This document is an amendment for a federal contract opportunity to provide architectural and engineering (A-E) services for the design of a new police annex facility at the VA Menlo Park Division in Menlo Park, California.
The amendment provides responses to questions received regarding the use of prior project subconsultants, signage requirements, and LEED certification. It confirms there are no restrictions on using prior subconsultants, the VA will provide signage standards, and there is no LEED requirement for this project. The SF-330 qualifications packages are due on September 23, 2024 at 8 AM PT. The anticipated contract award is planned for Spring 2025 with a 222-calendar-day period of performance for design completion. This is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSBs).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Encl 2F OrigBidDwgsSignageStructFireAlarm.zip | ZIP file | |
| Encl 2A OrigBidDwgsGeneralLandscape.zip | ZIP file | |
| Encl 2G OrigBidDwgsPMTeleFP.zip | ZIP file | |
| SOW_AE_Services - Construct New Police Annex MPD FINAL.pdf | ||
| Encl 4 Exist Materials Testing Report dated April 20 2021.pdf | ||
| Encl 3 Conceptual Floor Plan-The new design scope.pdf | ||
| SCA WD 2015-5637 Rev 27 07222024.pdf | ||
| Encl 2J OrigBidDwgsE Part 2.zip | ZIP file | |
| Encl 6 Geotechnical Report Emergency Service Annex May 17 2013.pdf | ||
| Encl 2K OrigBidSpecs.zip | ZIP file | |
| Encl 2H OrigBidDwgsE Part 1.zip | ZIP file | |
| Encl 2B OrigBidDwgsCIVIL Part 1.zip | ZIP file | |
| Encl 5 PG 18-15 Vol C.pdf | ||
| Encl 1 CommissioningRqmts.zip | ZIP file | |
| 36C77624R0134.docx | DOCX document | |
| PPQ - 7-11-24.docx | DOCX document | |
| Encl 2C OrigBidDwgsCIVIL Part 2.zip | ZIP file | |
| Encl 2D OrigBidDwgsArch Part 1.zip | ZIP file | |
| Encl 2E OrigBidDwgsArch Part 2.zip | ZIP file |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
640-421 36C776 Department of Veterans Affairs Program Contracting Activity Central
6100 Oak Tree Blvd, Suite 490 Independence OH 44131
36C776 Department of Veterans Affairs Program Contracting Activity Central
6100 Oak Tree Blvd, Suite 490 Independence OH 44131 To all Offerors/Bidders
36C77624R0134
X
X 9/23/2024 at 8:00 am PT
Minor Design for New Police Annex for Menlo Park, CA
The purpose of this Amendment 01 is to provide responses to the questions received through 9/6/2024 (see attached).
All other terms and conditions remain unchanged unless specified herein.
SF 330s are due on September 23, 2024 at 8 AM PT.
Joelle Mascarenas VHA PCAC Contracting Officer
Project 640-421 - Minor Design for New Police Annex for Menlo Park, CA Amendment 1 for Project 640-421 36C77624R0134
Question 1: Could we approach and retain the primary consultants that were used on the original project: Mechanical, Electrical, Geotech, Structural, etc. It may make the learning curve much easier vis-a-vis a new team.
Response: There are no restrictions on use of prior project subconsultants. Consider qualifications and work required per the SOW and Request for SF-330s for team requirements. This is a new project, and the former project requirements do not apply.
Question 2: Signage...does Campus have on call Sign Supplier; and/or a sign design standard? Or is this scope to be included in Interior Design services. Other campuses we have worked on already have a signage package breaking out room types, etc.
Response: Refer to the SOW for the work required for signage, section 4.3.1.1-Base Bid Items-bullet 9: “Provide exterior and interior signage using VA standards.” The VA standards will be provided to the A/E after contract award. The A/E will need to work with the VA regarding the standards and any specific VA requirements.
Question 3: Also does it have to be formally LEED certified?
Response: There is no LEED requirement for this project.