This document is a Technical Questions and Responses Tracking Sheet for Solicitation #36C77625B0020, relating to the Atlanta EHRM Construction - Infrastructure & Data Center Upgrades project. The document contains 65 detailed questions and responses from potential contractors, covering a wide range of technical specifications and project requirements. Key areas of inquiry include telecommunications infrastructure, security systems, access control, network switches, fiber optic cabling, existing system compatibility, and project logistics.

Notable responses include clarifications that the project involves upgrading existing telecommunications rooms (TRs) in multiple buildings, utilizing existing pathways with supplemental J-hooks, and working with the current system vendor Trofholz Technologies. The VA confirmed that new cabling will be installed at existing locations, and contractors must evaluate and coordinate with existing system manufacturers. The bid due date has been extended to August 6, 2025, at 1 pm EST, and the project is a Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside with an estimated performance period of 730 calendar days.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND

RESPONSES TRACKING SHEET

SOLICITATION#:

PROJECT TITLE:

36C77625B0020

Atlanta - EHRM - Constr - Infrastructure & Data Center

Upgrades - 508-22-700

CONTRACTOR QUESTION VA RESPONSE

We have several RFls based on what appears to be a conflict between the drawings and specs (highlighted below) for your review / response.

Low Voltage (LV): Div. 27 and Div.

28 have separate requirements, as indicated on Sheet

• In Division 27 specifications, it does not specify who is providing the ethernet networkTN001• switches. Will the communication switches be existing or who is responsible for providing them?

o If the contractor is to provide, what is the preferred make and model?

o Who is responsible for configuring the devices?

• Will Division 28 23 00, Security ethernet network switches be existing, or who is responsible for providing them?

o If the contractor is to provide, what is the preferred make and model?

o Who is responsible for configuring the devices?

We ask these questions because of the verbiage listed below:

1. Drawings

a. Page TN201 - Note 6 says the following

i. 2 RU HORIZONTAL CABLE MANAGERS PER RACK SUPPORTING

CLIENT PROVIDED ETHERNET SWITCHES. PROVIDE ONE

CABLE MANAGER FOR EACH CABLING PATCH PANEL

INSTALLED. COORDINATE FINAL PLACEMENT WITH CLIENT.

2. Specifications

a. Attachment D-508-22-700 CLIENT SPECS BID

a. Page 1131/1151 - Division 28 23 00 -46

i. Network Switch:

1. Install the network switch per design and construction documents, and as specified by the OEM.

2. Connect network switch to AC power (UPS).

3. Connect network cameras to network switch.

4. Configure the network switch per manufacturer's recommendation and project requirements.

Sheet TN001 Communications (Div.

27) General Note 1 indicates to provide cabling infrastructure.

Powered equipment and electronic devices not in contractor scope unless otherwise noted. Communications switches provided by Client as indicated on Sheet TN201 Note 6.

Sheet TN001 Security (Div. 28) General Note 1 indicates to provide a complete and fully functional electronic safety and security system.

General Note 2 indicates the contractor shall evaluate existing systems and coordinate with manufacturers and service providers to finalize requirements and develop shop drawings to execute the work.

Sheet TN505 Detail 1 example line diagram indicates Security ethernet switches are existing. However, new switch may be necessary based on Contractor survey. Contractor to propose manufacturer for VA approval.

Security system analysis and design not in A&E scope.

CONTRACTOR QUESTION VA RESPONSE

Will the PACS & Video systems be connected to a supplied VAMC OIT network at LV: Yes. Also, see RFI line item 1.

2 each of the two locations?

Per the plans, will the government confirm that the Passive Infrared Motion Detectors LV: Yes. Also, see RFI line item 1.

labeled "MD" in TR Rooms be an input on the PACS system for reporting?

Is this project tax-exempt, if so, will a certificate

4 be provided? Please confirm that all state and local tax must be included for material and equipment

ET series drawings for CCTV camera. Bid spec documents do not specify what system are currently in place for this project, please answer the following questions:

a. What is the manufacturer of the current video management system?

b. What version/existing is the current video management system operating?

c. Are we expected to support version upgrades as part of this contract?

d. Are their sufficient existing licenses to support the new cameras?

e. Are the cameras to be 2MP pan/tilt/zoom or fixed dome?

Please refer to Solicitation - FAR

52.229 -3 and special note after.

Georgia is NOT Tax Exempt.

LV: Sheet TN001 Security (Div. 28) General Note 1 indicates to provide a complete and fully functional electronic safety and security system.

General Note 2 indicates the contractor shall evaluate existing systems and coordinate with manufacturers and service providers to finalize requirements and develop shop drawings to execute the work.

TN001 Symbols Legend indicates cameras are fixed.

Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com

f. Is there a current vendor/installer of this system that we can contact

CONTRACTOR QUESTION

ET series drawings for card reader/pin pad. Bid spec documents do not specify what system are currently in place for this project, please answer the following questions:

a. What is the manufacturer of the current access control system.

b. What version/existing software is the access control system operating.

c. Are we expected to support the version?

updates as part of the contract?

d. Are the sufficient licenses to support the new doors?

e. Is there any existing integration between the access control and CCTV systems?

f. Is there a current vendor/installer of this system that we can contact?

Is there an allowance of Cat 6A cables & 1" data rough-in that should be carried within the

Div .26&27 pricing? Some previous requirements on other projects requested 5-10% additional Cat

6A cables & 1" data rough-in to cover what may have missed during design.

Existing Nurse Call System.

a. Q- Is there a current maintenance vendor/installer of this system that we can contact?

9 Is conduit required for grounding conductors running/installed ceiling and risers?

Is there a requirement for x-ray scanning of concrete floor slabs prior to core drilling for floor-to-floor sleeves/conduits?

VA RESPONSE

LV: LV: Sheet TN001 Security (Div.

28) General Note 1 indicates to provide a complete and fully functional electronic safety and security system.

General Note 2 indicates the contractor shall evaluate existing systems and coordinate with manufacturers and service providers to finalize requirements and develop shop drawings to execute the work.

Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com

LV: Include a 10% contingency for cabling per each existing outlet configuration type/quantity indicated on drawings.

This system is currently being installed.

Vendor is Jeron 790 System.

ELEC: Yes, conduit is required.

G PR is to be used prior to core drilling.

Note 8 on FX001.

Is there a location where site asphalt and concrete can be stored/separated? Can 11 this material be removed from the site once per week?

Will soil testing be performed prior to construction, to determine if any soils are

12 contaminated?

Is there a location where spoil dirt can be stored?

Is there a specific location that will be used as a laydown yard during construction?

Will erosion control plans be provided?

Have there been any boring samples/test made for duct bank pathway/trench to determine subsurface condition?

No outside construction.

Not required per the Scope of Work, as all pathways exist. No new duct banks.

Not required per the Scope of Work, as all pathways exist. No new duct banks.

We don’t have a defined location.

VA will set aside a location for laydown prior to construction.

Not required per the Scope of Work, as all pathways exist. No new duct banks.

Not required per the Scope of Work, as all pathways exist. No new duct banks.

WAO-There are no prints that indicate new locations. Is this a 1 for 1 replacement for L V: Provide new cabling at existing existing cables?

locations as indicated on floor plans and Sheet Notes.

Is there required a full survey of every room/above ceiling? If so, who dictates the outlet location and quantity of cables per location?

Can the government provide a quantity of CAT6 A cables that need to be installed by TR? Please provide a Drop Count Matrix that needs to be provided.

What is the drop count of each coverage zone? If it is a 1 for 1 swap, how many existing drops are located in each coverage zone?

Is there a count and length for Cat6A patch cords?

22 Are we to provide one patch cable for each station and closet end?

23 Is there a count and length for Fiber Patch cords?

24 Are we to provide patch cables for each pair of strand at each end?

25 Is there any copper backbone (25-pair or larger) needed?

VA RESPONSE

LV: A field survey was conducted during design development to locate existing outlets to the best extent possible.

Provide new cabling at existing locations as indicated on floor plans and Sheet Notes.

Also, see Sheet TN001 Communications General Note 3.

LV: See Sheet TN701 WAO schedule

L V: See RFI line item 19.

LV: See Sheet TN701 Patch Cord Schedule.

LV: See RFI line item 21.

LV: See RFI line item 21.

LV: See RFI line item 21.

LV:No

TN series plan does not show pathways/backet cable tray for horizontal cabling. LV: The Client BOD was not intended Q-Attachment-E-508-22-?00_CLIENT_BOD_BID (1) section Telecommunications to be included in the Bid Package.

Basis of Design (see below). Please give location/pathway as per new building pathway requirements.

New Building Pathways

Existing code-compliant pathways will be utilized, supplemented by new pathways as needed, ensuring a maximum cable fill factor not exceeding 40%. Pathways penetrating fire-rated barriers shall be self-sealing UL listed mechanical assemblies that allow re-entry without the need for fire-stop pillows, caulk, putty, etc.

Furthermore, pathways will be routed for convenient access and will be isolated from sources of electromagnetic

26 interference (EMI), including cables with different signal types and voltage levels. Additional requirements include the following items:

. Provide a minimum 12" wide x 4' deep basket-type cable tray system in main corridors and hallways where feasible. The cable tray system shall be rigidly and structurally supported, maintain a reasonably level elevation, properly bonded between sections, and bonded to the nearest Telecommunications

Secondary Bonding Busbar.

. Use supplemental open-top cable supports (e.g., J-hooks) from the cable tray or primary pathway system to work area ouUets where local regulations allow. J-hooks shall be independenUy and structurally supported, spaced at 4' maximum, and not exceed 12" of sag for installed cables.

TN003 shows civil pathway (doted lines) does not indicate if new or existing. Please advise.

TN series plans show A/B fiber backbone do not indicate pathway requirements.

Q-ls Micro duct required?

Q-lf Micro duct is required; will it need to be installed in conduit (EMT)?

See Sheet TN001 Communications General Note 5, Utilize existing code-compliant building pathways and supplement with J-hooks as necessary to complete the work, and base bid quantity indicated.

New cable tray not included in design outside of Telecom Rooms.

LV: Pathways are existing.

LV: Sheets TN002 and TN003 Sheet Note 1 indicates air-blown micro-duct fiber optic pathway is required. Basis of design is Sumitomo Future-flex Solution.

Also, see Sheet TN601 Sheet Note 2.

Micro-duct not required to be in EMT.

CONTRACTOR QUESTION

Attachment-E-508-22-?00_CLIENT_BOD_BID (1) section Telecommunications Basis of Design indicates the existing pathway are either at or near full capacity. (see below)

Q-How is the A&EN A going to address this as the plans do not show any new pathways?

The existing access control system is currently not working/powered up. Is it in the Scope of Work to get the existing system operable?

Can we get a schedule that shows which existing access control doors go back to which panels?

VA RESPONSE

LV: The Client BOD was not intended to be included in the Bid Package.

See Sheet TN001 Communications General Note 5, Utilize existing code compliant building pathways and supplement with J-hooks as necessary to complete the work, and base bid quantity indicated.

Existing horizontal and backbone cabling in Contractor scope to be demolished.

LV: Sheet TN001 Security (Div. 28) General Note 1 indicates to provide a complete and fully functional electronic safety and security system.

General Note 2 indicates the contractor shall evaluate existing systems and coordinate with manufacturers and service providers to finalize requirements and develop shop drawings to execute the work.

Existing vendor and system manufacturer information - Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com.

There are no PACS on these doors.

What is the preferred Camera Manufacturer?

Camera locations are not shown on the drawings. Can we get a list of how many 33 camera cables there are in each Telecom Room?

Please confirm the Cat6A cable is a one for one cable replacement of all existing

Cat6/5e cabling.

262413 - Distribution Switchboards: We will be adding to the existing power distribution and need to match existing. Can the VA please advise the manufacturer of the existing switchboards and panelboards?

Division 27 Communications: Is the inner building fiber to be in tray, conduit or cable hooks?

VA RESPONSE

Existing vendor is Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com

Camera are indicated on floor plans outside of each modified/new Telecom Room and the Data Center.

Provide new cabling at existing locations as indicated on floor plans and Sheet Notes. Not necessarily a 1-1 cable replacement.

See Drawings TN505, 701

The facility appeared to have limited cable tray and primarily consisted of J-hooks.

See Sheet TN001 Communications General Note 5, Utilize existing code-compliant building pathways and supplement with J-hooks as necessary to complete the work, and base bid quantity indicated.

281300 - Physical Access Control System: We are adding to the existing security system. Can the VA advise the manufacturer of the existing PACS? Is there an existing maintenance contractor for the security system? If so, can you please provide contact information for the maintenance contractor?

Existing vendor is Trofholz

Technologies please contact Lee

Robbins at 803 243-1368 or lee.robbins@trofholz.com

281600 Intrusion Detection System: We are adding to the existing IDS system. Can the VA advise the manufacturer of the existing IDS system? Is there an existing maintenance contractor for this system? If so, can you please provide contact information for the maintenance contractor?

282300 Video Surveillance: We are adding to the existing SSTV system. Can the VA advise the manufacturer of the existing SSTV system? Is there an existing

39 maintenance contractor for this system? If so, can you please provide contact information for the maintenance contractor? Will additional licenses be needed for cameras?

283100 - Fire Alarm & Detection: We are adding to the existing fire alarm system. Can the VA advise the manufacturer of the existing fire alarm? Is there an existing maintenance contractor for the fire alarm system? If so, can you please provide contact information for the maintenance contractor?

Reference specification section 01 00 00 - 34 Paragraph 1.23 Photographic

Documentation

41 Can the contractor QC manager serve as the photographer if they meet the requirement of having experience photographing construction projects. The term "Commercial Photographer" is vague, has no licensing requirements or any other information required.

Is there a proprietary Controls Contractor at the facility? If so, please provide the 42 company name and point of contact.

On the telecom drawings (example 01-TN99B) there are drop locations labeled D.

43 Can you please provide information on what that means? Drop count?

Drawing TN701 shows the Communications WAO Schedule to have racks and drops for Building 01 TR 3121A. Please provide enlarged drawings for Room 3121A in

Existing vendor is Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com

Existing vendor is Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com

Siemens; Siemens is the sub-contractor.

Follow Design Manual.

Ameresco/ Hoffman

Marc.Skeen@va.gov

Correct reference is 3A121A, Included in the WAO schedule. Building 01.

Sheet TN001 Symbols Legend indicates existing outlet to be demolished.

TN002 is not too scale. Please confirm the distance between B01 and T-13 for proper fiber take off.

TN003 is not too scale. Please confirm the distance of the new duct bank to get proper fiber take off.

Reference Drawing TN003:

a. Is the underground fiber route on this drawing new or existing?

b. If the Underground fiber route is new, please provide details for the fiber run and Manholes/Hand Holes

Can we get an enlarged view of the MCR in Building 125? Is there any work that is required in this room?

Civil Engineering drawings indicating conditions See attachments I - K.

Pathways are existing. See

Attachments I - K.

Building 125 MCR room BA036 scope limited to accommodating new fiber optic backbone cabling in existing racks. Room identified on Sheet 125-

TN 100. Coordinate rack locations with local VA representatives.

All fiber cabling is new. See Sheet

TN601 cabling diagrams.

Pathways are existing. See attachments I - K.

Please confirm where Tube Distribution Units are required?

Please confirm if innerduct is required in this project?

Ref: Physical Access Control, Spec Section 28 13 00

1. Is there an existing server(s) in place for access control? If so, please provide the make/model?

2. Spec Section 28 13 00. What Version of Software House C-Cure are you currently running?

51 3. Will the government confirm that the Physical Access Control System to be installed will be Software House?

4. Per the site visit conducted on the 24 the June, there were access control panels in place. Are we reusing any of that equipment?

5. Is the Service and Support Agreement up to date for the Access control?

6. Are there any existing security vendors that are required to be utilized for this project?

Will the sign-in sheet from site visit be available in addendum?

VA RESPONSE

Sheet TN601 Sheet Note 2 indicates distribution hubs are acceptable in telecom Rooms. This is not limited to fiber optic fusion splicing. Other locations may be proposed in Contractor shop drawings for VA approval.

Sheets TN002 and TN003 Sheet Note 1 indicates air-blown micro-duct fiber optic pathway is required. Basis of design is Sumitomo Future-flex Solution.

Also, see Sheet TN601 Sheet Note 2.

Micro-duct not required to be in EMT.

Sheet TN001 Security (Div. 28) General Note 2 indicates the contractor shall evaluate existing systems and coordinate with manufacturers and service providers to finalize requirements and develop shop drawings to execute the work.

Existing vendor is Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com

Posted in Amend 0001 on 6/25.

Please clarify if a superintendent can be a dual hat to cover the requirements of

SSHO? If no to the question above, will the SSHO need to be full-time for this project?

Please clarify if a superintendent can be a dual hat to cover the requirements of

Yes.

No, they cannot be dual hat.

54 QA/QC? If no to the question above, will the QA/QC need to be full time for this project?

55 Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC? No, they cannot be triple hat.

Please provide the latest wage determination for this project's county.

Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?

Will mechanical rooms, offices, etc. be cleared of all stored materials prior to the contractor entering those areas?

Will a full-time fire watch be required during activities such as cutting, brazing, welding? How long after such activities are completed?

Posted with Solicitation - See Attachment B.

The wage determination awarded with the contract will be consistent and will not be updated throughout the life of the contract.

Yes.

Per NFPA 51 B, a fire watch shall be maintained for 1 hour following the completion of hot work operations.

Following the fire watch, fire monitoring shall be provided within the hot work area for up to an additional 3 hours as determined by the PAI (Permit authorizing Individual).

Will any existing glycol be required to be removed and disposed of by the contractor?

If so, can the total volume of glycol be provided?

Is there a particular vendor or contractor currently servicing and maintaining the Ameresco/ Hoffman Marc.Skeen@va.gov;

The current BMS system is obsolete and is set to be updated in 2026.

Building Automation System or Temperature Controls System?

Please confirm if we will be allowed to keep a locked storage container or Conex box within the grounds.

Is there a recent hazardous materials survey available? Are there any asbestos or

63 lead containing materials that need to be removed?

Who is the current security vendor?

To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date.

A survey is not included in BID PACKAGE; contractor to field verify all existing conditions.

Trofholz Technologies please contact Lee Robbins at 803 243-1368 or lee.robbins@trofholz.com.

Contracting has extended the bid due date. See SAM.gov Amendment 0002.

Bids are currently due August 6, 2025, at 1pm EST.

These TR are new. Shouldn’t require glycol disposal.

Yes.