Sources Sought Attachment 2 - DRAFT ESPC IDIQ SOW.docx

DOCX document 73 KB Posted

Attached to
Z2DZ--VA ESPC IDIQ
Solicitation number
36C77627Q0067
Issued by

About this file

This is a Draft Statement of Work (SOW) for an Energy Savings Performance Contract (ESPC) Indefinite Delivery/Indefinite Quantity (IDIQ) contract with the Department of Veterans Affairs. The contract will provide energy savings performance contract conservation and renewable energy services for VA facilities, with a base ordering period of 60 months and one optional 60-month extension period for a total contract value not to exceed $1.5 billion ($750 million base and $750 million option). The minimum guarantee order per IDIQ contract is $2,000, subject to market research. Individual projects will be defined through Task Orders (TOs) issued under this IDIQ contract, with specific ECM (Energy Conservation Measure) descriptions, scopes, and financial terms provided within each TO.

The contractor must provide all labor, materials, equipment, and services necessary to reduce energy and water consumption at VA facilities, with energy savings guaranteed and payment based on verified savings through Measurement and Verification (M&V). Key contractor responsibilities include performing a Preliminary Assessment (PA) and Investment Grade Audit (IGA) at the contractor's sole risk and expense, designing and installing ECMs compliant with VA design standards and codes, commissioning installed equipment, providing 30-day Proof of Performance where required, and conducting annual M&V to verify guaranteed savings. The contractor must also provide operations and maintenance manuals, training for VA personnel, preventive maintenance procedures, emergency repair response (non-emergency within four business hours; emergency within two hours), and latent-defect remediation. Payment consists of annual debt service payments in advance and performance-period service payments in arrears, with payment capped at guaranteed annual savings and shortfalls recoverable through credits or payment adjustments. The contract prohibits ECMs that would increase water consumption, jeopardize medical facilities, violate building codes, or exceed facility-specific capacity limits, and requires compliance with federal environmental laws (NEPA, NHPA), VA technical standards, and applicable industry codes (NEC, IBC, ASHRAE, NFPA).

View the file

Other files

File Type Posted
Sources Sought Attachment 1 - Capabilities Questionnaire.docx DOCX document
36C77627Q0067.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS

DRAFT — FOR INDUSTRY COMMENT ONLY — SUBJECT TO CHANGE. Attachments referenced in this draft (J-series) will be provided with the solicitation.

B.1 ITEMS BEING ACQUIRED/TOTAL PRICE

The contractor shall provide energy savings performance contract (ESPC) conservation and renewable energy services for Department of Veterans Affairs (VA) facilities. The contractor shall furnish all personnel, facilities, equipment, materials, supplies, and services (except as may be expressly set forth in this indefinite delivery/indefinite quantity (IDIQ) contract or any task order (TO) against this IDIQ contract as furnished by the Government) and otherwise do all things necessary for, or incident to, Energy Savings Performance Contract (ESPC) projects as described in Sections C through H. Specific descriptions of individual projects will be provided by VA through Task Orders (TOs) awarded under this IDIQ contract.

CLIN Description Performance Period Maximum Value

0001ESPC IDIQSixty (60) Months$750 Million*
Base Ordering Period
0002ESPC IDIQSixty (60) Months$750 Million*
Option 1 Ordering Period

* NOTE: Each ordering-period maximum is shared by all IDIQ contracts awarded under this solicitation. The aggregate maximum for the base and option ordering periods combined is $1.5 billion.

B.2 ORDER LIMITATIONS / CONTRACT CEILING

This IDIQ contract has a base ordering period of 60 months with one sixty (60) month option period, for a total ordering period of 120 months, if the option is exercised. There is no guarantee that the option will be exercised on any or all of the awarded contracts.

THE TOTAL MAXIMUM CONTRACT VALUE, defined as the sum of contractor payment streams associated with all task orders issued under all IDIQ contracts awarded under this solicitation, shall not exceed $1,500,000,000.00 (one billion five hundred million dollars): $750,000,000.00 for the base ordering period and $750,000,000.00 for the option ordering period, if exercised. The full value of each task order (the sum of its contractor payment streams over the task order term) counts against the maximum for the ordering period in which the task order is issued.

THE MINIMUM GUARANTEE ORDER(S) VALUE for each IDIQ contract awarded is [$2,000.00 – subject to market research], which VA will obligate at contract award. VA has no obligation to issue orders beyond the minimum guarantee.

B.3 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE

If this acquisition is set aside under VAAR Subpart 819.70, the resulting contract will include VAAR 852.219-73, VA Notice of Total Set-Aside for Certified Service-Disabled Veteran-Owned Small Businesses (or the corresponding VOSB set-aside clause), and VAAR 852.219-75, VA Notice of Limitations on Subcontracting—Certificate of Compliance for Services and Construction. The contractor is advised in performing contract administration functions, the CO may use the services of a support contractor(s) retained by the U.S. Department of Veterans Affairs (“VA” or “Government”) to assist in assessing the contractor's compliance with the limitations on subcontracting or percentage of work performance requirements specified in the clause. To that end, the support contractor(s) may require access to contractor's offices where the contractor's business records or other proprietary data are retained and to review such business records regarding the contractor's compliance with this requirement. All support contractors conducting this review on behalf of VA will be required to sign an “Information Protection and Non-Disclosure and Disclosure of Conflicts of Interest Agreement” to ensure the contractor's business records or other proprietary data reviewed or obtained in the course of assisting the CO in assessing the contractor for compliance are protected and to ensure information or data is not improperly disclosed or other impropriety occurs. Furthermore, if VA determines any services the support contractor(s) will perform in assessing compliance are advisory and assistance services as defined in FAR 2.101, Definitions, the support contractor(s) must also enter into an agreement with the contractor to protect proprietary information as required by FAR 9.505-4, obtaining access to proprietary information, paragraph (b). The contractor is required to cooperate fully and make available any records as may be required to enable the VA CO to assess the contractor's compliance with the limitations on subcontracting or percentage of work performance requirement.

B.4 REQUIRED SERVICES

Project development is at the ESCO’s risk. The Preliminary Assessment (PA) and Investment Grade Audit (IGA) shall be performed at the ESCO’s sole risk and expense. VA has no obligation to reimburse any project development cost unless a TO is awarded following VA’s acceptance of the IGA, in which case allowable project development costs shall be included in the TO price. Phasing under this Section B.4 occurs only by modification to an awarded TO, and each phase financed through performance period payments shall independently satisfy the guaranteed-savings requirements of Section C.1.3, and VA-funded work is governed by Section C.1.3(f).

The Government requires ESPC conservation services for VA facilities and seeks to obtain these services through using this IDIQ contract. The Government reserves the right to implement an awarded TO in phases (Phase 1 (TO-1), Phase 2 (Mod -1), Phase 3 (Mod -2) etc., based on information obtained on the Energy Conservation Measures (“ECM”) developed or identified during the Preliminary Assessment (PA) and/or Investment Grade Audit (IGA) or various financial considerations including availability in out years of appropriated funds. This phasing process may include the addition/deletion of ECM(s) or Site(s) in order to obtain a comprehensive package to meet the energy requirements of VA and is in the best interest of the Government. This phasing process also allows for VA to directly fund ECMs identified with the Notice of Opportunity and/or the PA or IGA following award of an initial project which may not have been financially feasible at the time of TO award. The Energy Services Company (“ESCO”) shall provide, all labor, material, permits, equipment, transportation and supervision necessary to reduce energy and water consumption, provide energy cost savings and related operation and maintenance cost savings. See Attachment J-16 for the IGA Checklist.

Government reserves the right to use any combination of appropriated funds and private financing in Federal ESPCs as provided for in 42 U.S.C. § 8287 and 10 CFR 436. Contracted services may also include operations and maintenance services during a specific term as required in Section C, and/or as proposed by the ESCO and accepted by the Government. Energy savings are guaranteed; therefore, the ESCO shall only receive payment based on the guaranteed annual cost savings through Measurement and Verification (“M&V”) of the installed ECMs. Payment timing and adjustment are governed by Section C.1.8. Site specific M&V plans shall contain procedures and guidelines for quantifying the savings resulting from energy efficiency equipment and water conservation measures.

B.5 CONTRACT ON-RAMPS

DRAFT – FOR MARKET RESEARCH AND INDUSTRY COMMENTS ONLY

This solicitation may remain open for on-ramp proposals during the ordering period stated in Section B.2; however, following closure of the initial round of submissions, proposals will be accepted only by the due dates VA announces on SAM.gov. The Government will evaluate the market to determine if it is in the Government’s interest to award ESPC IDIQ contracts to additional qualified firms by employing “on-ramp” procedures following the initial selection and award. The Government reserves the right, based upon the evaluation of the market, to accept new proposals with the intention of adding awarded contracts to this IDIQ contract to provide the Government with better buying power. These proposals will be subject to the same proposal instructions and evaluation procedures as contained in the original solicitation. Previously awarded Task Orders will be unaffected by on ramp actions taken to refresh the multiple award IDIQ contract pool. On-ramping will be accomplished by either issuing an amendment to the IDIQ solicitation on SAM.gov or by a notice on SAM.gov. Any offeror awarded an IDIQ during an on-ramp will be subject to the established ordering period at initial award and as identified in Section B.2 at the time of initial IDIQ award.

Page 1 of Page 1 of

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1. GENERAL REQUIREMENTS / PROJECT SCOPE

C.1.1 This contract is intended to acquire energy and water conservation services, improve energy- and water-related infrastructure, reduce energy and water consumption and/or associated utility costs, and may reduce energy and water-related operations and maintenance costs, as specified in each TO issued against this IDIQ contract. The contractor shall be responsible for providing all labor, material, and capital to install energy and water conservation projects and/or renewable energy projects and provide operations and maintenance (O&M) as specified in each TO. Payments under each TO (hereafter referred to as the TO project) shall be made only from funds appropriated or otherwise made available to VA for energy, water, and related operation and maintenance expenses, and shall not exceed the savings guaranteed under Section C.1.3, except for VA-funded work added by modification as provided in Section C.1.3(f). The TO project cost savings must be verified and documented annually through measurement and verification (M&V). (Attachment J-10, Annual Measurement and Verification Report Outline). The baseline used for the validation will be from the ESCO’s Final Proposal that will have been validated by VA under each TO.

C.1.2 The services under the IDIQ and any TOs issued against it shall be provided in accordance with not only the Statement of Work provided in Section C, Description/Specifications/ Statement of Work, of the contract, but also in accordance with all the contract attachments. Unless otherwise stated, all provisions that follow throughout the remaining sections of this IDIQ contract may be revised within the overall scope of the contract, as necessary (based on the needs of VA), in a Notice of Opportunity (NOO) or the resulting TO. The ESCO shall submit each deliverable listed in Attachment J-4 on the schedule stated there, unless the NOO or TO states otherwise.

C.1.3 Guaranteed Savings.

(a) The ESCO shall guarantee annual energy, water, and related cost savings for each TO.

(b) In no performance year shall VA’s performance period payments to the ESCO exceed the ESCO’s guaranteed annual cost savings for that year, and in no performance year shall the aggregate of VA’s payments to the ESCO and to utilities exceed the amount VA would have paid for utilities in the absence of the TO, as determined under the accepted M&V plan (42 U.S.C. § 8287(a)(2)(B)–(C); 10 CFR Part 436, Subpart B).

(c) If verified savings in any performance year are less than the guaranteed savings, the ESCO shall reimburse the shortfall as provided in Section C.1.8(f) or, where that paragraph does not apply, in accordance with CO direction. VA may offset the shortfall against subsequent payments.

(d) Verified savings in excess of the guarantee accrue to VA unless the TO provides otherwise.

(e) Savings shall not be speculative; any savings category that cannot be measured or stipulated under the DOE FEMP M&V Guidelines shall not be included in the guarantee. See DOE’s Practical Guide to Savings and Payments in FEMP ESPC Task Orders.

(f) VA-funded work. Paragraphs (b) and (c) apply to payments financed from guaranteed savings. VA-funded work added by modification under Section B.4 shall be priced and paid as stated in the modification, is not subject to the payment limit in paragraph (b) and does not count toward the guaranteed savings of any phase unless the modification states otherwise.

C.1.4 Definitions. For purposes of this IDIQ contract and its TOs: “Contractor” and “ESCO” (Energy Service Company) are used interchangeably; “TO” means a task order issued under this IDIQ contract, and references to “the contract” in Sections C.3 through C.22 mean the applicable TO unless the context requires otherwise; “ECM” means an energy conservation measure and includes water conservation measures (“WCMs”) and on-site generation measures; “PA” means Preliminary Assessment; “IGA” means Investment Grade Audit; “NOO” means Notice of Opportunity; “implementation period” means the period from the start of construction or installation through Government acceptance of the project (see Section C.5.5); “performance period” means the period from Government acceptance through the end of the TO term; and “acceptance” means VA’s written acceptance of the project or an ECM under Section C.5.5.

C.1.5 Project Development – Preliminary Assessment (PA). The ESCO shall perform the PA at its sole risk and expense in accordance with Section B.4. The VA may, at its sole discretion, elect to skip the PA and move directly to the IGA – VA may choose to do that for limited scope TOs, particularly time sensitive TOs, or other cases where the VA determines that completion of the PA is unnecessary. If VA elects to skip the PA, the ESCO shall submit the items required by paragraphs (a) through (c) of this section and by Section C.4.8.A with the IGA. When completed, the PA shall, at a minimum, include the following:

(a) Validation of VA’s ECM wish list. The ESCO shall validate VA’s ECM wish list (the list of potential ECMs that VA provides in the NOO, developed from the site development package) and explore potential solutions to address the deficiencies and energy savings opportunities identified. ESCO may also conduct a fence-to-fence assessment and identify other potential ECMs across the facility(ies) and sites identified in the NOO for VA’s consideration, with preliminary estimates of annual energy, water, and related cost savings, implementation cost, and the proposed M&V approach required by Section C.4.8.A.

(b) Facility Condition Assessment (FCA) and Non-Recurring Maintenance (NRM) review. A review of the facility’s current FCA deficiency list and the facility’s planned NRM projects for the next [three (3) to five (5)] fiscal years, as furnished by VA under Section C.1.7, to identify each item that (i) is a potential ECM; (ii) would affect the scope, baseline, savings, or M&V of a potential ECM; or (iii) may be suitable for later phasing under Section B.4.

(c) Screening summary. For each item identified under paragraph (b), a screening summary stating the item; the related ECM or interaction; a preliminary recommendation (include in the initial TO, phase later, VA-funded outside the TO, or exclude) with the basis for that recommendation; and any dependency on funding source or timing.

(d) No entitlement. Inclusion of an item in the screening summary does not obligate VA to fund, procure, or include the item in any TO. VA reserves the right to determine the funding source for any item, to fund, procure, or compete any item separately, and to determine whether any later addition to a TO is within the scope of the TO and this IDIQ contract and is priced fairly and reasonably.

(e) Submission and review. The ESCO shall submit the PA in accordance with the approved VA PA schedule and the information in Section C.1.7. VA will review the PA and notify the ESCO in writing whether VA will request an IGA.

C.1.6 Project Development – Investment Grade Audit (IGA). The ESCO shall perform the IGA at its sole risk and expense, following VA’s written request to proceed, in accordance with Section B.4. The IGA shall, at a minimum:

(a) satisfy each item of the IGA Checklist Attachment J-16;

(b) verify the FCA and NRM data on which the ESCO relied in the PA, update the screening summary required by Section C.1.5(c), and include a phasing plan identifying each NRM-eligible or VA-funded item, its estimated cost, and the earliest fiscal year in which VA funding would be required;

(c) identify each planned NRM project or FCA deficiency that interacts with the proposed baseline, ECMs, or savings calculations, and state how the baseline and M&V plan will be adjusted if the item is completed during the performance period;

(d) establish the baseline, ECM design basis, savings calculations, and site-specific M&V plan in accordance with Sections C.1.3 and C.4 and Attachment J-8, such that each financed phase independently satisfies Section C.1.3;

(e) identify project development costs separately. Those costs are recoverable only as provided in Section B.4 and shall not be recovered through the minimum guarantee under Section B.2; and

(f) include a Proof of Performance (POP) Applicability Table identifying, for each ECM, whether POP is required and the basis. The Commissioning Plan shall update the table (see Section C.5.5.3).

C.1.7 Government-Furnished Project Development Information. VA will furnish the FCA deficiency list and the planned NRM project list for the facility/facilities identified in the NOO within 14 days after the NOO. VA does not warrant the accuracy or completeness of this information, and the ESCO shall verify any information on which it relies during the IGA. The ESCO shall protect this information in accordance with Sections C.20.6 and C.22 and shall not release it to any third party without the written approval of the Contracting Officer.

C.1.8 Payment Timing (Default). Unless the TO provides otherwise, VA payments under the TO consist of the following components, as set out in the TO payment schedule (Attachment J-6):

(a) Commencement. VA performance-period payments begin only upon acceptance under Section C.5.5 and as provided in Section C.5.5.9. Implementation-period payments, if any, are governed by Section C.5.5.7.

(b) Debt service component – annual in advance, unless otherwise specified in the task order. After project acceptance, VA shall pay the debt service component annually in advance, at the beginning of each performance year, on the payment date stated in the TO payment schedule (Attachment J-6), provided that (i) acceptance has occurred as provided in Section C.5.5.6; (ii) a proper invoice has been submitted through the VA-designated electronic invoicing system (currently Tungsten) not less than 30 calendar days before VA’s payment date; and (iii) funds are available for payment in the fiscal year of payment. The first debt service payment is due 30 days after the later of acceptance and VA’s receipt of a proper invoice.

(c) Services component – in arrears. VA shall pay the performance period services component (O&M, M&V, repair and replacement, and other ESCO services, as applicable to the TO) in arrears, after the services have been performed. Payment for M&V and for any amount that depends on verified savings requires VA’s written acceptance of the annual M&V report (Section C.4.8.D). Payment shall be made in accordance with the Prompt Payment Act (FAR Subpart 32.9; 5 CFR Part 1315).

(d) Draft invoice. The ESCO shall submit a draft invoice by email to the CO and COR not less than sixty (60) calendar days before VA’s payment date. VA will review the draft within [10] business days. VA’s review of a draft invoice does not constitute acceptance of any matter under Section C.5.5.

(e) Limits. Payments shall follow the TO payment schedule and shall not exceed the limits in Section C.1.3(b). Payment in advance of the financier’s due date does not change the guaranteed-savings requirements of Section C.1.3.

(f) Shortfall adjustment. If the accepted annual M&V report shows verified savings below the guaranteed annual cost savings for the TO, and the CO determines the shortfall is not attributable to VA under Attachment J-7 or Section C.11, VA will, after consulting the ESCO, recover the shortfall as follows: (1) VA will apply a credit for the shortfall against the next debt service invoice, and against later invoices until the shortfall is recovered, and the ESCO shall show the credit on its draft invoice under paragraph (d); (2) if the shortfall exceeds the next payment or recurs in consecutive years, the CO may instead adjust the payment schedule (Attachment J-6) by modification, and shall adjust it again when performance is restored; and (3) if no later payment remains, the ESCO shall pay the shortfall as the CO directs under Section C.1.3(c). Recovery under this paragraph does not relieve the ESCO of its duty to restore ECM performance at its own cost and does not limit VA’s other rights. The guarantee applies to the TO as a whole. Any advance debt service payment for a performance year in which verified savings fall below the guaranteed savings is recoverable under this paragraph.

(g) ESCO responsibility. The ESCO is solely responsible for scheduling financier payments in light of the acceptance procedures in Section C.5.5. The ESCO is responsible for submitting draft invoices for approval in accordance with paragraph (d) and uploading approved invoices into Tungsten timely. The ESCO is also responsible for ensuring proper access/submission information such as vendor identification numbers in VA’s payment system. VA is not liable for late fees, interest, or penalties arising from a failure to meet the conditions of this Section C.1.8.

C.1.9 Project Schedule. (a) Baseline. With the final IGA/proposal, the ESCO shall submit a detailed, logically linked critical path method (CPM) schedule showing engineering and design; VA design reviews (Section C.5.1.D); permits and National Environmental Policy Act and National Historic Preservation Act reviews (Section C.5.6); equipment procurement and lead times; installation by facility and ECM; planned service interruptions (Section C.5.7) and the periods each facility is available for construction; commissioning and proof of performance; the post-installation report; and project acceptance. The schedule the CO accepts at TO award is the baseline schedule and is incorporated into the TO. (b) Updates. The ESCO shall submit schedule updates bi-weekly (Attachment J-4) and shall review them with VA at monthly schedule reviews. (c) Changes. The ESCO will be held to the baseline schedule. Only the CO may approve a change to the baseline schedule, in writing, at a monthly schedule review or by TO modification. VA review of a schedule update is not approval of a change. Delay is governed by Sections C.5.5.9 and C.5.5.10. (d) Consistency. The installation schedule (Section C.5.1.C), the monthly work schedule (Section C.21), and look-ahead schedules shall derive from the baseline schedule. Where they conflict, the baseline schedule as approved by the CO controls.

C.2 ENERGY CONSERVATION MEASURE (ECM) TECHNOLOGY CATEGORIES

C.2.1 ECM TCs – This IDIQ contract and its TOs require the contractor to possess the capability to implement ECMs that reduce energy and water consumption or costs, improve energy- and water-related infrastructure, increase renewable energy use, and may reduce energy and water-related O&M costs. ECMs include measures to increase efficiency of energy-consuming systems and to reduce water consumption. ECMs also include measures that improve the efficiency of energy production systems that generate electrical and/or thermal energy. A list of ECM TCs that shall be considered during the development of each project is provided in Attachment J-3.

C.2.2 Restrictions on ECMs ECMs installed by the contractor shall not do the following:

1. Jeopardize the operation or environmental conditions of existing systems or areas such as medical treatment facilities, and dedicated computers or computer rooms;

2. Increase water consumption; e.g., once-through freshwater cooling systems (note: evaporative cooling technologies may be considered where environmentally appropriate);

3. Result in cogeneration or an electrical generating project that produces electrical power exceeding that required by the Federal site covered by the TO;

4. Result in an adverse effect upon the quality of the human environment (e.g., requires the preparation of an Environmental Impact Statement) or violates any Federal, State, or local environmental protection regulations;

5. Degrade performance or reliability of existing Government equipment;

6. Reduce extra capacity that was intentionally included for future growth, mobilization needs, safety, or emergency back-up;

7. Violate current versions of national code (e.g., National Electrical Code, International Building Code), state or local building codes, etc.; or

8. Create unsafe conditions or otherwise adversely impact Government facilities, operations, and/or personnel.

C.2.3 VA is interested in considering two potential options for generating assets (e.g. photovoltaic systems, cogeneration systems, etc.):

1. Conventional ECM. A generating asset that will be Government-owned upon commissioning and acceptance.

2. Energy Sales Agreement (ESA). A generating asset that will not be Government-owned until the end of the contract, with payment based on electricity generation (cents / kWh). The ESCO is solely responsible for determining the availability, value, and eligibility requirements of any Federal, State, or local tax incentive as of the date of TO award, including any placed-in-service or beginning-of-construction deadlines and foreign-entity restrictions under 26 U.S.C. §§ 45Y and 48E, as amended by Public Law 119-21. VA makes no representation regarding tax-incentive eligibility. Any TO that includes an ESA shall be structured consistent with IRS Revenue Procedure 2017-19 (Internal Revenue Bulletin 2017-7) and 42 U.S.C. § 8287. Attachment J-23 (ESA Statement of Work template) shall serve as a guide for the structure and terms and conditions of any TO that includes an ESA.

C.3 FACILITY PERFORMANCE REQUIREMENTS OF ECMs Installed ECMs shall comply with the standards of service required for facilities included in the TO. The standards of service may include acceptable temperature and humidity ranges, allowable setbacks, noise criteria, air quality parameters, lighting levels, and other related factors, as agreed to between VA and the contractor. At a minimum, where automated controls of lighting or environmental conditions are to be installed, VA must have the ability to, or direct the contractor to, respond within a specified time to temporarily override the heating, ventilating and air-conditioning (“HVAC”) and lighting systems.

C.3.1 ESCO installed ECMs shall meet the RFP performance requirements as specified below. VA master specifications and design guides take precedence over the RFP performance requirements, if there is a conflict. The ESCO proposal shall document any conflict(s) between requirements. Follow the guidance provided in VA’s Technical Information Library at http://www.cfm.va.gov/til. Guidance includes but is not limited to design manuals and guides (including the VA Sustainable Design and Energy Reduction Manual), master specifications, and technical summaries.

C.3.2 Environmental & Lighting Conditions. Modifications to building lighting systems and environmental control systems shall not be permitted to exceed the ranges for Standards of Service specified in Paragraph C.3.3. Where automated controls of lighting or environmental conditions are to be installed, occupants must have the ability to override the system only in areas VA designates in the TO. Occupant override shall not be provided in spaces with required pressure relationships, air-change rates, or temperature and humidity limits (including patientcare, isolation, operating, procedure, pharmacy compounding, and sterile processing spaces) under ASHRAE 170, NFPA 99, and VA design standards.

C.3.3 Standards of Service. Installed ECMs shall comply with the Standards of Service required for facilities as contained in VA’s Technical Information Library http://www.cfm.va.gov/til. The Standards of Service include acceptable temperature and humidity ranges, air quality parameters, lighting levels, and other related factors. Guidance includes but is not limited to design manuals and guides (including the VA Sustainable Design and Energy Reduction Manual), master specifications, and technical summaries.

C.3.4 Lighting Systems. Except where special circumstances exist, illumination levels shall be maintained as near as practical to the Illuminating Engineering Society of North America (“IES”) recommended illumination level. IES values that vary from VA design manual values are to be identified for VA review and decision. Lighting system ECMs should examine demand response capability (auto-dimming to reduce peak demand when required) and daylight harvesting or daylight response. ESCOs must comply with VA’s lighting ECM guidance (see Attachment J-1).

C.4 MEASUREMENT AND VERIFICATION (M&V) OF ECM PERFORMANCE

C.4.1 VA M&V guidelines specifying VA M&V requirements and procedures for annual reporting are provided in Attachment J-10. The reporting guidelines apply to various factors such as type of ECMs, projected value of energy savings, certainty/uncertainty of savings being achieved, and the intended risk allocation between VA and the ESCO.

C.4.2 The contract shall include a site-specific M&V plan that specifies the M&V requirements and procedures that shall apply to the project based on various factors, such as type of ECMs, projected value of energy savings, certainty/uncertainty of savings being achieved, and the intended risk allocation between VA and the contractor.

C.4.3 The M&V plan is the primary vehicle that VA uses to first document and then to periodically evaluate the performance expectations of the project. This document shall be thoroughly understood by the contractor and VA. It shall, in a clearly understandable format, state where and how energy, water and related cost savings are going to occur and how they are to be calculated and verified. If the scope of work does not include the entirety of a site, or all the systems or significant portions within a building, then that exclusion shall be stated clearly so that VA and the contractor are aware of what the contract covers and what it does not. Each building and/or space within a building that will be affected shall be identified, and buildings or portions of buildings that will not be affected shall be identified. The ECMs that generate savings shall be identified, as well as the building systems that they affect. If there are significant energy- or water-using building systems or other energy or water uses within the buildings, which will not be affected by the contract, they shall be identified so that there is clear understanding of the extent to which total energy, water and related costs at the site will be affected. To the extent this information is provided in the IGA, it will be repeated in the M&V plan.

C.4.4 The description of facilities and systems affected by the ECMs serves as the context for determining risks associated with the performance of the ECMs and the likelihood of success in achieving projected savings. The first step in developing an M&V plan will be accomplished through the completion of an ESPC Risk, Responsibility and Performance Matrix (Attachment J-7). The matrix indicates the responsibility and performance of actions agreed to by the contractor and VA.

C.4.5 The M&V plan for each TO shall specify the M&V options and methods that will be used for each ECM included in the contract. M&V options and methods proposed for each ECM shall comply with the Department of Energy (DOE) Federal Energy Management Program’s (FEMP) M&V Guidelines: Measurement and Verification for Performance-Based Contracts, Version 5.0, or the most current version in effect on the date of TO award (“DOE FEMP M&V Guidelines”), and the “International Performance Measurement and Verification Protocol (“IPMVP”).” If there is a discrepancy between these two documents, the DOE FEMP M&V Guideline takes precedence. The DOE FEMP M&V Guidelines includes a variety of guidelines and tools that will help in the development of a technically rigorous M&V plan, including both optional M&V methods for differing ECMs and tools for assessing the cost implications of these options. See https://evo-world.org/en/products-services-mainmenu-en/protocols/ipmvp for the IPMVP and https://www.energy.gov/cmei/femp/articles/mv-guidelines-measurement-and-verification-performance-based-contracts-version-0 for the DOE FEMP M&V Guidelines.

C.4.6 Contractor shall identify as part of each ECM, how weather conditions are expected to impact the actual energy savings realized. Calculation methods should be pre-identified to compensate for unusual weather conditions. During the first year of operation, contractor should build some weather factored trend data to validate their weather dependency calculations.

C.4.7 M&V Activities - The contractor shall perform the following required M&V activities:

A. Define a site-specific M&V plan for the particular project being installed, once the project has been fully defined and the IGA is completed. This shall occur before the TO is awarded, and the M&V plan will be incorporated into the TO. Draft M&V plans shall be provided per the IGA Checklist (Attachment J-16) during each IGA stage to ensure agreement between all parties about the particulars of the plan.

B. Define a pre-installation baseline including: (a) equipment/systems, (b) baseline energy use, (c) system performance factors (e.g., lighting levels, temperature setpoints, time clock settings, etc.), and/or (d) actions to determine baseline energy use, which may include site surveys, short-term or long-term metering, analysis of billing data, and/or engineering calculations. The pre-installation baseline should also identify factors beyond the contractor’s control that influence post-installation energy (e.g., building occupancy, weather, plug load creep, etc.). Where factors beyond the contractor’s control potentially exist, VA and contractor will agree on what measures should be taken to adjust the baseline, modify savings calculations or otherwise account for such factors. Where feasible, adjustments to the calculation methodology for savings are preferred over changes to the baseline. Such adjustments make it easier to present the actual savings. The ESPC Risk, Responsibility and Performance Matrix (Attachment J-7) will guide the identification of factors on which such agreements may need to be reached. The definition of all elements of the pre-installation baseline will be agreed upon before award. Please see Attachment J-5, “VA Project Checklist,” for more clarity and understanding of general requirements.

C. Define post-installation conditions including: (a) equipment/systems, (b) post-installation energy use, and/or (c) actions to determine post-installation energy use, which may include site surveys, short-term or long-term metering, analysis of billing data, and/or engineering calculations. The contractor shall verify and document any changes or activities that impact energy use throughout the life of the contract. These include changes in occupancy schedules, addition or removal of equipment, implementation of computer power management, and other changes.

D. Conduct annual M&V activities to verify operation of the installed equipment/systems. Compare verified actual savings with the guaranteed savings. During the first year, M&V site inspections shall be performed quarterly unless otherwise stated in the TO; savings shall be verified and reported annually.

E. Government Witnessing of M&V. A Contracting Officer’s Representative (“COR”), VA-appointed Energy Manager, or another VA-designated representative shall accompany the ESCO during M&V activities, which will be performed on a quarterly basis during the first year and on an annual basis thereafter, unless otherwise agreed to in the TO.

F. The contractor shall not take credit toward realized savings for O&M cost savings when VA personnel perform the operations and maintenance on that particular ECM. O&M cost savings shall only be credited toward realized savings if the O&M was previously contracted for, and implementing a particular ECM will result in reduced costs paid to a contractor.

G. Building metering shall be installed and utilized to support the M&V where sufficient metering does not already exist, and VA does not have a contract in place for meter installation. All metering shall be compatible with the metering systems installed by VA and be compatible with and able to connect into the existing building energy management system. The data will be used in long term building performance trend analysis, problem identification, etc. Metering shall comply with VA’s advanced utility metering system specification in the VA Technical Information Library https://www.cfm.va.gov/til/ . Where existing VA meters are used to establish the baseline, the ESCO shall verify their calibration during the IGA; the cost is a project development cost recoverable only if a TO is awarded. Connection of any meter or data system to a VA network is subject to Section C.22.

C.4.8 M&V Submittals during Development and Post-Award A. The contractor shall prepare and submit a general M&V approach with its Preliminary Assessment (PA), identifying the M&V options and methods to determine a site-specific pre-installation baseline and post-installation ECM performance for each proposed ECM.

B. The contractor shall prepare and submit a site-specific M&V plan with its final proposal, per the requirements in Section H and Attachment J-8. This site-specific M&V plan shall include a schedule indicating M&V activities and post-award M&V reporting milestones for each ECM. Prior to installation of ECMs, VA must witness measurements and review calculations, records (e.g., utility bills) and other elements of the baseline, to confirm its accuracy and to confirm that methods are consistent with the approved M&V plan, as described in FEMP’s "Guide to Government Witnessing and Review Measurement and Verification Activities" and FEMP’s “Reviewing Post-Installation and Annual Reports for Federal ESPC Projects” at https://energy.gov/eere/femp/downloads/reviewing-post-installation-and-annual-reports-federal-espc-projects.

C. The contractor shall prepare and submit a post-installation report to VA (Attachment J-9), which should verify that installed ECMs will meet the required standards of service and the guaranteed annual energy, water, and related cost savings specified in the awarded contract. Inspections and measurements conducted by the contractor for this post-installation report must be witnessed by VA, in accordance with FEMP’s "Guide to Government Witnessing and Review Measurement and Verification Activities." Documentation of this witnessing shall be attached to the post-installation report. The post-installation report shall be reviewed as recommended in FEMP’s “Reviewing Post-Installation and Annual Reports for Federal ESPC Projects,” and must be accepted in writing, by VA. VA will review and respond within 60 days.

D. The contractor shall prepare and submit an annual M&V report to VA (Attachment J-10), including data and calculations that demonstrate that continued ECM performance achieves the guaranteed annual energy, water, and related cost savings as required by the contract. Additionally, the ESCO shall provide proof and documentation that any post-acceptance services such as O&M or repair and replacement required under the contract were completed during the reporting period by the ESCO. The annual M&V report shall be submitted once per performance year; the TO may require brief quarterly or semi-annual status summaries during the first year. Inspections and measurements conducted by the contractor for this annual M&V report must be witnessed by VA in accordance with FEMP’s "Guide to Government Witnessing and Review Measurement and Verification Activities." The annual M&V report should be reviewed, as recommended in FEMP’s “Reviewing Post-Installation and Annual Reports for Federal ESPC Projects,” and must be accepted, in writing, by a duly authorized representative of VA. Review and acceptance of the annual M&V report, in accordance with FEMP’s "Guide to Government Witnessing and Review Measurement and Verification Activities " constitutes documentation to determine amount of contractor payment. VA will review and respond within 60 calendar days. The TO shall establish the acceptance period for M&V reports and the effect of report acceptance on invoicing (5 CFR 1315.4; FAR Subpart 32.9).

C.5 INSTALLATION REQUIREMENTS FOR ECMs C.5.1 Design and Construction Package A. The contractor shall prepare and submit a design and construction package (“Design and Construction Package”) to the Contracting Officer (“CO”) for review and approval prior to starting ECM installation in accordance with Attachment J-4, Deliverables. The Design and Construction Package shall be certified (stamped) by a professional engineer licensed in any U.S. state or territory to assure compliance with applicable building codes and VA design standards. Site-specific VA requirements of the design and construction package shall be found at the Technical Information Library https://vatilms.va.gov/vatilms/landing-page#. Acceptance of the Design and Construction Package by VA shall not relieve the contractor from responsibility for meeting facility standards of service and guaranteed cost savings. Contractor shall not proceed with construction until formal direction from the CO is obtained after approval of the Design and Construction Package. Approval may be granted for individual ECMs to proceed.

B. The Design and Construction Package due date is included in Attachment J-4, Deliverables. Phased design and construction may be allowed and specified by VA in the contract. Performance and payment bonds, each in a penal sum equal to 100 percent of the TO implementation (construction) price, shall be furnished within [10] calendar days after TO award and before VA issues the notice to proceed with construction (FAR 28.102; FAR 52.228-15). Bonds are not required for performance-period services or for the financed amount.

C. The Design and Construction Package shall include at least the following:

1. Manufacturer's Data - For all ECM equipment to be installed, the contractor shall provide the manufacturer's descriptive literature of equipment including drawings, diagrams, performance and characteristic curves, catalog cuts, installation guidelines, and warranty considerations.

2. Design and Construction Specifications - Unless otherwise specified by VA, the contractor shall identify and reference design and construction specifications applicable to installed ECMs. Modifications or removals of any specs or designs must be highlighted and approved by the VA.

3. Construction Drawings - Construction drawings shall be prepared by the contractor, subcontractor, or any lower-tier subcontractor, showing in detail:

i. The installation (i.e., form, fit, and attachment details) of the interface between ECM equipment and existing Government equipment.

ii. The location of installed equipment on building floor plans.

iii. Certification of ECM compliance with building codes and standards. The ESCO shall provide registered Professional Engineer (“PE”) certification that ECMs comply with all applicable building codes and standards. ECM installation plans submitted to the VA without evidence of the registered PE certification shall be returned for resubmission.

4. Planned Service Interruptions - If any utility services must be discontinued temporarily to perform work, such interruptions shall be described and indicated on the project installation schedule. Required service interruptions shall be scheduled per Section C.5.7 to include: the length of the interruption, interruption time (date, day of week, time of day, etc.), justification, and Government point of contact for coordination and workarounds needed to minimize impact. This information shall be included as part of the Design and Construction Package.

5. Site Plan and Compliance with Federal Site Exterior Architectural Plan - If an ECM involves the installation of facilities or exterior structures, the contractor shall provide a site plan showing its location, or show its location on VA's existing site plan. The contractor shall also provide plan and elevation drawings of the facility or exterior structure showing its size and exterior appearance.

6. Acquisition of Permits - For any ECM installation requiring permits from regulatory agencies, the contractor shall provide its plan and schedule for acquiring such permits in accordance with VA instructions and requirements.

7. Installation Schedules - The installation schedule shall derive from the Project Schedule under Section C.1.9 and shall show the order in which the contractor proposes to perform the work and the dates on which the contractor contemplates starting and completing all major milestones (including acquiring materials, equipment, permits, and inspections). The schedule shall be in the form of a progress chart of suitable scale to indicate the amount of work scheduled for completion by any given date during the installation period.

i. Schedule must identify any work proposed to be performed outside normal hours for VA’s review and approval. Off-hours work must be identified on look-ahead schedules as well, and coordinated with the COR for approval no less than [five (5)] working days before the work starts.

8. Commissioning – See C.5.4 for ECM commissioning related documents.

D. Design documents will require both a preliminary and final review by VA.

Design review submissions shall occur at the 30%, 60%, and 100% (Final) of design completion for all ECMs. The selected ESCO’s design review submissions shall be provided to the COR and to the VA CO. VA will review and provide comments within 30 days of each submission. Comments shall be incorporated into the subsequent version submitted, which must be reviewed and approved prior to moving on to the next phase in the design process. VA reviewer failure to identify an instance of non-compliance with applicable code or VA specifications or requirements during any design stage does not absolve the ESCO of the need to comply with those requirements. Any requested deviations must be called out and explicitly approved, silence does not confer approval.

C.5.2 Design and Construction Standards A. All ECMs, work, equipment and materials required for ECM installation under this IDIQ and its TOs shall comply with the most recent issue of the design and construction standards found at VA’s Technical Information Library https://vatilms.va.gov/vatilms/landing-page#, including but not limited to VA directives effective on the date of TO award. The following list of standards is provided as a guideline for establishing these requirements and should not be considered exhaustive:

· American National Standards Institute (ANSI)

· Code of Federal Regulations (CFR)

· 29 CFR 1910, Occupational Safety and Health Standards

· 10 CFR 433, Energy Efficiency Standards for the Design and Construction of New Federal Commercial and Multi-Family High-Rise Residential Buildings

· 29 CFR 1926, Safety and Health Regulations for Construction

· National Electrical Code (NEC)

· National Electrical Safety Code (NESC)

· National Fire Protection Association (NFPA) Standards including, but not limited to, NFPA 101 - Life Safety Code

· NFPA 99, Health Care Facilities Code

· NFPA 110, Standard for Emergency and Standby Power Systems

· National Electrical Manufacturers Association (NEMA)

· Underwriters Laboratories (UL)

· International Building Code (IBC)

· Uniform Plumbing Code (UPC)

· American Society of Heating, Refrigerating and Air-Conditioning Engineers (ASHRAE)

· ASHRAE 62

· ASHRAE 90.1

· ASHRAE 170, Ventilation of Health Care Facilities

· National Historic Preservation Act, as applicable

· Illuminating Engineering Society of North America (IESNA)

· Air-Conditioning, Heating, and Refrigeration Institute (AHRI)

· Occupational Safety and Health Administration (OSHA) regulations

· Other design standards required by the ordering VA Contracting Officer (CO)

· National Environmental Policy Act (NEPA)

· VA design manuals: https://vatilms.va.gov/vatilms/reports/PG-18-10

· VA Master Construction Specifications: https://vatilms.va.gov/vatilms/reports/PG-18-1

· Facility Guidelines Institute (FGI) Guidelines for Design and Construction of Hospitals and Outpatient Facilities

· VA Physical Security and Resiliency Design Manual

· VA Seismic Design Requirements (H-18-8)

· VA Boiler and Boiler Plant Operations Directive (Attachment J-19) B. No requirement of this contract shall supersede applicable regulations, local codes and/or standards. Any violation of such regulations and standards shall be brought to the attention of the VA CO for clarification or direction prior to proceeding with the work.

C. If conflicts between designated applicable codes and/or standards exist, the VA CO and applicable authority having jurisdiction shall determine the appropriate code to follow.

D. The contractor shall formally submit the conflict of applicable codes to VA within 10 business days of discovering the conflict. The contractor shall include a copy of the Design Manuals, Guides and VA Master Specifications which indicate the conflict, and were in place at the time the final task order is awarded. The submitted documents should be electronic, downloadable format and submitted through the selected construction/project management software (such as Procore) There is a function on the CFM VA-TIL website (see C.5.2.A above) to perform this complete download.

C.5.3 ECM Quality Control Inspection Program The contractor shall be responsible for…