Phasing Plan Narrative Summary

This document is a Phasing Plan Narrative for the EHRM Infrastructure Upgrades project at Martinsburg VA Medical Center, establishing the construction sequencing and coordination requirements for a firm-fixed-price contract (Contract #36C776220169, PO #613C20234, Project #613-22-700) located at 510 Butler Avenue, Martinsburg, West Virginia 25405. The project encompasses fiber optic cabling upgrades across 49 buildings at the VA medical center campus, with an overall construction duration of approximately 700 days. Normal working hours are 7:00 AM to 4:30 PM, Monday through Friday, with outside-hours work requiring 72-hour advance approval from the Contracting Officer's Representative at no additional cost to the Government. All construction sequencing must be coordinated with local VA, OIT, the Registered Communications Distribution Designer (RCDD), and Healthcare Environment and Facilities Programs (HEFP)/Special Engineering Projects (SEP) coordinators to maintain telecommunication service to critical areas and comply with code and life safety measures.

The project phases include four civil work phases (246 days total, January 6, 2027 through December 15, 2027) involving underground duct bank conduits and interbuilding backbone cabling, followed by five interior construction phases (704 days total, December 16, 2027 through July 5, 2030) focused on Telecom Room (TR) renovations, Telecom Enclosure (TE) installations, and data center upgrades. Phase 1 prioritizes Building 511's Data Center (68 days for cabinet replacement and fiber activation) and Building 500 (Main Hospital Building with six floors plus basement). Subsequent phases address approximately 40 additional buildings in a sequenced manner to minimize operational disruption. The General Contractor must provide all labor, materials, and supervision for demolition, renovation, new construction, MEP installations, structured cabling, fiber splicing, testing, and decommissioning of existing infrastructure. Key coordination dependencies include VA-OIT equipment relocation services, core switch transitions limited to 90-day windows, and staged cabling cutover managed by VA OIT personnel. Infection Control Risk Assessment and asbestos abatement protocols must comply with VA Safety Requirements and specifications; fire-resistance ratings must be maintained throughout construction.

View the file

Other files

File Type Posted
P02 - 36C77627Q0036.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Phasing Plan Narrative

Final Bid Documents

June 18, 2026

Martinsburg VA Medical Center

EHRM Infrastructure Upgrades – Martinsburg, WV

Contract #: 36C776220169

PO#: 613C20234

Project # 613-22-700

Final Bid Documents Submittal | 613-22-700 EHRM Infrastructure Upgrades – Martinsburg, WV

Table of Contents

Background

General Project Requirements

Construction Statement of Work

Infection Control Risk Assessment (ICRA) and Asbestos Abatement

Codes/Requirements

Wayfinding

Campus - Phasing Plan

Campus Civil Work:

PHASING WORK

Campus Civil Work

Interior Construction Work

PHASE 1

PHASE 2

PHASE 3

PHASE 4

PHASE 5

APPENDICES

Background

This Phasing Plan Narrative is written to meet the requirements for EHRM Infrastructure

Upgrades, VAMC Martinsburg, WV. The Narrative has been developed to ensure compliance with the requirements set forth in Contract # 36C77622C0169, PO #

613C20234, Project # 613-22-700. These phasing requirements shall describe the general sequence of the project work, estimated project duration, and what Government constraints will exist that will influence the Contractor's approach to the construction project. The A/E shall be responsible for recording the phasing requirements.

Figure 1 – Campus View

General Project Requirements

This section describes the principal tasks that the A/E must accomplish to meet the expectations of the contract. It also includes proposals following A/E observations of the existing conditions in the current TRs, data center, and proposed TRs and data center at the Martinsburg VAMC campus. An important facet for the success of this project is the location of the data center. The overall phasing plan is approximately 700 days until completion. All construction sequencing shall be coordinated with local VA, local OIT, the

Registered Communications Distribution Designer (RCDD) and the Healthcare

Environment and Facilities Programs (HEFP)/Special Engineering Projects (SEP) coordinators for work-related times for day, night, and weekend work. Work shall be coordinated with VA for code and life safety-related measures associated with phasing of demolition and construction work to support life safety measures. Construction will be phased by building and floor to maintain telecommunication service to critical areas.

Current TRs and the work area outlets will need to remain operational throughout the construction process until the new TRs are operational.

Normal working hours for this contract will be from 7:00AM to 4:30PM (local time), Monday through Friday except for weekends and established Federal Holidays. It is anticipated that the work outside regular working hours will be required. Performing on-site work outside normal working hours will require approval from the COR. Requests shall be submitted via email at least 72 hours prior to the requested date and at no additional cost to the Government. Approval is subject to the availability of on-site staff.

Construction Statement of Work

The Department of Veterans Affairs (VA), Veterans Health Administration (VHA), Program Contracting Activity Central (PCAC) anticipates soliciting bids and subsequently awarding a single Firm-Fixed-Price contract for the construction of the Martinsburg VAMC

EHRM Infrastructure Upgrades project 613-22-700 located at 510 Butler Ave., Martinsburg, WV 25405.

The Martinsburg VAMC is seeking a general contractor to furnish all labor, materials, supervision and perform all work necessary to complete EHRM Infrastructure Upgrades

Martinsburg VA Medical Center. Contractor shall completely prepare site for building operations, including demolition and removal of existing construction, and furnish labor and materials and perform work for Martinsburg VA Medical Center, EHRM Infrastructure

Upgrades, as required by drawings and specifications.

Infection Control Risk Assessment (ICRA) and Asbestos

Abatement

The major applicable codes with regards to the ICRA for this project will adhere to the VA

Safety Requirements as listed in Specifications Section 01 35 26. The Asbestos

Abatement protocol will be followed in accordance with the Confined Space and Asbestos

Programs Usage Limitations.

The buildings’ construction type and fire-resistive ratings of existing buildings will not change as part of this project. Existing fire-resistance rated and smoke-rated walls and floor assemblies within the buildings shall be maintained. Penetrations through rated walls and floors are required to be fire stopped in accordance with NFPA 101 Section 8.3.4.2.

Codes/Requirements

The following is a list of VA and other design and construction criteria per the Scope of

Work (SOW) that will be utilized by the A/E for the development of the phasing plan of this project:

• PG-18-1: Master Construction Specification Index

• PG-18-3: Design and Construction Procedures

• PG-18-15: Minimum Requirements for A/E Submissions, Vol C

Wayfinding

As the Awen Team develops new TR and data center solutions that modify and enhance the facility, our attention will address concerns and inform VA COR regarding signage and graphics to accompany any new TR and data center locations. Temporary

Wayfinding signage will be coordinated and implemented throughout the construction period and dependent on the phase of the plan. Signage will adhere to the local VA station

Wayfinding Plan and the following guidelines/standards:

• VA Signage Design Manual, PG-18-10

• VA Graphic Standards

• VA Signage Design Guide

Campus - Phasing Plan

The telecommunication design of the VA Martinsburg EHRM Infrastructure Upgrade project will provide fiber optic cabling upgrades to support OIT initiatives for the following buildings: 19, 117, 203, 205, 207, 209, 211, 213, 217, 219, 302, 304, 305, 306, 307, 308, 309, 310, 311, 313, 313T, 314, 317, 318, 319, 320, 321, 328, 330, 331, 401, 403, 405, 407, 409, 411,413, 500, 501, 502, 503, 504, 508, 509, 511, 512, 513, 516, 518, 519, 526, and 528.

The A/E has created a phased plan and construction schedule that incorporates specific time constraints and durations for the work to be performed for the construction phase of the project. Sequencing for Telecom Rooms varies and is specific to the construction category identified in the Scope Summary, sheet 00-GI-020/21.

New Telecom Rooms (NEW TR/TE) are to be sequenced as follows:

• Pre-Construction Clearances: Prerequisite Phase.

o Establish the Infection Control Risk Assessment (ICRA) and Pre-Construction Risk

Assessment (PCRA) environmental boundaries.

• Structural Framing & Slab-to-Slab Envelope: Shell Construction.

o Erect the heavy-gauge metal stud partitions (if new in scope). All framing must extend completely slab-to-slab (deck-to-deck) rather than stopping at a suspended ceiling grid.

This creates the continuous physical security boundary mandated by VA physical security directives.

• MEP Rough-Ins & Dedicated HVAC: Infrastructure Trades.

o Install the multi-trade infrastructure paths simultaneously. Route lines for the dedicated

Direct Expansion (DX) split cooling system, mount line-voltage conduits and panelboards

(with 3-phase power where baseline specifications require), and drop the low-voltage conduit stubs for the Division 28 security access controls (PIV card readers and interior IP

CCTV cameras).

• Wall Enclosure, Backboards & Static Flooring: Room Finishes.

o Hang 5/8-inch Type X fire-rated drywall, tape, and sand. Install the required 3/4-inch Fire-

Retardant Treated (FRT) plywood backboards across designated walls from 12 inches to

8 feet 6 inches above the finished floor, keeping the visible fire stamp uncovered. Paint walls and boards with two coats of light-colored, low-VOC, anti-static paint, and lay the

Static-Dissipative Tile (SDT) flooring.

• HVAC Commissioning o Completely clean the space of all construction dust, seals, and drywall particles. Energize, balance, and commission the dedicated HVAC split-cooling units. The room must achieve a continuous, dust-free, climate-controlled status (64Fto 75F, max 55% relative humidity) before any data networking infrastructure or electronics enter the space.

• Grounding Backbone & 4-Post Rack Anchor: Electrical & Rack Assembly.

o Install the Secondary Bonding Busbar (SBB) and establish mechanical bonding to the main campus telecommunications grounding matrix. Assemble and bolt the heavy-duty 4-post equipment racks directly into the structural concrete slab using approved seismic anchor bolts, maintaining a minimum 36-inch clearance envelope at both the front and rear of the racks.

• Structured Cabling, Fiber Splicing & Testing: Low-Voltage Systems.

o Pull the horizontal Category 6A shielded copper bundles and the incoming multi-strand single-mode backbone fiber optic lines through the sleeves and along overhead ladder trays. Terminate lines into the patch panels, perform fusion splicing on the fiber strands, and run full-frequency permanent link diagnostic tests using certified testing hardware.

• PACS Activation & OIT Equipment Handoff: Final Security & Sign-off.

o Energize the localized Uninterruptible Power Supply (UPS) units. Activate the Division 28

Physical Access Control System (PACS) on the outward-swinging door so that entry requires an authenticated federal PIV badge. Hand over the certified cabling matrix test reports to the VA Contracting Officer's Representative (COR), formally transferring custody of the space to VA-OIT to begin loading their active edge switches and clinical servers.

Telecom Rooms to Remain (EXIST):

• Remove existing ceiling system (if room has ceiling) and associated items. Provide temporary lighting as needed.

• Remove existing flooring (if required) and if flooring is hazardous, refer to specification sections 02

82 11 and 02 82 13.19 for location and procedures.

• Reference discipline drawings for extents of architectural, MEP, and telecom work per each room.

It is anticipated this work can be done during normal business hours, but Contractor needs to coordinate with VA COR for scheduling.

• Once any architectural and mechanical work is complete Install new cabling and cabling runway into telecom rooms.

• Once cabling to existing and new cable jacks has been Installed, contractor to coordinate cutover

(cutover by VA OIT) with VA OIT.

• Work will need to be coordinated with VA for rooms that can Be done during normal and night hours.

• Provide new circuiting in rooms where none exist and in rooms Where existing circuits will be removed. Reference electrical drawings for extents of electrical work per each room.

• New power to be installed from existing panel to new circuits In telecom room. Coordinate installation with VA COR due to possible downtime of VA End Users. This work is anticipated to occur at nights or over the weekends.

Telecom Rooms to be Decommissioned (DECOM):

• Prior to removal of existing racks, cabling and associated Hardware, installation of new cabling and cabling runway in Telecom rooms shall be complete and cutover (cutover by VA OIT) to the new installation.

• Once new telecom room work is complete, remove existing Racks, cabling and associated hardware from telecom rooms to be decommissioned. No other equipment should be disturbed or removed. This work is anticipated to be done during normal working hours. Contractor shall coordinate with VA COR for scheduling.

• Disconnect, and seal or cap off abandoned electrical services back to the nearest operational j-box.

• No additional architectural, mechanical or electrical work is anticipated to be done in the decommissioned telecom rooms.

Constraints and durations are applied to the construction schedule and are planned as follows:

Campus Civil Work:

o Four phases, each consisting of 73 days and a total duration of 246 days. The estimated start date is 1/6/27 through 12/15/27

▪ Coordinate Phasing Plan: 1/6/27 – 1/12/27

▪ Phase 1: 1/13/27 – 4/23/27

▪ Phase 2: 4/1/27 – 7/12/27

▪ Phase 3: 6/18/27 – 9/28/27

▪ Phase 4: 9/6/27 – 12/15/27

• Interior Construction Work

• Phase 1: 338 days, 12/16/27 – 4/2/29 o Typical Durations

▪ Telecom Room (TR) Renovation: 65 days, typical

▪ Telecom Enclosure (TE) Installation: 11 days, typical

▪ Cabling: 10 days, typical

▪ Decommissioning existing rooms: 6 days, typical o Building 511 Data Center

▪ Data Center (DC) and Entrance Rooms: 77 days

• Data Center Room 221: 68 days

• Integration Room 131 (Entrance Room Leg A): 10 days

• Tele/Demarc/PBX Room 222 (Entrance Room Leg B): 10 days o Building 500

▪ Basement

▪ 1st Floor

▪ 2nd Floor

▪ 3rd Floor

▪ 4th Floor

▪ 5th Floor

▪ 6th Floor

• Phase 2: 130 days, 3/9/29 – 9/6/29 o Building 501A o Building 501D o Building 502A o Building 502D o Building 502E o Building 512 o Building 513 o Building 516

• Phase 3: 145 days, 8/8/29 – 2/26/30 o Building 217 o Building 302 o Building 304 o Building 306 o Building 308 o Building 310 o Building 314 o Building 318 o Building 319 o Building 320 o Building 321 o Building 328 o Building 330 o Building 331 o Building 411 o Building 413 o Building 503 o Building 508 o Building 519

• Phase 4: 94 days, 2/4/30 – 6/13/30 o Building 305 o Building 313A o Building 313T o Building 317 o Building 403 o Building 405 o Building 407 o Building 409 o Building 504

• Phase 5: 81 days, 3/15/30 – 7/5/30 o Building 19 o Building 117 o Building 203A o Building 205 o Building 209 o Building 211A o Building 213 o Building 518

• Closeout

PHASING WORK

Campus Civil Work

The civil work required to upgrade the campus is extensive, will be constructed prior to the Data Center, and subsequent TR installation. The primary task is to route the exterior infrastructure through the site in a manner that reduces the impacts to existing utilities and the function of the VAMC during construction and includes installation of underground duct bank conduits and interbuilding backbone cabling. Civil work will be conducted in four (4) phases as illustrated in the diagram below. This will minimize disruption to normal operations around the campus.

Interior Construction Work

PHASE 1

Building 511 Data Center

The upgrade of the Data Center located in Room 221 includes a minor renovation of the space and will involve retaining six (6) existing cabinets and replacement of twelve (12) new cabinets. The new fiber optic cabling connection will be established prior to the work commencing in the Data Center. The replacement of the cabinets has a duration of 68 days but must be coordinated with a VA-contracted service for relocation of equipment within the racks. Each system is coordinated with a VA-contracted service for relocation of the equipment within the rack. VA-OIT is responsible for the final connection of each component. The General Contractor is responsible for relocating existing racks and/ or any new racks, patch panels, blanking panels, and patch cables. The sequence for replacing will be initiated with upgrade of Entrance Room Leg A and proceeded by

Entrance Room Leg B for campus LAN (CAN). If A-path is the first new fiber path, then it must be completed, tested, and the core switch must be active on that path before B-path can commence. The cores must be logically connected (temporary umbilical) as one will be in the CRRC and the other will be in the old Data Center for a period of time during transition. New redundant fiber optic cabling will be provided between the existing CRRC and the new MDA. Provide temporary fibers (72-strand OM-4, with 12-strand MM fiber assemblies and 24-strand OS-2 with 12-strand SM assemblies) routed to CRRC and old data center. Temporary fiber will be required for server connection during construction.

Once the first new fiber leg is complete, extend WAN Circuit 1 from building 500 to CRRC.

Move Core Switch 1 from building 500 to CRRC. Make MDA fiber cross connects. Once the second new fiber leg is complete, extend WAN Circuit 2 from building 500 to CRRC.

Move Core Switch 2 from 500 to CRRC. Coordinate with National OIT to provide a new

Core Switch during this process.

The GC will coordinate minor renovation of the Data Center with phasing of work to be completed within 90 days to allow the VA National LAN Team sufficient opportunity to complete activation. Core switches should not be separated for more than the 90-days period, which means once Core A has been relocated, all associated TR migrations should be completed within that 90-day window so that Core B can also be relocated accordingly. At no point should a core switch be off-line. WAO activation of a new TR cannot be completed until at least one side of fiber is connected and both COREs are logically connected to the TR. DC rack relocations will have intermittent durations of activation by the VA where the GC is prohibited from work. GC’s construction contract should include the necessary fiber and patch cables to move servers. Unless otherwise directed, the GC will provide fiber and patch cables in sufficient quantities to move servers prior to transition. Patch cables are to be purchased in 1 meter, 2 meter and 3-meter lengths and utilized in a manner that minimizes the length of loop in the cable managers.

No “spaghetti” cabling will be allowed. GC to purchase 10% spare of each cable length.

The local VA Office of Information & Technology (OIT) is instrumental in coordinating the installation phase of the project and will have responsibility for those items addressed in the Project Phasing Checklist. The VA OIT department is responsible for conducting the commissioning review and approving the final acceptance and verification of operation of the DC. These items include the following:

• Validate Team Freedom’s Main Computer inventory list and provide to the A/E for proper phasing.

• Validate all OIT servers with Team Freedom

• Validate all FMS servers with Team Freedom

• Validate all other tenant servers with Team Freedom

• Verify that Team Freedom has provided a server consolidation plan

• Verify Area Manager submitted Service Now ticket 6 months prior to DC activation

• Coordinate B-path installation of campus fiber loop

• Coordinate with AE/GC on minimizing downtime in efforts to remain operational

• GC to validate with VA COR that there are no other projects that impact the phasing of the EHRM project

Building 500: Main Hospital Building

The second part of phase 1 is to proceed with the TRs listed in the Main Hospital Building as noted below. There are 6 floors to this building plus a basement and will be completed in ascending order by floor. Phasing for new TRs will be coordinated by installing new equipment in the new TR, running new cables, if required) or relocating the existing telecom equipment. No temporary TR spaces will be utilized. New TRs are designed with new racks and new components, UPS, and cabling. The floors include renovation of existing TRs to include phases of Demolition, completion of Interior upgrade to current design, installation of Mechanical/Fire Suppression systems followed by Telecom upgrades including new racks, switches, UPS, and cabling. All new system upgrades are tested and inspected to finish up the room and prepare for full operation. Once TRs are found to be in compliance and fully operational, the work for the TRs identified for decommissioning is begun and prepared for turnover. The VA OIT department is responsible for conducting the commissioning review and approving the final acceptance and verification of operation of the TR. Rooms are identified below.

• Basement TR Renovation/Construction o GA-036 o GB-134 o GD-100A o GD-129

• Basement TRs for Decommission o GA-101 o GA-139B o GC-105B o GC-105C o GD-102B o GD121B

• 1st Floor TR Renovation/Construction o 1B-109 o 1D-114 o 1D-123A

• 1st Floor TRs for Decommission o 1A-106 o 1A-143B o 1C-143C o 1C-100 o 1D-122B o 1D-180B o 1D-180C

• 2nd Floor TR Renovation/Construction o 2A-122D o 2B-130 o 2D-113A

• 2nd Floor TRs for Decommission o 2A-100 o 2A-120 o 2B-102 o 2C-156B o 2C-156C o 2D-110B o 2D-146B o 2D-146C

• 3rd Floor TR Renovation/Construction o 3A-303 o 3A-304

• 3rd Floor TRs for Decommission o 3A-300 o 3A-310 o 3C-101

• 4th Floor TR Renovation/Construction o 4A-144A o 4A-152

• 4th Floor TRs for Decommission o 4A-102 o 4A-145 o 4C-101

• 5th Floor TR Renovation/Construction o 5A-123 o 5A-139

• 5th Floor TRs for Decommission o 5A-102A o 5A-109A o 5C-100

• 6th Floor TR Renovation/Construction o 6A-136

• 6th TRs for Decommission o 6A-102 o 6A-140

PHASE 2

Phase 2 Buildings

There are nine (9) buildings included in Phase 2 as listed below with the corresponding

(number of TRs, as in other phase descriptions) TRs to be renovated/constructed and the

(number of) rooms to be decommissioned. The phase sequencing will be coordinated with the VA and the GC to ensure that all rooms remain operational and to coordinate any afterhours work. The buildings include renovation of existing TRs to include phases of

Demolition, completion of Interior upgrade to current design, installation of

Mechanical/Fire Suppression systems followed by Telecom upgrades including new racks, switches, UPS, and cabling. All new system upgrades are tested and inspected to finish up the room and prepare for full operation. Once TRs are found to be in compliance and fully operational, the work for the TRs identified for decommissioning is begun and prepared for turnover. The VA OIT department is responsible for conducting the commissioning review and approving the final acceptance and verification of operation of the TR. Rooms are identified below.

• Building 501A TR Renovation/Construction o A-106

• Building 501B TR Renovation/Construction o B-105

• Building 501D TR Renovation/Construction o 501D-101

• Building 502A TR Renovation/Construction o A-103A

• Building 502D TR Renovation/Construction o D-176

• Building 502E TR Renovation/Construction o E-107A

• Building 512 TR Renovation/Construction o 08

• Building 513 TR Renovation/Construction o 130

• Building 516 TR Renovation/Construction o 133

• TRs for Decommissioning o Building 501A

▪ A-146

▪ A-214 o Building 501B

▪ B-146 o Building 501C

▪ C-118 o Building 502B

▪ B-172 o Building 502C

▪ C-172 o Building 502D

▪ D-172 o Building 502E

▪ E-122 o Building 502F

▪ 120 o Building 503

▪ 503-6

PHASE 3

Phase 3 Buildings

There are seventeen (17) buildings included in Phase 3 as listed below with the corresponding six (6) TRs to be renovated/constructed, eight (8) TEs for installation, and the rooms to be decommissioned. The phase sequencing will be coordinated with the VA and the GC to ensure that all rooms remain operational and to coordinate any afterhours work. The buildings include renovation of existing TRs to include phases of Demolition, completion of Interior upgrade to current design, installation of Mechanical/Fire

Suppression systems followed by Telecom upgrades including new racks, switches, UPS, and cabling. All new system upgrades are tested and inspected to finish up the room and prepare for full operation. TEs are to be installed in this phase which includes demolition/preparation of the office/room for installation of a telecom enclosure, testing, and inspection. Once TRs/TEs are found to be in compliance and fully operational, the work for the six (6) TRs identified for decommissioning is begun and prepared for turnover. There are three (3) buildings whose scope is limited to upgrade of the fiber cabling only. The VA OIT department is responsible for conducting the commissioning review and approving the final acceptance and verification of operation of the TR. Rooms are identified below.

• Building 217 TR Renovation/Construction o 103-L

• Building 302 TR Renovation/Construction o 302-5

• Building 304 TE Installation o 304-1TE

• Building 306 Fiber Cable Upgrade

• Building 308 TR Renovation/Construction o 308B-6

• Building 310 Fiber Cable Upgrade

• Building 314 TR Renovation/Construction o 314-18

• Building 318 TR Renovation/Construction o 318-13

• Building 319 TR Renovation/Construction o 319-B

• Building 320 TE Installation o 107TE

• Building 321 Fiber Cable Upgrade

• Building 328 TE Installation o 328-6

• Building 330 TE Installation o 330TE

• Building 331 TE Installation o 331-2

• Building 411 o 411A-18

• Building 503 TE Installation o 008C

• Building 508 TE Installation o 508-118

• Building 519 TE Installation o 106A

• TRs for Decommissioning o Building 217

▪ 102-G

▪ 111-B o Building 318

▪ 318-113TE

▪ 318-114A o Building 320

▪ 102TE

o Building 413

▪ 413B-2 o Building 503

▪ 503-6

PHASE 4

Phase 4 Buildings

There are eleven (11) buildings included in Phase 4 as listed below with the corresponding four (4) TRs to be renovated/constructed, two (2) TEs for installation, and the rooms to be decommissioned. The phase sequencing will be coordinated with the VA and the GC to ensure that all rooms remain operational and to coordinate any afterhours work. The buildings include renovation of existing TRs to include phases of Demolition, completion of Interior upgrade to current design, installation of Mechanical/Fire

Suppression systems followed by Telecom upgrades including new racks, switches, UPS, and cabling. All new system upgrades are tested and inspected to finish up the room and prepare for full operation. TEs are to be installed in this phase which includes demolition/preparation of the office/room for installation of a telecom enclosure, testing, and inspection. Once TRs/TEs are found to be in compliance and fully operational, the work for the three (3) TRs identified for decommissioning has begun and is prepared for turnover. There are five (5) buildings whose scope is limited to upgrade of the fiber cabling only. The VA OIT department is responsible for conducting the commissioning review and approving the final acceptance and verification of operation of the TR. Rooms are identified below.

• Building 305 Fiber Cable Upgrade

• Building 309 Fiber Cable Upgrade

• Building 313A Fiber Cable Upgrade

• Building 313T TE Installation o Room 9

• Building 317 TR Renovation/Construction o 317-100E

• Building 403 TR Renovation/Construction o 403A-16

• Building 405 TR Renovation/Construction o Room 10

• Building 407 Fiber Cable Upgrade

• Building 409 Fiber Cable Upgrade

• Building 411 TR Renovation/Construction o 411A-18

• Building 504 TE Installation o Room 114

• TRs for Decommissioning o Building 311A

▪ 311A o Building 311B

▪ 311B-1 o Building 413B

▪ 413B-2

PHASE 5

Phase 5 Buildings

There are eight (8) buildings included in Phase 5 as listed below with the corresponding four (4) TRs to be renovated/constructed, two (2) TEs for installation, and the rooms to be decommissioned. The phase sequencing will be coordinated with the VA and the GC to ensure that all rooms remain operational and to coordinate any afterhours work. The buildings include renovation of existing TRs to include phases of Demolition, completion of Interior upgrade to current design, installation of Mechanical/Fire Suppression systems followed by Telecom upgrades including new racks, switches, UPS, and cabling. All new system upgrades are tested and inspected to finish up the room and prepare for full operation. TEs are to be installed in this phase which includes demolition/preparation of the office/room for installation of a telecom enclosure, testing, and inspection. Once

TRs/TEs are found to be in compliance and fully operational, the work for the three (3)

TRs identified for decommissioning has begun and is prepared for turnover. There are two (2) buildings whose scope is limited to upgrade of the fiber cabling only. The VA OIT department is responsible for conducting the commissioning review and approving the final acceptance and verification of operation of the TR. Rooms are identified below.

• Building 19 TE Installation o Room 19

• Building 117 TE Installation o Room 117-3

• Building 203A TR Renovation/Construction o 203A-2

• Building 205 Fiber Cable Upgrade

• Building 209 Fiber Cable Upgrade

• Building 211A TR Renovation/Construction o 211A-4-16

• Building 213 TR Renovation/Construction o B125

• Building 518 TR Renovation/Construction o 212

• TRs for Decommissioning o Building 117

▪ 117 o Building 205A

▪ 205-3A o Building 209A

▪ 209-3

APPENDICES

Appendix 1: Draft Construction Schedule

Appendix 2: Final Bid Documents - Drawings

Background
General Project Requirements
Construction Statement of Work
Infection Control Risk Assessment (ICRA) and Asbestos Abatement
Codes/Requirements
Wayfinding
Campus - Phasing Plan
Campus Civil Work:
PHASING WORK
Campus Civil Work
Interior Construction Work
PHASE 1
PHASE 2
PHASE 3
PHASE 4
PHASE 5

APPENDICES