This document contains responses to questions regarding a solicitation for a Multiple Award Task Order Contract for construction services. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 23 is seeking proposals for indefinite-delivery indefinite-quantity contracts valued between $2,000 to $10,000,000 for maintenance, repair, alteration, and new construction projects at VA medical centers in Iowa and Nebraska. The solicitation will be a total 100% set-aside for Service Disabled Veteran Owned Small Businesses. The initial period of performance is five years from date of award with a minimum of five contracts to be awarded. Offerors must be SDVOSB eligible, a small business for the assigned NAICS code, and listed as a verified SDVOSB in the VetBiz VIP database. Responses to technical questions were provided relating to drawings, specifications and other requirements.
36C26318R0687 0001 Responses to Questions 3.22.19 (2 pages).pdf
View the file
Other files
Show 40 more
Latest 50 of 84 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Responses to Questions/Clarifications as submitted verbatim through 3/22/19:
Q: Will additional drawings be posted in a forth coming amendment for the seed project under the solicitation in subject?
A: No additional drawings are being provided specifically for the seed project but see Attachment 11-- Revised 636-18-125 Drawings and attached Asbestos Survey’s for the project areas.
Q: Is the Attachment 1 – Subcontractor Information and Consent Form only to be included in the proposal if we are utilizing a Subcontractor/Teaming Partner’s projects in the Past Performance section?
Or is it still a requirement to include this even if we are utilizing our own past performance as Prime?
A: Attachment 1—Subcontractor Information and Consent Form is required if you are proposing a teaming partner/arrangement with a major subcontractor for the overall MATOC. The Government must have subcontractor/teaming partner consent to obtain performance information and contact references of the subcontractor and or teaming partner if you are proposing this type of an arrangement. If a Subcontractor teaming partner/arrangement is not used, then Attachment 1— Subcontractor Information and Consent Form is not required.
Q: RFI #1 – Section 09 06 00 of the specifications, as well as, the general scope of work refers the bidder to the project plans for the room finish schedule, however, no room finish schedule or finish floor plan is provided. Please provide a room finish schedule and finish floor plan designating where all specified finishes are to installed. (The “Finish Schedule” located in the Spec Section 09 60 00 does not specify locations for the listed material and neither the specifications nor the drawings indicate quantity or scale).
A: Locations shall be coordinated with the COR.
Q: RFI #2 – No sections or interior elevations are shown of the restrooms other than typical installations of fixtures. Please provide interior elevations and sections of the restrooms with room labels and view directions showing the planned design for the restroom layout including tile, fixture, casework, and partition installation.
A: Locations shall be coordinated with the COR.
Q: RFI #3 – No plans, elevations, sections, details or measurements are provided for the reception counters. Please provide applicable plans, elevations, sections, details, callouts, etc. showing heights, widths, depths, thicknesses, installation of applicable material, etc.
A: See Attachment 11--Revised 636-18-125 Drawings.
Q: RFI #4 – No Door Tags (Numbers) or Door/Hardware schedules are provided designating door/frame types, heights, widths, ratings, or hardware sets per door location. Please provide Door Tag Numbers designating the locations of the specified doors and please provide a corresponding door/hardware schedule designating door/frame types, heights, widths, ratings, or hardware sets per door location.
A: Sizes are shown on the plans. Types, ratings and hardware are described in the specifications.
Q: RFI #5 – No ceiling plans are provided showing specified ceiling material and location and number of new electrical fixtures, HVAC registers, or other ceiling utility. Please provide ceiling plans showing installation of all applicable materials, lighting fixtures, HVAC registers, ceiling utility (sprinkler heads if required), etc.
A: All ceiling fixtures, registers, etc. are to remain in-place. Where walls are removed, ceiling materials shall match existing.
Q: RFI #6 – No ceiling heights are provide for the restroom where complete demolition and installation is to occur. Please provide applicable ceiling heights for bidding and takeoff purposes.
A: Ceiling heights are approximately 9 feet.
Q: RFI #7 – No scales are provided on ANY of the provided drawings. Please provide scales on all drawings for bidding and takeoff purposes.
A: See Attachment 11--Revised 636-18-125 Drawings.
Q: RFI #8 – No MEP plans have been provided for the restrooms showing supply/returns, power, lights, and fixtures. Please provide MEP plans for the restrooms.
A: All ceiling fixtures, registers, etc. are to remain in-place.
Q: RFI #9 – No asbestos survey has been provided for the affected areas. Please provide.
A: See attached asbestos drawings.
Q: RFI # 10 – No asbestos drawings or quantities were provided for the affected areas. Please provide abatement drawing or quantities for affected areas.
A: See attached asbestos drawings.
Q: We respectfully submit for your consideration a request to approve products as an accepted substitute on VA NB Bldg 8 Restroom MOVE Clinic & Ultrasound Remodel IDIQ (19-585850) Toilet Compartments.
A: Manufacturer’s trade names and numbers used herein are only to identify colors, finishes, textures and patterns. Products of other manufacturer’s equivalent to colors, finishes, textures and patterns of manufacturers listed that meet requirements of technical specifications will be acceptable upon approval in writing by contracting officer for finish requirements. Substitution requests are not approved prior to award. After award, the contractor can submit a product via the submittal process, so it can be reviewed for conformance of the requirements of the specifications.