About this file

This attachment provides a transition detail between a concrete slab over steel deck and a prestressed concrete deck with a 2-inch topping for the federal contract opportunity to Expand SPS Minor Construction in Phoenix, Arizona. The detail calls for a drawing indicating an 8-inch prestressed concrete deck with a 2-inch concrete topping and notes that plans specify a concrete slab over steel deck installed by others. Bidders should provide a design showing the transition between the slab on metal deck and prestressed concrete deck with topping per the project requirements. The related federal opportunity is solicitation number 36C77623B0032 from the Department of Veterans Affairs Technology Acquisition Center Austin for minor construction expansion at the Phoenix location.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--Expand SPS Minor Construction - Phoenix AZ, newest first.
File Type Posted
Technical Questions and Answers - FINAL 4 - Volume 2.xlsx XLSX spreadsheet
36C77623B0032 0007.pdf PDF
Attachment - 20110426 Final IIA.pdf PDF
36C77623B0032 0006.pdf PDF
Technical Questions and Answers - FINAL.xlsx XLSX spreadsheet
Attachment - Deck to Wall Sketch.pdf PDF
Electrical_Dwgs Normal Essential Manhole.pdf PDF
36C77623B0032 0005.pdf PDF
644-235 Expand SPS Technical questions Response to question 59 LMF.pdf PDF
B34 As-Builts Combined.pdf PDF
VA Phoenix Basement Steam Supply.pptx PPTX presentation
S06 - 36C77623B0032 0004.pdf PDF
S06 - 36C77623B0032 0003.pdf PDF
S06 - 36C77623B0032 0002.pdf PDF
Amendment 002 - Attachment 02 - Site Visit Sign in Sheet - Page 2.pdf PDF
S06 - 36C77623B0032 0001.pdf PDF
Amendment 001 - Atatchment 01 - Site Visit Sign in Sheet - Page 1.pdf PDF
ATTACHMENT 5 - Construction Wage Rates - Maricopa 9-01-23.pdf PDF
ATTACHMENT 3 - GeoTech.pdf PDF
ATTACHMENT 2 - Drawings.pdf PDF
ATTACHMENT 6 - Site Visit Instructions.pdf PDF
ATTACHMENT 1 - Specifications.pdf PDF
36C77623B0032_1.docx DOCX document
ATTACHMENT 4 - Limitations on Subcontracting - Construction.docx DOCX document
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Vli104865 Image

Vli104865 Text Box SE103 indicates an 8” prestressed concrete deck with a 2” topping. In addition the plans call out for a concrete slab over steel deck by others. Please provide a transition detail between the slab on metal deck and the prestressed concrete deck with a 2” topping.