Att 1 Construction SOW Revised 504-21-700 - 3-27-25.pdf

PDF 119 KB Posted

Attached to
Z2DA--VHA Construction for EHRM Infrastructure Upgrades at the Amarillo VAMC Project 504-700
Solicitation number
36C77624R0084_1
Issued by

About this file

This Revised Statement of Work (SOW) details infrastructure upgrade requirements for the Amarillo VA Medical Center's telecommunications system. The project encompasses comprehensive telecommunications infrastructure improvements, including demolition and construction of a new main computer building with potential future expansion, installation of new fiber routes, data cables, cable trays, conduits, telecommunications enclosures, and security systems. The contractor will be responsible for completing all work within 548 calendar days of the Notice to Proceed, while maintaining continuous operation of surrounding departments throughout construction and demolition phases.

Key technical requirements include upgrading campus telecommunications infrastructure, constructing new telecommunications rooms, performing trenching and dirt work, installing new fiber and data cable routes, and implementing security systems. The contractor must adhere to strict quality assurance standards, provide daily progress reports, ensure safety compliance, obtain necessary permits, and warranty all work for one year from the date of acceptance. The project is being executed by the Department of Veterans Affairs Technology Acquisition Center Austin, with the specific solicitation number 36C77624R0084_1, and will require careful coordination with the VA's Contracting Officer's Representative to minimize disruption to ongoing medical center operations.

View the file

Other files

File Type Posted
36C77624R0084 0006 SF 30.docx DOCX document
36C77624R0084 0012.docx DOCX document
PPQ - Amarillo.docx DOCX document
Limitations on Subcontracting - Construction.docx DOCX document
RFP 36C77624R0084 3-28-2025.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REVISED STATEMENT OF WORK

EHRM INFRASTRUCTURE UPGRADES AMARILLO

504-21-700

1. SCOPE: Provide all labor, supervision, materials, equipment, to update the telecommunications system at the Amarillo VA Medical Center located in Amarillo, Texas 79106.

This project is to replace the campus main computer room, upgrade and replace telecommunications closets, and upgrade campus fiber and data cable.

2. CONTRACTOR RESPONSIBILITIES: The Contractor shall exercise extreme care to avoid damaging Government property such as buildings, equipment, trees, shrubs, or turf. Any damage to Government property by the Contractor shall be repaired by the Contractor to its original condition at no additional cost to the Government. The contractor shall restore ALL disturbed grounds to existing conditions. The Contractor shall ensure that all materials are new, free from defects, imperfections and asbestos free (NO ASBESTOS CONTAINING MATERIALS SHALL

BE USED ON THIS PROJECT).

3. SCHEDULE OF WORK: The Contractor shall notify the Contracting Officer’s Representative (COR) Mr. Logan Dunn, Engineering Building 34, phone: 806-355-9703 x4516, prior to start of work. The Contractor shall schedule work through the COR. The Contractor shall coordinate work with COR NLT 3 days before starting work. Work shall be completed with-in 548 calendar days of the Notice to Proceed. Other contractors may be working in the same area performing other work. The contractor shall execute work in a manner so as not to impede other contract work.

4. HOURS OF WORK: Refer to Specification 01 00 00 General Requirements.

5. WORKMANSHIP: All work under this contract shall conform to the standards of these specifications. The Contractor at no additional cost to the Government shall correct work not meeting these specifications. Work shall be accomplished by mechanics skilled in the trade.

6. DAILY PROGRESS REPORTS: The Contractor shall provide on a daily basis and no later than 9:00 AM, a progress report of work accomplished the previous day to COR Logan Dunn, located in Bldg. 34.

7. WORKING CONDITIONS: The buildings and the surrounding site areas will be occupied, and Government operations will continue on a normal, temporary, or restricted basis for the duration of the contract. The Contractor shall take all precautions to ensure that his operations are conducted in a manner so as not to interfere with the normal operation of surrounding facilities.

The Contractor shall execute work in a safe manner and shall not subject personnel to unsafe conditions. The Contractor shall provide safety barricades, devices, and equipment to protect personnel and property and repair damage caused by construction operations. Take all precautions to protect the building and its occupants during the construction period.

8. SITE VISIT: The Contractor should visit the site to determine the full extent of the work.

Failure to inspect the site will not constitute grounds for a claim after contract award. Visits to the site by Bidders may be made in accordance with what is listed in the solicitation and at the discretion of the Contracting Officer.

9. DISPOSAL: Disposal of materials removed under this contract at an approved disposal site in accordance with all local, state, and federal laws, regulations, and guidelines are the Contractor’s sole responsibility. The contractor shall adhere to all OSHA requirements concerning removal, transporting, and disposal of the material. The contractor shall provide records of receipts for all recycled and waste material to the COR including specific quantities for VA environmental records.

10. CLEAN-UP: The Contractor shall keep the area neat and tidy and free of debris at the end of each workday.

11. TEMPORARY FACILITIES: Temporary electrical power and water may be provided by the Government at no cost to the Contractor from existing lines and sources located at the building site. The characteristics and source locations may be verified by a visit to the site. The Contractor shall provide ample temporary storage shed space for materials requiring shelter from the weather, and security and safety protection. Storage facilities shall be located in the areas of the facility designated by the Contracting Officer’s Representative. Reference Specification Section 01 00 00, 1.19 Availability & Use of Utility Services for additional guidance on what would be an additional cost to the contractor.

12. SAFETY AND FIRE: Contractor must comply with all applicable city, county, state, and federal regulations / codes, and applicable OSHA standards project. Construction shall also comply with Infection Control Risk Assessment (ICRA), attached, and IC standards delineated in the specifications.

13. PERMITS: The Contractor shall be responsible for obtaining any licenses and permits and complying with any laws, codes, and regulations applicable to the execution of this work as required Federally and by the State of Texas.

14. WARRANTEE: The contractor shall warrantee work to be free of defects and workmanship for a period of 1 year from date of acceptance. Contractor shall provide a minimum one (1) certified year warranty, unless specified otherwise in the specs, from both the manufacturer and installer including parts and labor to include normal, premium or holidays hours. The Warranty period shall start on the date of Final Payment issued in IPPS from VA.

15. ACCEPTANCE: For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all the following:

a. The Contractor has demonstrated/ verified that the implemented ECMs function as intended at commissioning. All punch list items identified during the commissioning have been resolved.

b. The Contractor has provided O&M manuals.

c. The Contractor has provided Record drawings to include a CD with all as builds CAD files, PDF copes, one full set printed, and one half set printed.

16. STATEMENT OF WORK: The Contractor shall perform installation for all materials and components. This project includes upgrading the stations telecommunications system, including but not limited to:

Demolition Construction of new main computer building with possibility of future expansion of additional 5 floors.

Construction of new telecommunication rooms in existing spaces and as expansions of current buildings Installation of new fiber routes on campus including trenching and dirt work Installation of new data cable Demolition of existing data cable Installation of cable trays Installation of conduit and firestopping Installation of telecommunications enclosures Installation of security systems

Scope includes but is not limited to phasing for continued operation of surrounding departments through construction, demolition, and rebuild. Refer to contract documents for detailed scope information.

17. QUALITY ASSURANCE: The Contracting Officer reserves the right to conduct any inspections or perform any tests deemed necessary at any time during the execution of the contract to determine conformance with the requirements of theses specifications.

18. SUBMITTALS: Contractor shall provide with their quote manufacturer’s descriptive literature for items mentioned in the project package (STATEMENT OF WORK, SPECS, and DRAWINGS) with Data Sheets and/or Shop Drawings.

END OF SECTION