This document is an amendment (0002) to a Request for Proposal (RFP) for a Firm Fixed Price contract for a Cost-Per-Patient-Reportable system to provide urinalysis laboratory services to the Department of Veterans Affairs' Veterans Integrated Service Network (VISN) 23.

The key changes in this amendment include:

  • Allowing offerors to minimize the need for dilutions and manual intervention to obtain accurate results, rather than requiring the ability to perform dilutions
  • Clarifying that the primary and backup urinalysis analyzers are not required to have matching technology or capabilities
  • Confirming that the title of the equipment will remain with the contractor, who must remove the equipment at the end of the contract
  • Denying the request to allow for annual contract price adjustments based on volume fluctuations The proposal due date remains August 30, 2024, with a question deadline of August 20, 2024. Offers must be emailed to the specified VA personnel.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

01 01

36C263-24-AP-0653

n/a

36C263

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

1303 5th St

Suite 300

Coralville IA 52241

36C263

Department of Veterans Affairs

NETWORK 23 CONTRACTING OFFICE

1303 5th St, Suite 300

Coralville IA 52241

To all Offerors/Bidders

36C26324R0135

08-11-2024

X

X X

Funding will be included per delivery order placed against

IDIQ.

X

Important: Offerors are required to acknowledge receipt of this RFQ Amendment 0002 by email to both joseph.bennett@va.gov and christi.melendez@va.gov buy closing date OR include a signed copy with offer.

This Amendment answers questions received from offerors in regards to the RFP 36C26324R0135.

This Amendment changes some language in the RFP. These changes are described on the Continuation Page below.

Attached is a revised RFP document. See text in BLUE highlight for text being deleted. See text in RED Font for text being added. These changes are the same as those described on the Continuation Page.

Offers are still due no later than 12:00 PM EDT, Friday, August 30, 2024.

We are aware that the period for questions actually closes 5:00 PM EDT Monday August 26, 2024.

This is an attempt to share the questions and answers we have at this point with participating offerors.

Joseph Bennett

Contract Officer

VA-VHA-RPOC-2024-0088

Continuation Page

The following are vendor questions we have received in regard to RFP 36C263240135.

VA responses to the questions are in RED font below each question.

1. Question: The B.2 Statement of Work section 4 Technical Specifications page 6 of 80 states offers must have “m. Ability to perform dilutions”. Because the requirement to make dilutions in Urinalysis is often a result of restrictive linearity limits and inability to eliminate interferences, would the VISN consider adding “Ability to minimize need for dilutions and manual intervention to obtain accurate results is preferred.” to this section?

Answer: The language was changed to:

m. Ability to perform dilutions or ability to minimize need for dilutions and manual intervention to obtain accurate results.

See page 6 for the revisions. Thank you for your question.

2. Question: The B.2 Statement of Work section 4 Technical Specifications page 6 of 80 states “o.

All known interferences must be listed” as it relates to results. Would the VISN consider adding “Preferred urinalysis solution provides interferences reducing technology.” and/or “Preferred urinalysis solutions must not introduce interfering fluids to samples that would contaminate the sample and preclude additional testing if needed.” to this section?

Answer: The VA will keep the language as it currently exists. No change.

Thank you for your question.

3. Question: The B.2 Statement of Work section 4 Technical Specifications page 7 of 80 states “q.

On board stability sufficient to accommodate both low and high volume use.” Does the VISN have a more specific preferred minimum onboard stability of Urinalysis chemistry strips?

Answer: No. The VA will keep the language at it currently exists. No Change.

4. Question: The B.2 Statement of Work section listing ITEMS AND PRICES on page 11 of the 80 lists for specific locations the need for a “back-up chemistry”. Is it preferred or required that chemistry analyzers acting as the primary or backup for all sites have matching technology and operation capabilities for standardization across the VISN?

Answer: Primary analyzers should be the same within the same Healthcare System, for example, NWIHCS which is comprised of Omaha, Grand Island, and Lincoln, or BHHCS which is comprised of Hot Springs and Fort Meade. Primary and backup analyzers are NOT required to be the same.

NWIHCS stands for: VA Nebraska Western-Iowa Healthcare System.

BHHCS stands for: VA Black Hills Healthcare System.

5. Question: C.1 52.212-4, section (n) Title on page 32 of 80 asks that if title of equipment is to remain with contractor, it must be specified in the contract. Because equipment is to only be utilized by the government to obtain reportable results and returned at the end of the contract, can you confirm the title of equipment will remain with the contractor?

Answer: Yes, we confirm the title of the equipment will remain with the contractor. The following language is added to B.2 STATEMENT OF WORK, paragraph 3. SCOPE:

Ownership of Equipment and Title to the equipment shall remain with the Contractor.

The Contractor, upon contract expiration, termination and/or replacement of equipment, shall remove the equipment. All accessories (unused consumables, etc.) furnished by the Contractor shall accompany the equipment when returned to the Contractor except when equipment is being replaced to maintain a functional system. The Contractor shall disconnect the analyzer (gas, water, air, etc.) and shall be responsible for all packing and shipping required to remove the analyzer.

See page 5 and 6.

6. Question: Is it agreeable to add language that would allow for an annual CPRR adjustment if agreed to by both parties should the volumes provided fluctuate by greater than +/-15% from those provided in provided volume estimates? Our volumes are ESTIMATES and provider driven.

Answer: The VA does not agree to add such language.

7. If a delayed response to questions, would a one-week extension to RFP response due date be considered?

Answer: The time and date for offers to be received was extended with Amendment 0001 to 12:00 PM EDT, Friday, August 30, 2024. This modification 0002 does not change that time and date. If an offeror requests an additional extension, they shall include a short explanation for why such an extension is necessary. All requests will be considered but will be granted at the discretion of the Contracting Officer.