Questions and Answers.docx
DOCX document 15 KB Posted
- Attached to
- 6530--Project 405 CLC Activation; Patient Lifts
- Solicitation number
- 36C26221Q1195
About this file
This document outlines requirements for a federal contract to provide patient lift equipment and installation services to the VA Long Beach Healthcare System. The contractor will supply 74 ceiling lifts for patient bedrooms and bathrooms, 10 ceiling lifts for bathing suites, 10 bariatric ceiling lifts for patient bedrooms and baths, additional materials and components for 94 lifts, 94 sling kits, and training. Products must meet specified technical and safety standards. Delivery is required between October 1, 2021 and November 1, 2021 to the VA facility located in Long Beach, California. Installation will take place on site according to the schedule coordinated with the Contracting Officer Representative. The contractor must provide all tools, labor, and materials for assembly and installation, and properly dispose of waste. Training of VA staff must also be provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S0236C26221Q1195 0001.docx | DOCX document | |
| 36C26221Q1195_2.docx | DOCX document | |
| S02-Soliciation .pdf | ||
| 36C26221Q1195_1.docx | DOCX document | |
| ATTACHMENT A SOW.pdf | ||
| S02.pdf | ||
| 36C26221Q1195.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. The quantities of items in Attachment A differ from the Price/Cost Schedule in the solicitation. In Attachment A, Table 1, A1205B states 94, but on page 11 in the Salient Characteristics, it states 10. CLIN0004 from the Price/Cost Schedule states 1 EA. Can you please clarify the correct quantities?
The correct QTY is QTY 94
1. The delivery date in the solicitation states 90 days, but Attachment A states between 10/1/2021 and 11/1/2021. Can you please clarify the intended delivery date?
Project will commence 10/1, we will be flexible with project delivery dates as we understand construction times will be dependent upon project and engineering plans and deliverables.
1. The solicitation includes a 1100lb. weight limit as one of the Salient Characteristics, one that must be met by all equal product offers. We believe this requirement of 1100lbs. is specific to Guldmann and Guldmann alone. In order to allow Alliant and other potential companies a fair opportunity of submitting a fully compliant response, would you be willing to revise this requirement to 1000lbs.?
Yes that is acceptable.
1. There are salient characteristics for item number A1205C that are listed on pages 5-6, 7-8 as well as page 11 of the SOW. Can you please verify that these are all supposed to be for item number A1205C? Can you please also verify which set of salient characteristics we are supposed to use for the Sling Set?
The amendment posted was the most recent Solicitation and SOW, the previous ones should be ignored.
1. There are salient characteristics for item number A1025A on page 7 of the SOW, but that item is not listed in the Table on page 1, Item A1205A is listed instead. Can you please confirm which item number is correct?
The amendment posted was the most recent Solicitation and SOW, the previous ones should be ignored.