongation greater than 50 percent and be on the state’s Department of Transportation
Approved Material List for separation application.
K. Geotextile Filter Fabric: Geotextile fabric shall be needle punched non-woven geotextile composed of polypropylene fibers and confirm to
ASTM D6707. Elongation shall be greater than 50 percent and the flow rate shall be a minimum of 95 gpm/sqft. The filaments shall consist of a long-chain synthetic polymer and shall contain stabilizers and/or inhibitors added to the base plastic to make the filaments resistant to deterioration due to ultraviolet and heat exposure. The fabric shall have a minimum physical strength meeting industry standards when tested in accordance with ASTM D 5034 using the grab test method with 1 square inch jaws and a constant rate of travel of 12 inches per minute. The fabric shall be constructed so that the filaments will retain their relative position with respect to each other. The edges of the fabric shall be selvaged or otherwise finished to prevent the outer material from pulling away from the fabric. The fabric shall be woven into a width that may be installed as shown without longitudinal seams.
31 20 11 - 5
PART 3 - EXECUTION
3.1 SITE PREPARATION
A. Clearing: Clearing within the limits of earthwork operations as described or designated by the Project Engineer or COR. Work includes removal of trees, shrubs, fences, foundations, incidental structures, paving, debris, trash and any other obstructions. Remove materials from the Cemetery Property.
B. Grubbing: Remove stumps and roots 75 mm (3 inches) and larger diameter.
Undisturbed sound stumps, roots up to 75 mm (3 inches) diameter, and nonperishable solid objects which will be a minimum of 900 mm (3 feet) below subgrade or finished embankment may be left. Cemetery Projects: do not leave material within the burial profile up to 2400 mm (8 feet) below finished grade.
C. Trees and Shrubs: Trees and shrubs, not shown for removal, may be removed from the areas within 4500 mm (15 feet) of new construction and
2250 mm (7’-6”) of utility lines if such removal is approved in advance by the Project Engineer or COR. Remove materials from the Cemetery
Property. Trees and shrubs, shown to be transplanted, shall be dug with a ball of earth and burlapped in accordance with the latest issue of the, "American Standard for Nursery Stock", of the American Association of Nurserymen, Inc. Transplant trees and shrubs to a permanent or temporary position within two hours after digging. Maintain trees and shrubs held in temporary locations by watering as necessary and feeding semi-annually with liquid fertilizer with a minimum analysis of 5 percent nitrogen, 10 percent phosphorus and 5 percent potash. Maintain plants moved to permanent positions as specified for plants in temporary locations until the conclusion of the contract. Box, and otherwise protect from damage, existing trees and shrubs which are not shown to be removed in the construction area. Repair immediately damage to existing trees and shrubs by trimming, cleaning and painting damaged areas, including the roots, in accordance with standard industry horticultural practice for the geographic area and plant species. Building materials shall not be stored closer to trees and shrubs, that are to remain, than the farthest extension of their limbs.
D. Stripping Topsoil: Unless otherwise indicated on the drawings, the limits of earthwork operations shall extend anywhere the existing grade is filled or cut or where construction operations have compacted or otherwise disturbed the existing grade or turf. Strip topsoil as defined herein, or as indicated in the geotechnical report, from within the limits of earthwork operations as specified above unless specifically
31 20 11 - 6 indicated or specified elsewhere in the specifications or shown on the drawings. Topsoil shall be fertile, friable, natural topsoil of loamy character and characteristic of the locality. Topsoil shall be capable of growing healthy horticultural crops of grasses. Stockpile topsoil and protect as directed by the COR. Eliminate foreign material, such as weeds, roots, stones, subsoil, frozen clods, and similar foreign materials, larger than 0.014 m3 (1/2 cubic foot) in volume, from soil as it is stockpiled. Retain topsoil on the station. Remove foreign materials larger than 50 mm (2 inches) in any dimension from topsoil used in final grading. Topsoil work, such as stripping, stockpiling, and similar topsoil work, shall not, under any circumstances, be carried out when the soil is wet so that the tilth of the soil will be destroyed.
1. Cemetery Projects: Recommend that the top soil be tested for chemicals, pesticides and fertilizers if topsoil is to be removed from lands formerly utilized as farmland, to verify suitability for use as topsoil in the cemetery where new lawn areas are to be established.
2. Concrete Slabs and Paving: Score deeply or saw cut to insure a neat, straight cut, sections of existing concrete slabs and paving to be removed where excavation or trenching occurs. Extend pavement section to be removed a minimum of 300 mm (12 inches) on each side of widest part of trench excavation and insure final score lines are approximately parallel unless otherwise indicated. Remove material from the Cemetery Property.
E. Disposal: All materials removed from the property shall be disposed of at a legally approved site, for the specific materials, and all removals shall be in accordance with all applicable Federal, State and local regulations. No burning of materials is permitted onsite.
3.2 EXCAVATION
A. Shoring, Sheeting and Bracing: Shore, brace, or slope to its angle of repose banks of excavations to protect workmen, banks, adjacent paving, structures, and utilities, in compliance with OSHA requirements.
1. Extend shoring and bracing to the bottom of the excavation. Shore excavations that are carried below the elevations of adjacent existing foundations.
2. If the bearing of any foundation is disturbed by excavating, improper shoring or removal of shoring, placing of backfill, and similar operations, provide a concrete fill support under disturbed foundations, as directed by Project Engineer or COR, at no additional cost to the Government. Do not remove shoring until permanent work in
31 20 11 - 7 excavation has been inspected and approved by Project Engineer or
COR.
B. Excavation Drainage: Operate pumping equipment, and/or provide other materials, means and equipment as required, to keep excavations free of water and subgrades dry, firm, and undisturbed until approval of permanent work has been received from the Project Engineer or COR.
Approval by the Project Engineer or COR is also required before placement of the permanent work on all subgrades. When subgrade for foundations has been disturbed by water, remove the disturbed material to firm undisturbed material after the water is brought under control.
Replace disturbed subgrade in trenches by mechanically tamped sand or gravel. When removed disturbed material is located where it is not possible to install and properly compact disturbed subgrade material with mechanically compacted sand or gravel, the Project Engineer or COR should be contacted to consider the use of flowable fill.
C. Blasting: Blasting shall be permitted only when authorized by the
Project Engineer or COR. Blasting shall be done with explosives of such quantity and power, and fired in such sequence and locations as to not injure personnel, damage or crack rock against which concrete is to be placed, damage property, or damage existing work or other portions of new work. The Contractor shall be responsible for damage caused by blasting operations.
D. Building Earthwork:
1. Excavation shall be accomplished as required by drawings and specifications.
2. Excavate foundation excavations to solid undisturbed subgrade.
3. Remove loose or soft material to solid bottom.
4. Fill excess cut under footings or foundations with 25 MPa (3000 psi) concrete, poured separately from the footings.
5. Do not tamp earth for backfilling in footing bottoms, except as specified.
E. Trench Earthwork:
1. Utility trenches (except sanitary and storm sewer):
a. Excavate to a width as necessary for sheeting and bracing and proper performance of the work.
b. Grade bottom of trenches with bell-holes, scooped-out to provide a uniform bearing.
c. Support piping on undisturbed earth unless a mechanical support is shown.
d. The length of open trench in advance of pipe laying shall not be greater than is authorized by the Project Engineer or COR.
31 20 11 - 8
2. Sanitary and storm sewer trenches:
a. Trench width below a point 150 mm (6 inches) above top of the pipe shall be 600 mm (24 inches) for up to and including 300 mm (12 inches) diameter and four-thirds diameter of pipe plus 200 mm (8 inches) for pipe larger than 300 mm (l2 inches). Width of trench above that level shall be as necessary for sheeting and bracing and proper performance of the work.
b. The bottom quadrant of the pipe shall be bedded on undisturbed soil or granular fill.
1) Undisturbed: Bell holes shall be no larger than necessary for jointing. Backfill up to a point 300 mm (12 inches) above top of pipe shall be clean earth placed and tamped by hand.
2) Granular Fill: Depth of fill shall be a minimum of 75 mm (3 inches) plus one-sixth of pipe diameter below the pipe of 300 mm (12 inches) above top of pipe. Place and tamp fill material by hand.
c. Place and compact as specified the remainder of backfill using acceptable excavated materials. Do not use unsuitable materials.
d. Use granular fill for bedding where rock or rocky materials are excavated.
F. Site Earthwork: Excavation shall be accomplished as required by drawings and specifications. Remove subgrade materials that are determined by the
Project Engineer or COR as unsuitable, and replace with acceptable material. If there is a question as to whether material is unsuitable or not, the Contractor shall obtain samples of the material, under the direction of the Project Engineer or COR, and the materials shall be examined by an independent testing laboratory for soil classification to determine whether it is unsuitable or not. Testing of the soil shall be performed by the contractor’s Testing Laboratory. When unsuitable material is encountered and removed, the contract price and time will be adjusted in accordance with Articles, DIFFERING SITE CONDITIONS, CHANGES and CHANGES-SUPPLEMENT of the GENERAL REQUIREMENTS as applicable.
Adjustments to be based on meters (yardage) in cut section only.
G. Finished elevation of subgrade shall be as follows:
1. Pavement Areas - bottom of the pavement or base course as applicable.
2. Planting and Lawn Areas - 100 mm (4 inches) below the finished grade, unless otherwise specified or indicated on the drawings.
3.3 FILLING AND BACKFILLING
A. General: Do not fill or backfill until all debris, unsatisfactory soil materials, obstructions, and deleterious materials have been removed
31 20 11 - 9 from the excavation. Proof-roll exposed subgrades with a fully loaded dump truck. Use excavated materials or borrow for fill and backfill, as applicable. Do not use unsuitable excavated materials. Do not backfill until foundation walls have been completed above grade and adequately braced, waterproofing or dampproofing applied, and pipes coming in contact with backfill have been installed, and inspected and approved by
Project Engineer or COR.
B. Proof-rolling Existing Subgrade: Proof-roll with a fully loaded dump truck. Make a minimum of one pass in each direction. Remove unstable uncompactable material and replace with granular fill material completed to mix requirements specified.
C. Placing: Place material in horizontal layers not exceeding 200 mm (8 inches) in loose depth and then compacted. Do not place material on surfaces that are muddy, frozen, or contain frost.
D. Compaction: Use approved equipment (hand or mechanical) well suited to the type of material being compacted. Do not operate mechanized vibratory compaction equipment within 3000 mm (10 feet) of new or existing building walls without the prior approval of the Project
Engineer or COR. Moisten or aerate material as necessary to provide the moisture content that will readily facilitate obtaining the specified compaction with the equipment used. Compact each layer until there is no evidence of further compaction and to not less than 95 percent of the maximum density determined in accordance with any of the following test methods: // AASHTO // T99 // T180 // Method A // ASTM // D698 // D1557
Method A //.
3.4 GRADING
A. General: Uniformly grade the areas within the limits of this section, including adjacent transition areas. Smooth the finished surface within specified tolerance. Provide uniform levels or slopes between points where elevations are indicated, or between such points and existing finished grades. Provide a smooth transition between abrupt changes in slope.
B. Cut rough or sloping rock to level beds for foundations. In unfinished areas fill low spots and level off with coarse sand or fine gravel.
C. Slope backfill outside the building away from the building walls for a minimum distance of 1800 mm (6 feet).
D. The finished grade shall be 150 mm (6 inches) below bottom line of windows or other building wall openings unless greater depth is shown.
E. Place crushed stone or gravel fill under concrete slabs on grade tamped and leveled. The thickness of the fill shall be 150 mm (6 inches), unless otherwise indicated.
31 20 11 - 10
F. Finish subgrade in a condition acceptable to the Project Engineer or COR at least one day in advance of the paving operations. Maintain finished subgrade in a smooth and compacted condition until the succeeding operation has been accomplished. Scarify, compact, and grade the subgrade prior to further construction when approved compacted subgrade is disturbed by contractor's subsequent operations or adverse weather.
G. Grading for Paved Areas: Provide final grades for both subgrade and base course to +/- 6 mm (0.25 inches) of indicated grades.
3.5 LAWN AREAS
A. General: Harrow and till to a depth of 100 mm (4 inches), new or existing lawn areas to remain, which are disturbed during construction.
Establish existing or design grades by dragging or similar operations.
Do not carry out lawn areas earthwork out when the soil is wet so that the tilth of the soil will be destroyed. Plant bed must be approved by
Project Engineer or COR before seeding or sodding operation begins.
B. Finished Grading: Begin finish grading after rough grading has had sufficient time for settlement. Scarify subgrade surface in lawn areas to a depth of 100 mm (4 inches). Apply topsoil so that after normal compaction, dragging and raking operations (to bring surface to indicated finish grades) there will be a minimum of 100 mm (4 inches) of topsoil over all lawn areas; make smooth, even surface and true grades, which will not allow water to stand at any point. Shape top and bottom of banks to form reverse curves in section; make junctions with undisturbed areas to conform to existing topography. Solid lines within grading limits indicate finished contours. Existing contours, indicated by broken lines are believed approximately correct but are not guaranteed.
C. Fertilizing: Incorporate fertilizer into the soil to a depth of 100 mm
(4 inches) at a rate of 12 kg/100 m2 (25 pounds per 1000 square feet).
D. Seeding: Seed at a rate of 2 kg/100 m2 (4 pounds per 1000 square feet) and accomplished only during periods when uniform distribution may be assured. Lightly rake seed into bed immediately after seeding. Roll seeded area immediately with a roller not to exceed 225 kg/m (150 pounds per foot) of roller width.
E. Sodding: Topsoil shall be firmed by rolling and during periods of high temperature the topsoil shall be watered lightly immediately prior to laying sod. Sod strips shall be tightly butted at the ends and staggered in a running bond fashion. Placement on slopes shall be from the bottom to top of slope with sod strips running across slope. Secure sodded slopes by pegging or other approved methods. Roll sodded area with a
31 20 11 - 11 roller not to exceed 225 kg/m (150 pounds per foot) of the roller width to improve contact of sod with the soil.
F. Watering: The contractor is responsible for having adequate water available at the site. As sodding or seeding is completed in any one section, the entire area shall be thoroughly irrigated by the contractor. For sod areas, this shall be done to a sufficient depth that the underside of the new sod pad and soil, immediately below sod, is thoroughly wet. Cemetery will be responsible for seed or sod areas once the area is accepted by the Government AND the required establishment period is completed by the contractor(if required, see specification 32 90 00 Planting for more information).
3.6 DISPOSAL OF UNSUITABLE AND EXCESS EXCAVATED MATERIAL
A. Disposal: Remove surplus satisfactory soil and waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off
Cemetery property.
1. Remove waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off Cemetery property.
B. Place excess excavated materials suitable for fill and/or backfill on site where directed.
C. Remove from site and dispose of any excess excavated materials after all fill and backfill operations have been completed.
D. Segregate all excavated contaminated soil designated by the Project
Engineer or COR from all other excavated soils, and stockpile on site on two 0.15 mm (6 mil) polyethylene sheets with a polyethylene cover. A designated area shall be selected for this purpose. Dispose of excavated contaminated material in accordance with State and Local requirements.
3.6 CLEAN-UP
Upon completion of earthwork operations, clean areas within contract limits, remove tools, and equipment. Provide site clear, clean, free of debris, and suitable for subsequent construction operations. Remove debris, rubbish, and excess material from the Cemetery Property.
11-01-16
PLANTING
32 90 00 - 1
SECTION 32 90 00
PLANTING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Plants, soils, turf, and landscape materials and accessories.
1.2 RELATED REQUIREMENTS
A. Topsoil Materials, Stripping and Stockpiling: Section 31 20 11, EARTH
MOVING.
B. Topsoil Testing: Section 01 45 29, TESTING LABORATORY SERVICES.
C. Erosion control: Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS.
D. Protection of Tress and Plantings: Section 02 41 10, DEMOLITION AND
SITE CLEARING.
E. Topsoil Placement and Compaction Test: Section 31 20 11, EARTH MOVING.
F. Landscape Irrigation: Section 32 84 00, PLANTING IRRIGATION.
1.3 APPLICABLE PUBLICATIONS
A. Comply with references to extent specified in this section.
B. American National Standards Institute (ANSI) Publications:
1. ANSI Z60.1-2014 - Nursery Stock.
2. ANSI Z133.1-2012 - Tree Care Operations-Pruning, Trimming, Repairing, Maintaining, and Removing Trees and Cutting Brush- Safety
Requirements.
C. ASTM International (ASTM):
1. C33/C33M-16-Concrete Aggregates.
2. C136/C136M-14 - Sieve Analysis of Fine and Coarse Aggregates.
3. D698-12 - Test Methods for Laboratory Compaction Characteristics of
Soil Using Standard Effort (12,400 ft-lbf/ft3 (600 kN-m/m3)).
4. D977-13e1 - Emulsified Asphalt.
5. D2028/D2028M-15 - Cutback Asphalt (Rapid-Curing Type).
6. D2103-15 - Polyethylene Film and Sheeting.
D. Hortus Third, most current edition: A Concise Dictionary of Plants
Cultivated in the United States and Canada.
E. National Cemetery Administration (NCA):
1. Handbook 3410 - Integrate Pest Management.
2. Handbook 3420-11 - Turfgrass Maintenance.
F. Turfgrass Producers International (TPI):
1. 2006 Guideline Specifications to Turfgrass Sodding.
32 90 00 - 2
G. United States Department of Agriculture (USDA):
1. Federal Seed Act-2011 - Rules and Regulations of the Secretary of
Agriculture.
H. United States Environmental Protection Agency (EPA):
1. 40 CFR Part 503-1993 - Biosolids Rule.
1.4 PREINSTALLATION MEETINGS
A. Conduct preinstallation meeting at project site minimum 30 days before beginning Work of this section.
1. Required Participants:
a. Contracting Officer's Representative (COR).
b. COR (RE).
c. Contractor.
d. Installer.
2. Meeting Agenda: Distribute agenda to participants minimum 3 days before meeting.
a. Inspection of planting materials.
b. Installation schedule.
c. Installation sequence.
d. Preparatory work.
e. Protection before, during, and after installation.
f. Installation.
g. Inspecting.
h. Environmental procedures.
3. Document and distribute meeting minutes to participants to record decisions affecting installation.
1.5 SUBMITTALS
A. Submittal Procedures: Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Manufacturer's Literature and Data:
1. Description of each product.
a. Seeds.
b. Sod.
c. Soil amendments.
d. Antidesiccant.
e. Erosion control materials.
f. Hydro mulch.
g. Non-Asphaltic Trackifier.
32 90 00 - 3
h. Herbicide.
i. Weed Control.
j. Mulches.
k. Edging.
2. Plant list: List of local/regional suppliers for each species to be installed. Include quantities, plant dimension (height x spread) and container/root ball size. Certify in writing, confirmed orders for plants by submitting a Bill of Sale for each plant to be installed.
Each plant of the same species shall be supplied by one grower only unless otherwise approved by COR.
a. Requests for substitutions of plants not available in size, quantity or type specified must be made within 30 days after
Contract award. Submit written evidence that a specified plant cannot be obtained and has been unobtainable since Contract award.
b. Substitutions will only be authorized when a plant (or its alternates as specified) is not obtainable and COR, in consultation with District Agronomist, authorizes a change order for use of nearest equivalent obtainable size or variety of plant having same essential characteristics with an equitable adjustment of contract price.
3. Warranty shall match the standard 1 year period.
C. Samples: Submit before beginning Work of this section:
Inert Mulch 2.3 kg (5 lb.) of each type to be used.
Organic Mulch 2.3 kg (5 lb.) of each type to be used.
Imported Topsoils 2.3 kg (5 lb.) of each type to be used.
Organic
Amendments
2.3 kg (5 lb.) of each type to be used.
32 90 00 - 4
Inert Mulch 2.3 kg (5 lb.) of each type to be used.
All pesticides required such as preemergence or post emergence herbicides, insecticides, or fungicides.
EPA approved labeling and
MSDS sheet for each such product selected for use.
Edging Materials Manufacturer's standard size
D. Test reports: Certify products comply with specifications.
1. Imported Topsoil: Provide 2.3 kg (5 lbs.) representative sample from each proposed source for testing, analysis, and approval. Deliver samples to acceptable testing laboratory and have testing report sent directly to COR. Testing reports to include following tests and recommendations according to Association of Official Agricultural
Chemists standards:
a. Soil Composition: USDA particle size analysis indicating percentages of sand, silt and clay, and percent organic matter.
Mechanical gradation (sieve analysis) and chemical (pH soluble salts) performed by public extension service agency, State Land
Grant College, or certified private testing laboratory.
Percentages of clay and silt to be determined by hydrometer.
b. Percent of organics to be determined by loss on ignition of oven-dried samples. Test samples to be oven-dried to constant weight at 110 degrees C (230 degrees F), plus or minus
5 degrees C (41 degrees F).
c. Macro and micro nutrient fertility tests as determined by
Chemical analysis to include Macro and micro nutrient fertility tests as determined by pH, Salinity (EC), Nitrate Nitrogen, Ammonium Nitrogen, Phosphorus, Potassium, Calcium, Magnesium, Soluble Copper, Zinc, Manganese, Iron, Saturation Extract Boron, Aluminum, Soluble Salts, Exchangeable Sodium Percentage (ESP), Sodium Adsorption Ratio (SAR).
d. Tests, as specified, for gradation, organics, soil chemistry and pH to be performed by testing laboratory retained by National
Cemetery Administration as described in Section 01 45 29, TESTING LABORATORY SERVICES.
32 90 00 - 5
e. Include recommendations for soil additives to correct soils deficiencies, as necessary, and for fertilizing and to adjust soil pH to optimum range for the site and the specified sod type’s liming applications to support successful turfgrass growth.
2. Organic Soil Amendment:
a. Testing: Provide testing by an independent laboratory, with the experience and capability to conduct the testing indicated following U.S. Composting Council Seal of Testing Assurance
(STA) procedures, or equivalent.
b. Soil Amendment Analysis: Provide documentation from supplier that compost has reached a monitored temperature of 140 degrees
Fahrenheit for at least one week. Engage an independent soil testing laboratory to test representative samples of compost and provide compost analysis report for the following parameters:
1) Percent organic matter, percent moisture, percent inerts
(foreign matter), pH, soluble salts, and particle size.
2) Nutrient content, including: Nitrogen (N), Phosphorus (P), Potassium (K), Calcium (Ca), and Magnesium (Mg) and Sulfur s.
3) Trace Metals, including: Arsenic (As), Cadmium (Cd), Chromium
(Cr), Copper (Cu), Lead (Pb), Mercury (Hg), Nickel (Ni), and
Zinc (Zn).
4) Maturity Indicator. Provide bioassay results. Provide
Carbon-Nitrogen ratio.
5) Stability Indicator: Provide respiration test results.
3. Amended Soil (in place): Following incorporation of amendments and additives, provide minimum six (6)samples per 3,700 sq. m
(40,000 sq. ft.), 150 mm (6 inch) depth by 75 mm (3 inch) diameter core samples of amended soil taken from project site for testing, analysis, and approval. Locate each samples as directed by COR from areas designated to be planted in turfgrass. Deliver samples to testing laboratories and have testing report sent directly to COR.
Obtain amended soil sample acceptance before seeding or hydroseeding.
E. Certificates: Certify products comply with specifications.
F. Before delivery, submit notarized certificates for approval to COR attesting that following materials meet specified requirements:
32 90 00 - 6
1. Plant Materials (Department of Agriculture certification by State
Nursery Inspector from the state in which the plant material originates declaring material to be free from insects and disease).
2. Fertilizers: Four certificates of analysis for each type of fertilizer.
3. Lime
4. Gypsum
5. Soil Sulfur
6. Humates
7. Mycorrhizae
8. Peat
9. Seed: Include guaranteed percentages of purity, weed content and germination of seed, and net weight and date of shipment.
10. Sod.
11. Membranes.
12. M-Binder
13. Hydro Mulching: Number of kilograms (pounds) of materials to be used per liter (gallon) of water.
G. Maintenance Data:
1. Care instructions for each plant material.
1.6 QUALITY ASSURANCE
A. Installer Qualifications:
1. Regularly installs specified materials and products.
2. Installed specified products with satisfactory service on five similar installations for minimum five years.
1.7 DELIVERY
A. Deliver products in manufacturer's original sealed packaging.
B. Mark packaging, legibly. Indicate manufacturer's name or brand, type, production run number, and manufacture date.
C. Before installation, return or dispose of products within distorted, damaged, or opened packaging.
D. Bulk Products:
1. Deliver bulk products away from buildings, utilities, pavement, and existing turf and planted areas. Maintain dry bulk product storage away from contaminants. Protect products from weather.
2. Install erosion control materials to prevent erosion or displacement of bulk products.
32 90 00 - 7
E. Notify COR of delivery schedule five days in advance, minimum. COR will inspect materials upon arrival. Remove unacceptable plant materials from project site immediately.
F. Protect plants during delivery to prevent damage to root balls or desiccation of leaves.
G. Protect trees during transport by covering root balls and tying branches.
H. Machine dug plants are permitted provided root balls are sized according to ANSI Z60.1 and tops are protected from damage.
I. Protect sod from drying out.
1.8 STORAGE AND HANDLING
A. Store seeds, soil amendments, fertilizers, and packaged materials in dry locations away from contaminants.
B. Keep sod moist and protect from exposure to wind and direct sunlight.
C. Store plants not installed on day of arrival at project site as follows:
1. Shade and protect plants from wind when stored outside.
2. Heel in bare root plants.
3. Protect plants by covering roots with moist wood chips, shredded bark, peat moss, or similar mulching material.
4. Keep plants moist including those in containers, by watering with fine mist spray until planted.
1.9 FIELD CONDITIONS
A. Seasons and Conditions: unless more strictly noted herein, install products during their seasonally appropriate times. Note specific earliest date below for turfgrass.
B. Perform turfgrass installation operations within following dates: Do not install turfgrass during the summer season until September 7th or later.
C. Restrictions: Do not plant when ground is frozen, snow covered, saturated or in otherwise unsuitable condition for planting. Special conditions may exist that warrant variance in specified planting dates or conditions. Submit written request for approval to COR stating special conditions and proposal variance.
1.10 WARRANTY
A. Construction Warranty: FAR clause 52.246-21, "Warranty of
Construction."
32 90 00 - 8
B. Comply with "Warranty" requirements in including the following supplements:
1. One Year Plant and Turfgrass Warranty: Warranty begins when
Government accepts plants and turfgrass but not before end of
Landscape Plant and Turfgrass Establishment Period.
2. Replace any dead plant material and any areas void of turfgrass immediately during warranty period and during an active growing season. One year warranty for replaced plants and turfgrass begins on day replacement work is completed and accepted.
3. Replacement of relocated plants, not furnished, is not required unless they die from improper handling and care. Loss due to improper handling, care, or negligence requires replacement in kind and size.
4. Government will inspect replacement plants and turfgrass at end of
Warranty period. Replace any dead, missing, or defective plant material and turfgrass immediately and during growing season.
Warranty ends on date of this inspection…