About this file

This Statement of Work outlines requirements for pallet rack inspection services at the Northeast Consolidated Mail Outpatient Pharmacy (CMOP). The VA is seeking an independent expert or engineer specializing in warehouse racking systems to perform facility-wide rack damage assessment, conduct staff training for monthly inspections, and complete necessary repairs in accordance with ANSI MH 16.1-2023 standards.

The project includes specific milestones and deliverables with a strict timeline: site assessment and training must begin within 30 days of award, repair work within 30 days, training plan delivery within 60 days, and all work completed within 180 days. Key deliverables include a progress schedule, damage assessment documentation with photos, training materials and attendance records, and a final requirements document detailing repairs completed. The work will be performed at the Chelmsford CMOP facility, managed by the Department of Veterans Affairs Veterans Health Administration Network 15.

View the file

Other files

File Type Posted
36C77025Q0066 0004.docx DOCX document
36C77025Q0066 0003.docx DOCX document
36C77025Q0066 0002.docx DOCX document
RFQ_36C77025Q0066 0001_Rack Insp Trg Rpr.docx DOCX document
Wage Determination_Middlesex County_Chelmsford CMOP_No 2005-2255 Rev 19_12-29-2015.txt TXT text file
Final SOW_761 Pallet racks inspection.doc DOC document
36C77025Q0066 0001.docx DOCX document
36C77025Q0066.docx DOCX document
P07_Wage Determination_Middlesex County_Chelmsford CMOP_No 2005-2255 Rev 19_12-29-2015.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Northeast Consolidated Mail Outpatient Pharmacy Statement of Work

Request to inspect pallet rack in facility 10/1/2024 Presented by:

Michael D. Graybeal Statement of work General Task Description

Rack damage must be assessed, and a facility wide rack inspection performed by an independent expert or engineer specializing in warehouse racking systems. CMOP staff (selected by facility) shall also be trained by the expert to conduct their own monthly rack inspections. Contractor to provide options and recommendations as applicable. Contractor to follow up with required repairs and ensure all racks are appropriately placarded IAW ANSI MH 16.1-2023.

Estimated Key Milestones

1. Formation of project team and virtual kick-off meeting.

2. Site visit scheduled.

3. Training plan and knowledge assessment developed.

4. Site visit completed.

5. Repair recommendations made.

6. Repairs made.

Key Deliverables

1. Planned Progress Schedule with associated resources.

2. Summary of data/information to be provided for the facility.

a. Summary of rack damage assessment with photos of damaged areas of the rack.

b. Copy of training plan and knowledge assessment tool with list of attendees.

c. Summary of repairs completed with corresponding photos.

3. Final requirements document and presentation to include:

a. Project summary and description of damaged racks with photos.

b. Training content and sign-in sheets

c. Project conclusion (description of repairs with corresponding photos) Facility on site rack assessment and training schedule within 30 days from award.

Schedule for follow-up rack repair within 30 days.

Draft training plan and knowledge assessment tool shall be delivered within 60 days from award.

All on-site assessments, training, and repairs completed within 180 days from award.

****The C&A requirements do not apply, and that a Security Accreditation Package is not required.

File details come from the government source that posted it. Updated .