36C78618Q0255-003.docx

DOCX document 23 KB Posted

Attached to
NRM CONTINENTAL DISTRICT. Project 886-18-201: Fort Bliss
Solicitation number
36C78618Q0255
Issued by

About this file

36C78618Q0255 096513ResilientBase.docx

View the file

Other files

File Type Posted
36C78618Q0255-00002000.docx DOCX document
36C78618Q0255-00002001.docx DOCX document
36C78618Q0255-00002003.docx DOCX document
36C78618Q0255-00002002.docx DOCX document
36C78618Q0255-00002004.pdf PDF
36C78618Q0255-00001000.docx DOCX document
36C78618Q0255-001.docx DOCX document
36C78618Q0255-004.docx DOCX document
36C78618Q0255-000.docx DOCX document
36C78618Q0255-002.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

06-01-14

SECTION 09 65 13

RESILIENT BASE AND ACCESSORIES

PART 1 - GENERAL

1.1 DESCRIPTION

A. This section specifies the installation of resilient base and resilient stair treads with sheet rubber flooring on landings.

1.2 SUBMITTALS

A.Manufacturer's Literature and Data:
1.Base and stair material manufacturer's recommendations for adhesives.
2.Application and installation instructions.
B.Samples:
1.Base: 150 mm (6 inches) long, each type and color.

1.3 Delivery

A.Deliver materials to the site in original sealed packages or containers, clearly marked with the manufacturer's name or brand, type and color, production run number and date of manufacture.
B.Materials from containers which have been distorted, damaged or opened prior to installation will be rejected.

1.4 STORAGE

A. Follow manufacturer’s instruction for storage and protection from damage by handling and construction operations before, during, and after installation.

1.5 APPLICABLE PUBLICATIONS

A.Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by the basic designation only. Comply with applicable provisions and recommendations of the following, except as
B.American Society for Testing and Materials (ASTM):
F1861-08(2012)e1Resilient Wall Base

PART 2 - PRODUCTS

2.1 GENERAL

A. Use only products by the same manufacturer and from the same production run.

2.2 RESILIENT BASE

A.ASTM F1861, 3 mm (1/8 inch) thick, 100 mm (4 inches) high, Type TP (Thermoplastic Rubber).
B.Where carpet occurs, use Style A-straight at carpet locations; Style Bcove other locations.

2.3 ADHESIVES

A.Use products recommended by the material manufacturer for the conditions of use.
B.Provide low VOC products that comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

PART 3 - EXECUTION

3.1 PROJECT CONDITIONS

A.Maintain temperature of materials above 21o C (70F), for 48 hours before installation.
B.Maintain temperature of rooms where work occurs, between 21o C and 27o C (70oF and 80oF) for at least 48 hours, before, during, and after installation.
C.Do not install materials until building is permanently enclosed and wet construction is complete, dry, and cured.

3.2 INSTALLATION REQUIREMENTS

A.The respective manufacturer's instructions for application and installation will be considered for use when approved by the COR.
B.Submit proposed installation deviation from this specification to the COR indicating the differences in the method of installation.
C.The COR reserves the right to have test portions of material installation removed to check for non-uniform adhesion and spotty adhesive coverage.
1.Do not use solvents to remove adhesives.
2.Prepare substrate as specified.

3.3 BASE INSTALLATION

A.Location:
1.Unless otherwise specified or shown, where base is scheduled, install base over toe space of base of casework, lockers, and where other equipment occurs.
2.Extend base scheduled for room into adjacent closet, alcoves, and around columns.
B.Application:
1.Apply adhesive uniformly with no bare spots.
2.Set base with joints aligned and butted to touch for entire height.
3.Before starting installation, layout base material to provide the minimum number of joints with no strip less than 600 mm (24 inches) length.
a.Short pieces to save material will not be permitted.
b.Locate joints as remote from corners as the material lengths or the wall configuration will permit.
C.Form corners and end stops as follows:
1.Score back of outside corner.
2.Score face of inside corner and notch cove.
D.Roll base for complete adhesion.

3.4 CLEANING AND PROTECTION

A.Clean all exposed surfaces of base and adjoining areas of adhesive spatter before it sets.
B.Keep traffic off resilient material for at least 72 hours after installation.
C.Clean and polish materials in the following order:
1.After two weeks, scrub resilient base, sheet rubber and treads materials with a minimum amount of water and a mild detergent. Leave surfaces clean and free of detergent residue. Polish resilient base to a gloss finish.
2.Do not polish tread and sheet rubber materials.
D.When construction traffic is anticipated, cover tread materials with reinforced kraft paper and plywood or hardboard properly secured and maintained until removal is directed by the RE/COR.
E.Where protective materials are removed and immediately prior to acceptance, replace damaged materials and re-clean resilient materials. Damaged materials are defined as having cuts, gouges, scrapes or tears and not fully adhered.

- - - E N D - - -

RESILIENT BASE AND ACCESSORIES

09 65 13 - 1

File details come from the government source that posted it.