36C26220R0024-0002001.pdf
PDF Posted
- Attached to
- Contracted Residential Services at VAGLAHS FY20
- Solicitation number
- 36C26220R0024
About this file
36C26220R0024 0002 A BRIDGE HOME - BASELINE DRAFT - FINAL 11-18-19 (002).pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26220R0024-0002000.docx | DOCX document | |
| 36C26220R0024-0001000.docx | DOCX document | |
| 36C26220R0024-0001001.docx | DOCX document | |
| 36C26220R0024-001.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
# Activity ID Activity Name Duration Start Finish Total Float
1 A BRIDGE HOME SHELTER A BRIDGE HOME SHELTER - VA WEST LA 139 19-Aug-19 04-Feb-20 0 2 ADMINISTRATIVE MILESTOADMINISTRATIVE MILESTONES 139 19-Aug-19 04-Feb-20 0 3 100.SUM Notice to Proceed 0 19-Aug-19* 0 4 101.SUM Current CPM (WD'S) 139 19-Aug-19 04-Feb-20 0 5 102.SUM Current CPM (CD'S) 170 19-Aug-19 04-Feb-20 0 6 103.SUM FINAL COMPLETION 0 04-Feb-20 0 7 MOBMOB 6 19-Aug-19 24-Aug-19 3 8 110.MOB USA Dig Alert 1 19-Aug-19 19-Aug-19 3 9 111.MOB Asbestos / Lead Testing 2 20-Aug-19 21-Aug-19 3 10 112.MOB Cut / Cap Existing Utilities 3 22-Aug-19 24-Aug-19 3 11 DEMODEMO 17 26-Aug-19 14-Sep-19 29 12 120.DEMO Clear and Grub 7 26-Aug-19 03-Sep-19 3 13 121.DEMO SWPPP Implementation 2 04-Sep-19 05-Sep-19 11 14 122.DEMO Remove Existing Structures Show on CD-1.0 10 04-Sep-19 14-Sep-19 3 15 123.DEMO Protect in Place Shown on CD-1.0 10 04-Sep-19 14-Sep-19 29 16 SITE GRADINGSITE GRADING 10 16-Sep-19 26-Sep-19 3 17 130.GRD Remove / Replace for Building Foundations / Pad 10 16-Sep-19 26-Sep-19 3 18 UTILITIESUTILITIES 87 16-Sep-19 30-Dec-19 25 19 SANITARY SEWERSANITARY SEWER 74 27-Sep-19 26-Dec-19 28 20 140.SS Layout for SS 1 27-Sep-19 27-Sep-19 69
21 141.SS Trenching for SS 5 28-Sep-19 03-Oct-19 69 22 142.SS Bedding for SS 5 01-Oct-19 05-Oct-19 69 23 143.SS Piping for SS 5 07-Oct-19 11-Oct-19 69 24 144.SS Pressure Test 5 12-Oct-19 17-Oct-19 69 25 145.SS Backfill 5 18-Oct-19 23-Oct-19 69 26 146.SS Final Connection to SS 5 24-Oct-19 29-Oct-19 69 27 147.SS Drains and Cleanouts to Finish Elevations 5 30-Oct-19 04-Nov-19 69 28 CATCH BASINSCATCH BASINS 61 12-Oct-19 26-Dec-19 28 29 148.SS Stub Up for 12" Catch Basins (Item 24) 5 12-Oct-19 17-Oct-19 79 30 149.SS Catch Basins 5 20-Dec-19 26-Dec-19 28 31 STORM DRAINSTORM DRAIN 74 27-Sep-19 26-Dec-19 28 32 150.SD Layout / Pothole (As Needed) 1 27-Sep-19 27-Sep-19 23 33 151.SD Excavate 3 28-Sep-19 01-Oct-19 23 34 152.SD Construct Catch Basins (F/R/P/S) 3 02-Oct-19 04-Oct-19 23 35 153.SD Complete Excavation for Pipe Installation 3 05-Oct-19 08-Oct-19 23 36 154.SD Bedding (Sand) 3 09-Oct-19 11-Oct-19 23 37 155.SD Piping 5 12-Oct-19 17-Oct-19 23 38 156.SD Testing as Needed 2 18-Oct-19 19-Oct-19 23 39 157.SD Backfill (Sand / Native Soil) 2 21-Oct-19 22-Oct-19 23
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
04-Feb-20, A BRIDGE HOME SHELTER - VA WEST LA
04-Feb-20, ADMINISTRATIVE MILESTONES
Notice to Proceed
FINAL COMPLETION
24-Aug-19, MOB
USA Dig Alert
Asbestos / Lead Testing
Cut / Cap Existing Utilities
14-Sep-19, DEMO
Clear and Grub
SWPPP Implementation
Remove Existing Structures Show on CD-1.0
Protect in Place Shown on CD-1.0
26-Sep-19, SITE GRADING
Remove / Replace for Building Foundations / Pad
30-Dec-19, UTILITIES
26-Dec-19, SANITARY SEWER
Layout for SS
Trenching for SS
Bedding for SS
Piping for SS
Pressure Test
Backfill
Final Connection to SS
Drains and Cleanouts to Finish Elevations
26-Dec-19, CATCH BASINS
Stub Up for 12" Catch Basins (Item 24)
Catch Basins
26-Dec-19, STORM DRAIN
Layout / Pothole (As Needed)
Excavate
Construct Catch Basins (F/R/P/S)
Complete Excavation for Pipe Installation
Bedding (Sand)
Piping
Testing as Needed
Backfill (Sand / Native Soil)
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19 Run Date: 17-Nov-19 / 20:42
40 CATCH BASINS (C-5.1)CATCH BASINS (C-5.1) 56 18-Oct-19 26-Dec-19 28 41 158.SD Stub Up for 24" Catch Basins (Item 2) 5 18-Oct-19 23-Oct-19 74 42 159.SD Catch Basins 5 20-Dec-19 26-Dec-19 28 43 FIRE WATERFIRE WATER 28 18-Nov-19 21-Dec-19 31 44 160.FW Fire Water Complete Design / Submit to VA Fire Marshal 15 18-Nov-19* 06-Dec-19 31 45 161.FW Locate Existing 6" FW Line 1 07-Dec-19* 07-Dec-19 31 46 162.FW Excavate 3 09-Dec-19 11-Dec-19 32 47 163.FW Install Back Flow Preventer System 4 09-Dec-19 12-Dec-19 31 48 164.FW Bedding 2 13-Dec-19 14-Dec-19 31 49 165.FW Piping / Stub Up to Building Locations 2 16-Dec-19 17-Dec-19 31 50 166.FW Pressure Test 1 18-Dec-19 18-Dec-19 31 51 167.FW Backfill (Sand and Native) 1 19-Dec-19 19-Dec-19 31 52 168.FW Cathodic Protection (After Pressure Test) 2 20-Dec-19 21-Dec-19 31 53 DOMESTIC WATER (3")DOMESTIC WATER (3") 21 16-Sep-19 09-Oct-19 46 54 170.DW3 Pothole / Verify Existing on Site DW 1 16-Sep-19 16-Sep-19 46 55 171.DW3 Make Connection (Provide Reducing Fittings Couplings as Needed) 3 17-Sep-19 19-Sep-19 46 56 172.DW3 Excavation for Installation of Piping 3 20-Sep-19 23-Sep-19 46 57 173.DW3 Bedding 3 24-Sep-19 26-Sep-19 46 58 174.DW3 Piping (Installation with Appropriate Stub Ups (Hose Bibs / Water to Bldg) 4 27-Sep-19 01-Oct-19 46 59 175.DW3 Testing 2 02-Oct-19 03-Oct-19 46 60 176.DW3 Thrust Blocks 3 04-Oct-19 07-Oct-19 46 61 177.DW3 Backfill (Sand/Native Soil) 2 08-Oct-19 09-Oct-19 46 62 DOMESTIC WATER (8")DOMESTIC WATER (8") 21 16-Sep-19 09-Oct-19 34 63 180.DW8 Pothole / Verify Existing on Site 8 DW 1 16-Sep-19 16-Sep-19 34 64 181.DW8 Install 8" Gate Valve at 2 Locations (North End and South End) 3 17-Sep-19 19-Sep-19 34 65 182.DW8 Excavate 3 20-Sep-19 23-Sep-19 34 66 183.DW8 Bedding (Sand) 3 24-Sep-19 26-Sep-19 34 67 184.DW8 Piping 4 27-Sep-19 01-Oct-19 34 68 185.DW8 Testing 2 02-Oct-19 03-Oct-19 34 69 186.DW8 Thrust Blocks (6 locations) 3 04-Oct-19 07-Oct-19 34 70 187.DW8 Backfill (Sand/Native Soil) 2 08-Oct-19 09-Oct-19 34 71 ELECTRICALELECTRICAL 38 16-Sep-19 29-Oct-19 29 72 188.ELEC Pothole and Intercept (E) Manhole #044 1 16-Sep-19 16-Sep-19 29 73 189.ELEC Core / Access Existing Conduit 1 17-Sep-19 17-Sep-19 29 74 190.ELEC Trenching to New Transformer Pad (Stub In / Stub Out) 2 18-Sep-19 19-Sep-19 29 75 191.ELEC Trench Transformer Pad to Switchboard (SB2) (Stub In / Stub Out) 2 20-Sep-19 21-Sep-19 29 76 192.ELEC Trench from Switchboard to Pull Box 1 of 3 2 23-Sep-19 24-Sep-19 29 77 193.ELEC Install Pre-Cast Pull Box (At 3 Locations) 2 25-Sep-19 26-Sep-19 29 78 194.ELEC Trench for Conduit to Hygiene Trailer #2 (L2A) (Stub Up) 2 27-Sep-19 28-Sep-19 29
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
26-Dec-19, CATCH BASINS (C-5.1)
Stub Up for 24" Catch Basins (Item 2)
Catch Basins
21-Dec-19, FIRE WATER
Fire Water Complete Design / Submit to VA Fire Marshal
Locate Existing 6" FW Line
Excavate
Install Back Flow Preventer System
Bedding
Piping / Stub Up to Building Locations
Pressure Test
Backfill (Sand and Native)
Cathodic Protection (After Pressure Test)
09-Oct-19, DOMESTIC WATER (3")
Pothole / Verify Existing on Site DW
Make Connection (Provide Reducing Fittings Couplings as Needed)
Excavation for Installation of Piping
Bedding
Piping (Installation with Appropriate Stub Ups (Hose Bibs / Water to Bldg)
Testing
Thrust Blocks
Backfill (Sand/Native Soil)
09-Oct-19, DOMESTIC WATER (8")
Pothole / Verify Existing on Site 8 DW
Install 8" Gate Valve at 2 Locations (North End and South End)
Excavate
Bedding (Sand)
Piping
Testing
Thrust Blocks (6 locations)
Backfill (Sand/Native Soil)
29-Oct-19, ELECTRICAL
Pothole and Intercept (E) Manhole #044
Core / Access Existing Conduit
Trenching to New Transformer Pad (Stub In / Stub Out)
Trench Transformer Pad to Switchboard (SB2) (Stub In / Stub Out)
Trench from Switchboard to Pull Box 1 of 3
Install Pre-Cast Pull Box (At 3 Locations)
Trench for Conduit to Hygiene Trailer #2 (L2A) (Stub Up)
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
79 195.ELEC Trench to Pull Box (Covered Dinning) - Conduit to Covered Dining (Stub Up) 2 30-Sep-19 01-Oct-19 29 80 196.ELEC Trench to Pull Box #3 at Hygiene Trailer #1 (Stub Up) 2 02-Oct-19 03-Oct-19 29 81 197.ELEC Conduit to Panel L1A (Stub In / Stub Out) 2 04-Oct-19 05-Oct-19 29 82 198.ELEC Conduit Run to Switchboard (SB1) (Stub In / Stub Out) 2 07-Oct-19 08-Oct-19 29 83 199.ELEC Concrete Encasement 2 09-Oct-19 10-Oct-19 29 84 200.ELEC Backfill 1 11-Oct-19 11-Oct-19 29 85 201.ELEC F / R / P for Transformer Pad (Dtl 4 - E01-01) 5 12-Oct-19 17-Oct-19 29 86 202.ELEC F / R / P for SB2 (Dtl 3 - E01-01) 5 18-Oct-19 23-Oct-19 29 87 203.ELEC F / R / P for SB1 (Dtl 2 - E01-01) 5 24-Oct-19 29-Oct-19 29 88 MECHANICAL #1MECHANICAL #1 18 09-Dec-19 30-Dec-19 25 89 EXTERIOREXTERIOR 18 09-Dec-19 30-Dec-19 25 90 210.MECH.EXT F / R / P Concrete Pads for HVAC x 2 5 09-Dec-19* 13-Dec-19 25 91 212.MECH.EXT Electrical / Disconnects x 2 3 14-Dec-19 17-Dec-19 25 92 211.MECH.EXT F / R / P Service Pad for CU (#14) x 1 5 14-Dec-19 19-Dec-19 31 93 213.MECH.EXT Installation of HVAC Units x 2 (HP1 through HP4) with Mounted Power Exhau 3 18-Dec-19 20-Dec-19 25 94 214.MECH.EXT Rigid Conduit from Unit Into Building 1 21-Dec-19 21-Dec-19 25 95 215.MECH.EXT Return Grills(#1) / Penetration (#5) 2 23-Dec-19 24-Dec-19 25 96 216.MECH.EXT Drain Lines to Drywell (#4) 2 26-Dec-19 27-Dec-19 25 97 217.MECH.EXT Drywell Installation (#6) 2 28-Dec-19 30-Dec-19 25 98 MECHANICAL #2MECHANICAL #2 18 09-Dec-19 30-Dec-19 25 99 EXTERIOREXTERIOR 18 09-Dec-19 30-Dec-19 25 100 220.MECH.EXT F / R / P Concrete Pads for HVAC x 2 *start 12/9 to 1/10 5 09-Dec-19 13-Dec-19 25 101 222.MECH.EXT Electrical / Disconnects x 2 3 14-Dec-19 17-Dec-19 25 102 221.MECH.EXT F / R / P Service Pad for CU (#14) x 1 5 14-Dec-19 19-Dec-19 31 103 223.MECH.EXT Installation of HVAC Units x 2 (HP1 through HP4) with Mounted Power Exhau 3 18-Dec-19 20-Dec-19 25 104 224.MECH.EXT Rigid Conduit from Unit Into Building 1 21-Dec-19 21-Dec-19 25 105 225.MECH.EXT Return Grills(#1) / Penetration (#5) 2 23-Dec-19 24-Dec-19 25 106 226.MECH.EXT Drain Lines to Drywell (#4) 2 26-Dec-19 27-Dec-19 25 107 227.MECH.EXT Drywell Installation (#6) 2 28-Dec-19 30-Dec-19 25 108 SPRUNG TENT STRUCTURSPRUNG TENT STRUCTURE #1 (EAST) 102 27-Sep-19 30-Jan-20 0 109 STRUCTURESTRUCTURE 102 27-Sep-19 30-Jan-20 0 110 U/G MEPFU/G MEPF 9 27-Sep-19 07-Oct-19 3 111 230.SPRNG1 U/G MEPF Backfill 9 27-Sep-19 07-Oct-19 3 112 FOOTINGSFOOTINGS 23 08-Oct-19 02-Nov-19 3 113 231.SPRNG1 Excavate & Soil Test (Proof Test) 2 08-Oct-19 09-Oct-19 3 114 232.SPRNG1 Form for Grade Footing 10 10-Oct-19 21-Oct-19 3 115 233.SPRNG1 Place Reinforcement for Grade Beam Footings 5 22-Oct-19 26-Oct-19 3 116 234.SPRNG1 Bolt Templates 2 28-Oct-19 29-Oct-19 3 117 235.SPRNG1 Place Concrete for Foundations 1 30-Oct-19 30-Oct-19 3
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Trench to Pull Box (Covered Dinning) - Conduit to Covered Dining (Stub Up)
Trench to Pull Box #3 at Hygiene Trailer #1 (Stub Up)
Conduit to Panel L1A (Stub In / Stub Out)
Conduit Run to Switchboard (SB1) (Stub In / Stub Out)
Concrete Encasement
Backfill
F / R / P for Transformer Pad (Dtl 4 - E01-01)
F / R / P for SB2 (Dtl 3 - E01-01)
F / R / P for SB1 (Dtl 2 - E01-01)
30-Dec-19, MECHANICAL #1
30-Dec-19, EXTERIOR
F / R / P Concrete Pads for HVAC x 2
Electrical / Disconnects x 2
F / R / P Service Pad for CU (#14) x 1
Installation of HVAC Units x 2 (HP1 through HP4) with Mounted Power Exhaust
Rigid Conduit from Unit Into Building
Return Grills(#1) / Penetration (#5)
Drain Lines to Drywell (#4)
Drywell Installation (#6)
30-Dec-19, MECHANICAL #2
30-Dec-19, EXTERIOR
F / R / P Concrete Pads for HVAC x 2 *start 12/9 to 1/10
Electrical / Disconnects x 2
F / R / P Service Pad for CU (#14) x 1
Installation of HVAC Units x 2 (HP1 through HP4) with Mounted Power Exhaust
Rigid Conduit from Unit Into Building
Return Grills(#1) / Penetration (#5)
Drain Lines to Drywell (#4)
Drywell Installation (#6)
30-Jan-20, SPRUNG TENT STRUCTURE #1 (EAST)
30-Jan-20, STRUCTURE
07-Oct-19, U/G MEPF
U/G MEPF Backfill
02-Nov-19, FOOTINGS
Excavate & Soil Test (Proof Test)
Form for Grade Footing
Place Reinforcement for Grade Beam Footings
Bolt Templates
Place Concrete for Foundations
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
118 236.SPRNG1 Strip and Backfill 1 31-Oct-19 31-Oct-19 3 119 237.SPRNG1 Waterproofing 2 01-Nov-19 02-Nov-19 3 120 SLAB ON GRADE POUR #SLAB ON GRADE POUR #1 / PARTITION FOUNDATIONS 15 04-Nov-19 21-Nov-19 3 121 240.SPRNG1 U/G Mechanical / Electrical 2 04-Nov-19 05-Nov-19 3 122 241.SPRNG1 Excavate / Trench for Partitions Walls 2 06-Nov-19 07-Nov-19 3 123 242.SPRNG1 Clean Aggregate Base (4 Inches) (Entire Area) 2 08-Nov-19 09-Nov-19 3 124 243.SPRNG1 Vapor Barrier (Entire Area) 4 12-Nov-19 15-Nov-19 3 125 244.SPRNG1 F / R / P for Partition Walls 4 16-Nov-19 20-Nov-19 3 126 245.SPRNG1 F / R / P for SOG (Control Joints) 4 16-Nov-19 20-Nov-19 3 127 246.SPRNG1 Strip SOG 1 21-Nov-19 21-Nov-19 3 128 SLAB ON GRADE POUR #SLAB ON GRADE POUR #2 / PARTITION FOUNDATIONS 7 22-Nov-19 02-Dec-19 3 129 247.SPRNG1 F / R / P for Partition Walls 2 22-Nov-19 23-Nov-19 3 130 248.SPRNG1 Flush Floor Box 2 22-Nov-19 23-Nov-19 3 131 249.SPRNG1 F / R / P for SOG (Control Joints) 2 25-Nov-19 26-Nov-19 3 132 250.SPRNG1 Strip SOG 1 02-Dec-19 02-Dec-19 3 133 TENT ERECTION / BUILDOTENT ERECTION / BUILDOUT 43 09-Dec-19 30-Jan-20 0 134 260.SPRNG1 Inventory Structure / Tools 1 09-Dec-19 09-Dec-19 5 135 261.SPRNG1 Splice Beams Into Arches 1 10-Dec-19 10-Dec-19 5 136 262.SPRNG1 Stand Arches 1 11-Dec-19 11-Dec-19 5 137 263.SPRNG1 Install Purlins 1 12-Dec-19 12-Dec-19 5 138 264.SPRNG1 Repeat Arch / Purlin 2 13-Dec-19 14-Dec-19 5 139 265.SPRNG1 Install Membrane Center Panel 1 16-Dec-19 16-Dec-19 5 140 266.SPRNG1 Install Remaining Membrane 2 17-Dec-19 18-Dec-19 5 141 267.SPRNG1 Electrical (By Others) 5 17-Dec-19 21-Dec-19 5 142 268.SPRNG1 Install Insulation 2 30-Dec-19 31-Dec-19 0 143 269.SPRNG1 Tape Insulation 3 30-Dec-19 02-Jan-20 0 144 270.SPRNG1 Install Vent Frames 1 31-Dec-19 31-Dec-19 0 145 271.SPRNG1 Install Liners 2 02-Jan-20 03-Jan-20 0 146 272.SPRNG1 Tension Structure 2 03-Jan-20 04-Jan-20 0 147 273.SPRNG1 Vents / Windows 1 06-Jan-20 06-Jan-20 0 148 274.SPRNG1 Install End Walls 1 06-Jan-20 06-Jan-20 2 149 275.SPRNG1 Trim and Seal Sidewalls 1 07-Jan-20 07-Jan-20 0 150 277.SPRNG1 Install End Walls (By Others) 2 07-Jan-20 08-Jan-20 0 151 278.SPRNG1 Fire Sprinkler (Interior - Riser / Piping / Testing) 5 07-Jan-20 11-Jan-20 0 152 279.SPRNG1 Insulation and Tape Endwalls 1 09-Jan-20 09-Jan-20 0 153 280.SPRNG1 Install Endwall Liner 1 10-Jan-20 10-Jan-20 0 154 281.SPRNG1 Tension Endwalls 1 10-Jan-20 10-Jan-20 0 155 282.SPRNG1 Install Doors and Windows 1 10-Jan-20 10-Jan-20* 0 156 283.SPRNG1 Fire Sprinkler (Exterior Connections) 5 13-Jan-20 17-Jan-20 0
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Strip and Backfill
Waterproofing
21-Nov-19, SLAB ON GRADE POUR #1 / PARTITION FOUNDATIONS
U/G Mechanical / Electrical
Excavate / Trench for Partitions Walls
Clean Aggregate Base (4 Inches) (Entire Area)
Vapor Barrier (Entire Area)
F / R / P for Partition Walls
F / R / P for SOG (Control Joints)
Strip SOG
02-Dec-19, SLAB ON GRADE POUR #2 / PARTITION FOUNDATIONS
F / R / P for Partition Walls
Flush Floor Box
F / R / P for SOG (Control Joints)
Strip SOG
30-Jan-20, TENT ERECTION / BUILDOUT
Inventory Structure / Tools
Splice Beams Into Arches
Stand Arches
Install Purlins
Repeat Arch / Purlin
Install Membrane Center Panel
Install Remaining Membrane
Electrical (By Others)
Install Insulation
Tape Insulation
Install Vent Frames
Install Liners
Tension Structure
Vents / Windows
Install End Walls
Trim and Seal Sidewalls
Install End Walls (By Others)
Fire Sprinkler (Interior - Riser / Piping / Testing)
Insulation and Tape Endwalls
Install Endwall Liner
Tension Endwalls
Install Doors and Windows
Fire Sprinkler (Exterior Connections)
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
157 284.SPRNG1 Lighting 6 18-Jan-20 25-Jan-20 0 158 285.SPRNG1 Mechanical 4 27-Jan-20 30-Jan-20 0 159 286.SPRNG1 Fire Alarm 4 27-Jan-20 30-Jan-20 0 160 BUILDOUTBUILDOUT 19 19-Dec-19 11-Jan-20 15 161 A101 - CASE MANAGERA101 - CASE MANAGER 19 19-Dec-19 11-Jan-20 15 162 290.A101 Layout Walls 1 19-Dec-19 19-Dec-19 15 163 291.A101 Frame Walls 2 20-Dec-19 21-Dec-19 15 164 292.A101 Door Frames 1 23-Dec-19 23-Dec-19 15 165 293.A101 Windows 1 24-Dec-19 24-Dec-19 15 166 294.A101 Overhead MEPF 2 26-Dec-19 27-Dec-19 15 167 295.A101 In-Wall MEP 2 28-Dec-19 30-Dec-19 15 168 296.A101 Devices in Ceilings 2 28-Dec-19 30-Dec-19 15 169 297.A101 Lights 1 31-Dec-19 31-Dec-19 23 170 298.A101 Drywall Ceilings 2 31-Dec-19 02-Jan-20 15 171 299.A101 Drywall 2 31-Dec-19 02-Jan-20 15 172 300.A101 Tape & Finish 2 03-Jan-20 04-Jan-20 15 173 301.A101 Tape & Finish Ceilings 2 03-Jan-20 04-Jan-20 15 174 302.A101 Paint 2 06-Jan-20 07-Jan-20 15 175 303.A101 Doors & Hardware 1 08-Jan-20 08-Jan-20 15 176 304.A101 Flooring 2 09-Jan-20 10-Jan-20 15 177 305.A101 Punchlist 1 11-Jan-20 11-Jan-20 15 178 A102 - LOUNGEA102 - LOUNGE 18 19-Dec-19 10-Jan-20 16 179 310.A102 Layout Walls 1 19-Dec-19 19-Dec-19 16 180 311.A102 Frame Walls 2 20-Dec-19 21-Dec-19 16 181 312.A102 Door Frames 1 23-Dec-19 23-Dec-19 16 182 313.A102 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 183 314.A102 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 184 315.A102 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 185 316.A102 Lights 1 30-Dec-19 30-Dec-19 24 186 317.A102 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 187 318.A102 Drywall 2 30-Dec-19 31-Dec-19 16 188 319.A102 Tape & Finish 2 02-Jan-20 03-Jan-20 16 189 320.A102 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 190 321.A102 Paint 2 04-Jan-20 06-Jan-20 16 191 322.A102 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 192 323.A102 Flooring 2 08-Jan-20 09-Jan-20 16 193 324.A102 Punchlist 1 10-Jan-20 10-Jan-20 16 194 A103 - CASE MANAGERA103 - CASE MANAGER 19 19-Dec-19 11-Jan-20 15 195 330.A103 Layout Walls 1 19-Dec-19 19-Dec-19 15
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Lighting
Mechanical
Fire Alarm
11-Jan-20, BUILDOUT
11-Jan-20, A101 - CASE MANAGER
Layout Walls
Frame Walls
Door Frames
Windows
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, A102 - LOUNGE
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
11-Jan-20, A103 - CASE MANAGER
Layout Walls
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
196 331.A103 Frame Walls 2 20-Dec-19 21-Dec-19 15 197 332.A103 Door Frames 1 23-Dec-19 23-Dec-19 15 198 333.A103 Windows 1 24-Dec-19 24-Dec-19 15 199 334.A103 Overhead MEPF 2 26-Dec-19 27-Dec-19 15 200 335.A103 In-Wall MEP 2 28-Dec-19 30-Dec-19 15 201 336.A103 Devices in Ceilings 2 28-Dec-19 30-Dec-19 15 202 337.A103 Lights 1 31-Dec-19 31-Dec-19 23 203 338.A103 Drywall Ceilings 2 31-Dec-19 02-Jan-20 15 204 339.A103 Drywall 2 31-Dec-19 02-Jan-20 15 205 340.A103 Tape & Finish 2 03-Jan-20 04-Jan-20 15 206 341.A103 Tape & Finish Ceilings 2 03-Jan-20 04-Jan-20 15 207 342.A103 Paint 2 06-Jan-20 07-Jan-20 15 208 343.A103 Doors & Hardware 1 08-Jan-20 08-Jan-20 15 209 344.A103 Flooring 2 09-Jan-20 10-Jan-20 15 210 345.A103 Punchlist 1 11-Jan-20 11-Jan-20 15 211 A104 - MEDSA104 - MEDS 18 19-Dec-19 10-Jan-20 16 212 350.A104 Layout Walls 1 19-Dec-19 19-Dec-19 16 213 351.A104 Frame Walls 2 20-Dec-19 21-Dec-19 16 214 352.A104 Door Frames 1 23-Dec-19 23-Dec-19 16 215 353.A104 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 216 354.A104 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 217 355.A104 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 218 356.A104 Lights 1 30-Dec-19 30-Dec-19 24 219 357.A104 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 220 358.A104 Drywall 2 30-Dec-19 31-Dec-19 16 221 359.A104 Tape & Finish 2 02-Jan-20 03-Jan-20 16 222 360.A104 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 223 361.A104 Paint 2 04-Jan-20 06-Jan-20 16 224 362.A104 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 225 363.A104 Flooring 2 08-Jan-20 09-Jan-20 16 226 364.A104 Punchlist 1 10-Jan-20 10-Jan-20 16 227 A105 - JANITORA105 - JANITOR 18 19-Dec-19 10-Jan-20 16 228 370.A105 Layout Walls 1 19-Dec-19 19-Dec-19 16 229 371.A105 Frame Walls 2 20-Dec-19 21-Dec-19 16 230 372.A105 Door Frames 1 23-Dec-19 23-Dec-19 16 231 373.A105 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 232 374.A105 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 233 375.A105 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 234 376.A105 Lights 1 30-Dec-19 30-Dec-19 24
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Frame Walls
Door Frames
Windows
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, A104 - MEDS
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, A105 - JANITOR
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
235 377.A105 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 236 378.A105 Drywall 2 30-Dec-19 31-Dec-19 16 237 379.A105 Tape & Finish 2 02-Jan-20 03-Jan-20 16 238 380.A105 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 239 381.A105 Paint 2 04-Jan-20 06-Jan-20 16 240 382.A105 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 241 383.A105 Flooring 2 08-Jan-20 09-Jan-20 16 242 384.A105 Punchlist 1 10-Jan-20 10-Jan-20 16 243 A106 - STORAGEA106 - STORAGE 18 19-Dec-19 10-Jan-20 16 244 390.A106 Layout Walls 1 19-Dec-19 19-Dec-19 16 245 391.A106 Frame Walls 2 20-Dec-19 21-Dec-19 16 246 392.A106 Door Frames 1 23-Dec-19 23-Dec-19 16 247 393.A106 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 248 394.A106 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 249 395.A106 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 250 396.A106 Lights 1 30-Dec-19 30-Dec-19 24 251 397.A106 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 252 398.A106 Drywall 2 30-Dec-19 31-Dec-19 16 253 399.A106 Tape & Finish 2 02-Jan-20 03-Jan-20 16 254 400.A106 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 255 401.A106 Paint 2 04-Jan-20 06-Jan-20 16 256 402.A106 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 257 403.A106 Flooring 2 08-Jan-20 09-Jan-20 16 258 404.A106 Punchlist 1 10-Jan-20 10-Jan-20 16 259 STAIRS / RAMPSSTAIRS / RAMPS 15 21-Dec-19 09-Jan-20 17 260 410.STR.RMPS.1 Stairs 5 21-Dec-19 27-Dec-19 17 261 411.STR.RMPS.1 Ramps 5 28-Dec-19 03-Jan-20 17 262 412.STR.RMPS.1 Handrails / Core 5 04-Jan-20 09-Jan-20 17 263 SPRUNG TENT STRUCTURSPRUNG TENT STRUCTURE #2 (WEST) 102 27-Sep-19 30-Jan-20 0 264 STRUCTURESTRUCTURE 102 27-Sep-19 30-Jan-20 0 265 U/G MEPFU/G MEPF 9 27-Sep-19 07-Oct-19 35 266 420.SPRNG2 U/G Plumbing 9 27-Sep-19 07-Oct-19 35 267 FOOTINGSFOOTINGS 23 08-Oct-19 02-Nov-19 35 268 421.SPRNG2 Excavate & Soil Test (Proof Test) 2 08-Oct-19 09-Oct-19 35 269 422.SPRNG2 Form for Grade Footing 10 10-Oct-19 21-Oct-19 35 270 423.SPRNG2 Place Reinforcement for Grade Beam Footings 5 22-Oct-19 26-Oct-19 35
271 424.SPRNG2 Bolt Templates 2 28-Oct-19 29-Oct-19 35 272 425.SPRNG2 Place Concrete for Foundations 1 30-Oct-19 30-Oct-19 35
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, A106 - STORAGE
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
09-Jan-20, STAIRS / RAMPS
Stairs
Ramps
Handrails / Core
30-Jan-20, SPRUNG TENT STRUCTURE #2 (WEST)
30-Jan-20, STRUCTURE
07-Oct-19, U/G MEPF
U/G Plumbing
02-Nov-19, FOOTINGS
Excavate & Soil Test (Proof Test)
Form for Grade Footing
Place Reinforcement for Grade Beam Footings
Bolt Templates
Place Concrete for Foundations
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
273 426.SPRNG2 Strip and Backfill 1 31-Oct-19 31-Oct-19 35 274 427.SPRNG2 Verify Waterproofing 2 01-Nov-19 02-Nov-19 35 275 SLAB ON GRADE POUR #SLAB ON GRADE POUR #1 / PARTITION FOUNDATIONS 15 04-Nov-19 21-Nov-19 35 276 430.SPRNG2 U/G Mechanical / Electrical 2 04-Nov-19 05-Nov-19 35 277 431.SPRNG2 Excavate / Trench for Partitions Walls 2 06-Nov-19 07-Nov-19 35 278 432.SPRNG2 Clean Aggregate Base (4 Inches) (Entire Area) 2 08-Nov-19 09-Nov-19 35 279 433.SPRNG2 Vapor Barrier (Entire Area) 4 12-Nov-19 15-Nov-19 35 280 434.SPRNG2 F / R / P for Partition Walls 4 16-Nov-19 20-Nov-19 35 281 435.SPRNG2 F / R / P for SOG (Control Joints) 4 16-Nov-19 20-Nov-19 35 282 436.SPRNG2 Strip SOG 1 21-Nov-19 21-Nov-19 35 283 SLAB ON GRADE POUR #SLAB ON GRADE POUR #2 / PARTITION FOUNDATIONS 5 22-Nov-19 27-Nov-19 35 284 437.SPRNG2 F / R / P for Partition Walls 2 22-Nov-19 23-Nov-19 35 285 438.SPRNG2 Flush Floor Box 2 22-Nov-19 23-Nov-19 37 286 439.SPRNG2 F / R / P for SOG (Control Joints) 2 25-Nov-19 26-Nov-19 35 287 440.SPRNG2 Strip SOG 1 27-Nov-19 27-Nov-19 35 288 TENT ERECTION / BUILDOTENT ERECTION / BUILDOUT 43 09-Dec-19 30-Jan-20 0 289 450.SPRNG2 Inventory Structure / Tools 1 09-Dec-19 09-Dec-19 5 290 451.SPRNG2 Splice Beams Into Arches 1 10-Dec-19 10-Dec-19 5 291 452.SPRNG2 Stand Arches 1 11-Dec-19 11-Dec-19 5 292 453.SPRNG2 Install Purlins 1 12-Dec-19 12-Dec-19 5 293 454.SPRNG2 Repeat Arch / Purlin 2 13-Dec-19 14-Dec-19 5 294 455.SPRNG2 Install Membrane Center Panel 1 16-Dec-19 16-Dec-19 5 295 456.SPRNG2 Install Remaining Membrane 2 17-Dec-19 18-Dec-19 5 296 457.SPRNG2 Electrical (By Others) 5 17-Dec-19 21-Dec-19 5 297 458.SPRNG2 Install Insulation 2 30-Dec-19 31-Dec-19 0 298 459.SPRNG2 Tape Insulation 3 30-Dec-19 02-Jan-20 0 299 460.SPRNG2 Install Vent Frames 1 31-Dec-19 31-Dec-19 0 300 461.SPRNG2 Install Liners 2 02-Jan-20 03-Jan-20 0 301 462.SPRNG2 Tension Structure 2 03-Jan-20 04-Jan-20 0 302 463.SPRNG2 Vents / Windows 1 06-Jan-20 06-Jan-20 0 303 464.SPRNG2 Install End Walls 1 06-Jan-20 06-Jan-20 3 304 465.SPRNG2 Trim and Seal Sidewalls 1 07-Jan-20 07-Jan-20 0 305 467.SPRNG2 Install End Walls (By Others) 2 07-Jan-20 08-Jan-20 0 306 466.SPRNG2 Fire Sprinkler (Interior - Riser / Piping / Testing) 5 07-Jan-20 11-Jan-20 0 307 468.SPRNG2 Insulation and Tape Endwalls 1 09-Jan-20 09-Jan-20 0 308 469.SPRNG2 Install Endwall Liner 1 10-Jan-20 10-Jan-20 0 309 470.SPRNG2 Tension Endwalls 1 10-Jan-20 10-Jan-20 0 310 471.SPRNG2 Install Doors and Windows 1 10-Jan-20 10-Jan-20* 0 311 472.SPRNG2 Fire Sprinkler (Exterior Connections) 5 13-Jan-20 17-Jan-20 0
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Strip and Backfill
Verify Waterproofing
21-Nov-19, SLAB ON GRADE POUR #1 / PARTITION FOUNDATIONS
U/G Mechanical / Electrical
Excavate / Trench for Partitions Walls
Clean Aggregate Base (4 Inches) (Entire Area)
Vapor Barrier (Entire Area)
F / R / P for Partition Walls
F / R / P for SOG (Control Joints)
Strip SOG
27-Nov-19, SLAB ON GRADE POUR #2 / PARTITION FOUNDATIONS
F / R / P for Partition Walls
Flush Floor Box
F / R / P for SOG (Control Joints)
Strip SOG
30-Jan-20, TENT ERECTION / BUILDOUT
Inventory Structure / Tools
Splice Beams Into Arches
Stand Arches
Install Purlins
Repeat Arch / Purlin
Install Membrane Center Panel
Install Remaining Membrane
Electrical (By Others)
Install Insulation
Tape Insulation
Install Vent Frames
Install Liners
Tension Structure
Vents / Windows
Install End Walls
Trim and Seal Sidewalls
Install End Walls (By Others)
Fire Sprinkler (Interior - Riser / Piping / Testing)
Insulation and Tape Endwalls
Install Endwall Liner
Tension Endwalls
Install Doors and Windows
Fire Sprinkler (Exterior Connections)
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
312 473.SPRNG2 Lighting 5 18-Jan-20 24-Jan-20 0 313 474.SPRNG2 Mechanical 5 25-Jan-20 30-Jan-20 0 314 475.SPRNG2 Fire Alarm 5 25-Jan-20 30-Jan-20 0 315 BUILDOUTBUILDOUT 21 19-Dec-19 14-Jan-20 13 316 B101 - CASE MANAGERB101 - CASE MANAGER 21 19-Dec-19 14-Jan-20 13 317 480.B101 Layout Walls 1 19-Dec-19 19-Dec-19 13 318 481.B101 Frame Walls 2 20-Dec-19 21-Dec-19 13 319 482.B101 Door Frames 1 23-Dec-19 23-Dec-19 13 320 483.B101 Windows 1 24-Dec-19 24-Dec-19 13 321 484.B101 Overhead MEPF 3 26-Dec-19 28-Dec-19 13 322 485.B101 Devices in Ceilings 2 30-Dec-19 31-Dec-19 14 323 486.B101 In-Wall MEP 3 30-Dec-19 02-Jan-20 13 324 487.B101 Lights 1 02-Jan-20 02-Jan-20 22 325 488.B101 Drywall Ceilings 2 02-Jan-20 03-Jan-20 14 326 489.B101 Drywall 2 03-Jan-20 04-Jan-20 13 327 490.B101 Tape & Finish Ceilings 2 04-Jan-20 06-Jan-20 14 328 491.B101 Tape & Finish 2 06-Jan-20 07-Jan-20 13 329 492.B101 Paint 2 08-Jan-20 09-Jan-20 13 330 493.B101 Doors & Hardware 1 10-Jan-20 10-Jan-20 13 331 494.B101 Flooring 2 11-Jan-20 13-Jan-20 13 332 495.B101 Punchlist 1 14-Jan-20 14-Jan-20 13 333 B102 - LOUNGEB102 - LOUNGE 18 19-Dec-19 10-Jan-20 16 334 500.B102 Layout Walls 1 19-Dec-19 19-Dec-19 16 335 501.B102 Frame Walls 2 20-Dec-19 21-Dec-19 16 336 502.B102 Door Frames 1 23-Dec-19 23-Dec-19 16 337 503.B102 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 338 504.B102 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 339 505.B102 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 340 506.B102 Lights 1 30-Dec-19 30-Dec-19 24 341 507.B102 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 342 508.B102 Drywall 2 30-Dec-19 31-Dec-19 16 343 509.B102 Tape & Finish 2 02-Jan-20 03-Jan-20 16 344 510.B102 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 345 511.B102 Paint 2 04-Jan-20 06-Jan-20 16 346 512.B102 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 347 513.B102 Flooring 2 08-Jan-20 09-Jan-20 16 348 514.B102 Punchlist 1 10-Jan-20 10-Jan-20 16 349 B103 - CASE MANAGERB103 - CASE MANAGER 19 19-Dec-19 11-Jan-20 15 350 520.B103 Layout Walls 1 19-Dec-19 19-Dec-19 15
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Lighting
Mechanical
Fire Alarm
14-Jan-20, BUILDOUT
14-Jan-20, B101 - CASE MANAGER
Layout Walls
Frame Walls
Door Frames
Windows
Overhead MEPF
Devices in Ceilings
In-Wall MEP
Lights
Drywall Ceilings
Drywall
Tape & Finish Ceilings
Tape & Finish
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, B102 - LOUNGE
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
11-Jan-20, B103 - CASE MANAGER
Layout Walls
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
351 521.B103 Frame Walls 2 20-Dec-19 21-Dec-19 15 352 522.B103 Door Frames 1 23-Dec-19 23-Dec-19 15 353 523.B103 Windows 1 24-Dec-19 24-Dec-19 15 354 524.B103 Overhead MEPF 2 26-Dec-19 27-Dec-19 15 355 525.B103 In-Wall MEP 2 28-Dec-19 30-Dec-19 15 356 526.B103 Devices in Ceilings 2 28-Dec-19 30-Dec-19 15 357 527.B103 Lights 1 31-Dec-19 31-Dec-19 23 358 528.B103 Drywall Ceilings 2 31-Dec-19 02-Jan-20 15 359 529.B103 Drywall 2 31-Dec-19 02-Jan-20 15 360 530.B103 Tape & Finish 2 03-Jan-20 04-Jan-20 15 361 531.B103 Tape & Finish Ceilings 2 03-Jan-20 04-Jan-20 15 362 532.B103 Paint 2 06-Jan-20 07-Jan-20 15 363 533.B103 Doors & Hardware 1 08-Jan-20 08-Jan-20 15 364 534.B103 Flooring 2 09-Jan-20 10-Jan-20 15 365 535.B103 Punchlist 1 11-Jan-20 11-Jan-20 15 366 B104 - MEDSB104 - MEDS 18 19-Dec-19 10-Jan-20 16 367 540.B104 Layout Walls 1 19-Dec-19 19-Dec-19 16 368 541.B104 Frame Walls 2 20-Dec-19 21-Dec-19 16 369 542.B104 Door Frames 1 23-Dec-19 23-Dec-19 16 370 543.B104 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 371 544.B104 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 372 545.B104 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 373 546.B104 Lights 1 30-Dec-19 30-Dec-19 24 374 547.B104 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 375 548.B104 Drywall 2 30-Dec-19 31-Dec-19 16 376 549.B104 Tape & Finish 2 02-Jan-20 03-Jan-20 16 377 550.B104 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 378 551.B104 Paint 2 04-Jan-20 06-Jan-20 16 379 552.B104 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 380 553.B104 Flooring 2 08-Jan-20 09-Jan-20 16 381 554.B104 Punchlist 1 10-Jan-20 10-Jan-20 16 382 B105 - JANITORB105 - JANITOR 18 19-Dec-19 10-Jan-20 16 383 560.B105 Layout Walls 1 19-Dec-19 19-Dec-19 16 384 561.B105 Frame Walls 2 20-Dec-19 21-Dec-19 16 385 562.B105 Door Frames 1 23-Dec-19 23-Dec-19 16 386 563.B105 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 387 564.B105 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 388 565.B105 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 389 566.B105 Lights 1 30-Dec-19 30-Dec-19 24
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Frame Walls
Door Frames
Windows
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, B104 - MEDS
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, B105 - JANITOR
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
390 567.B105 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 391 568.B105 Drywall 2 30-Dec-19 31-Dec-19 16 392 569.B105 Tape & Finish 2 02-Jan-20 03-Jan-20 16 393 570.B105 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 394 571.B105 Paint 2 04-Jan-20 06-Jan-20 16 395 572.B105 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 396 573.B105 Flooring 2 08-Jan-20 09-Jan-20 16 397 574.B105 Punchlist 1 10-Jan-20 10-Jan-20 16 398 B106 - STORAGEB106 - STORAGE 18 19-Dec-19 10-Jan-20 16 399 580.B106 Layout Walls 1 19-Dec-19 19-Dec-19 16 400 581.B106 Frame Walls 2 20-Dec-19 21-Dec-19 16 401 582.B106 Door Frames 1 23-Dec-19 23-Dec-19 16 402 583.B106 Overhead MEPF 2 24-Dec-19 26-Dec-19 16 403 584.B106 In-Wall MEP 2 27-Dec-19 28-Dec-19 16 404 585.B106 Devices in Ceilings 2 27-Dec-19 28-Dec-19 16 405 586.B106 Lights 1 30-Dec-19 30-Dec-19 24 406 587.B106 Drywall Ceilings 2 30-Dec-19 31-Dec-19 16 407 588.B106 Drywall 2 30-Dec-19 31-Dec-19 16 408 589.B106 Tape & Finish 2 02-Jan-20 03-Jan-20 16 409 590.B106 Tape & Finish Ceilings 2 02-Jan-20 03-Jan-20 16 410 591.B106 Paint 2 04-Jan-20 06-Jan-20 16 411 592.B106 Doors & Hardware 1 07-Jan-20 07-Jan-20 16 412 593.B106 Flooring 2 08-Jan-20 09-Jan-20 16 413 594.B106 Punchlist 1 10-Jan-20 10-Jan-20 16 414 STAIRS / RAMPSSTAIRS / RAMPS 15 23-Dec-19 10-Jan-20 16 415 600.STR.RMPS.1 Stairs 5 23-Dec-19* 28-Dec-19 16 416 601.STR.RMPS.1 Ramps 5 30-Dec-19 04-Jan-20 16 417 602.STR.RMPS.1 Handrails / Core 5 06-Jan-20 10-Jan-20 16 418 SITEWORKSITEWORK 41 03-Dec-19 22-Jan-20 7 419 610.SITEWRK Site Paving (Verify) 15 03-Dec-19 19-Dec-19 3 420 611.SITEWRK Path Lighting (Qty 18) 15 20-Dec-19 08-Jan-20 18 421 612.SITEWRK Perimeter Fencing 15 04-Jan-20 22-Jan-20 7 422 COVERED DININING AREA COVERED DININING AREA (PRED IS SITE PAVING) 22 20-Dec-19 16-Jan-20 11 423 620.CDINN F / R / P Foundations for Covered Dining 10 20-Dec-19 02-Jan-20 11 424 621.CDINN Wood Structure Erection 10 03-Jan-20 14-Jan-20 11 425 622.CDINN Dinning Finishes 2 15-Jan-20 16-Jan-20 11 426 TRASH ENCLOSURETRASH ENCLOSURE 15 20-Dec-19 08-Jan-20 18 427 630.TRSHENC Trash Enclosure 15 20-Dec-19 08-Jan-20 18 428 LANDSCAPING (North)LANDSCAPING (North) 30 20-Dec-19 27-Jan-20 3
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, B106 - STORAGE
Layout Walls
Frame Walls
Door Frames
Overhead MEPF
In-Wall MEP
Devices in Ceilings
Lights
Drywall Ceilings
Drywall
Tape & Finish
Tape & Finish Ceilings
Paint
Doors & Hardware
Flooring
Punchlist
10-Jan-20, STAIRS / RAMPS
Stairs
Ramps
Handrails / Core
22-Jan-20, SITEWORK
Site Paving (Verify)
Path Lighting (Qty 18)
Perimeter Fencing
16-Jan-20, COVERED DININING AREA (PRED IS SITE PAVING)
F / R / P Foundations for Covered Dining
Wood Structure Erection
Dinning Finishes
08-Jan-20, TRASH ENCLOSURE
Trash Enclosure
27-Jan-20, LANDSCAPING (North)
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
429 610.LND.N Rough Grade / Sub Base 3 20-Dec-19 23-Dec-19 3 430 611.LND.N U/G Electrical for Lighting Plan 2 24-Dec-19 26-Dec-19 3 431 612.LND.N Waterline for Drinking Fountain With Pet Basin 2 24-Dec-19 26-Dec-19 3 432 613.LND.N Footing For Canopy 2 24-Dec-19 26-Dec-19 3 433 614.LND.N Irrigation (Before Planting) 2 24-Dec-19 26-Dec-19 13 434 615.LND.N U/G Outdoor Egress Emergency Photometric's 3 24-Dec-19 27-Dec-19 11 435 616.LND.N Curbs 2 27-Dec-19 28-Dec-19 3 436 617.LND.N Fence Posts 1 28-Dec-19 28-Dec-19 11 437 618.LND.N Fine Grading Within Curbs 1 30-Dec-19 30-Dec-19 3 438 619.LND.N Fence 1 30-Dec-19 30-Dec-19 11 439 620.LND.N Pea Gravel 1 31-Dec-19 31-Dec-19 3 440 621.LND.N Trees (before Granite) After Fine Grade 1 31-Dec-19 31-Dec-19 10 441 622.LND.N Synthetic Turf 7 02-Jan-20 09-Jan-20 3 442 623.LND.N Decomposed Granite 7 10-Jan-20 17-Jan-20 3 443 624.LND.N Benches / Amenities 3 18-Jan-20 22-Jan-20 3 444 625.LND.N Shade 1 23-Jan-20 23-Jan-20 3 445 626.LND.N Shrubs 3 24-Jan-20 27-Jan-20 3 446 LANDSCAPING (South)LANDSCAPING (South) 12 24-Dec-19 08-Jan-20 18 447 630.LND.S Rough Grade / Fine Grade 2 24-Dec-19 26-Dec-19 18 448 631.LND.S River Rock 3 27-Dec-19 30-Dec-19 18 449 632.LND.S Trees 2 31-Dec-19 02-Jan-20 18 450 633.LND.S Shrubs 2 03-Jan-20 04-Jan-20 18 451 634.LND.S Grass 3 06-Jan-20 08-Jan-20 18 452 HYGENE TRAILER #1 (EASTHYGENE TRAILER #1 (EAST) 81 08-Oct-19 15-Jan-20 12 453 PRE-DELIVERYPRE-DELIVERY 6 08-Oct-19 14-Oct-19 60 454 640.HYG.1 U/G Plumbing 1 08-Oct-19 08-Oct-19 60 455 641.HYG.1 Trenching 1 09-Oct-19 09-Oct-19 60 456 642.HYG.1 Bedding 1 10-Oct-19 10-Oct-19 60 457 643.HYG.1 Pipe Install 1 11-Oct-19 11-Oct-19 60 458 644.HYG.1 Pressure Test 1 12-Oct-19 12-Oct-19 60 459 645.HYG.1 Backfill 1 14-Oct-19 14-Oct-19 60 460 POST-DELIVERYPOST-DELIVERY 11 20-Dec-19 03-Jan-20 22 461 650.HYG.1 Trailers on Site 1 20-Dec-19 20-Dec-19 7 462 651.HYG.1 Potable Water to Trailer 5 21-Dec-19 27-Dec-19 7 463 652.HYG.1 Sanitary Plumbing Under Trailer 5 21-Dec-19 27-Dec-19 12 464 653.HYG.1 Drywell Pit 5 28-Dec-19 03-Jan-20 7 465 654.HYG.1 Electrical Hook Up 5 28-Dec-19 03-Jan-20 12 466 655.HYG.1 Hose Bib 5 28-Dec-19 03-Jan-20 22 467 STAIRS / RAMPSSTAIRS / RAMPS 10 04-Jan-20 15-Jan-20 12
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Rough Grade / Sub Base
U/G Electrical for Lighting Plan
Waterline for Drinking Fountain With Pet Basin
Footing For Canopy
Irrigation (Before Planting)
U/G Outdoor Egress Emergency Photometric's
Curbs
Fence Posts
Fine Grading Within Curbs
Fence
Pea Gravel
Trees (before Granite) After Fine Grade
Synthetic Turf
Decomposed Granite
Benches / Amenities
Shade
Shrubs
08-Jan-20, LANDSCAPING (South)
Rough Grade / Fine Grade
River Rock
Trees
Shrubs
Grass
15-Jan-20, HYGENE TRAILER #1 (EAST)
14-Oct-19, PRE-DELIVERY
U/G Plumbing
Trenching
Bedding
Pipe Install
Pressure Test
Backfill
03-Jan-20, POST-DELIVERY
Trailers on Site
Potable Water to Trailer
Sanitary Plumbing Under Trailer
Drywell Pit
Electrical Hook Up
Hose Bib
15-Jan-20, STAIRS / RAMPS
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19
468 660.HYSTR.RMPS1 Install Decks 3 04-Jan-20 07-Jan-20 12 469 661.HYSTR.RMPS.1 Stairs 2 08-Jan-20 09-Jan-20 12 470 662.HYSTR.RMPS.1 Ramps 2 10-Jan-20 11-Jan-20 12 471 663.HYSTR.RMPS.1 Handrails / Core 3 13-Jan-20 15-Jan-20 12 472 HYGENE TRAILER #2 (WESHYGENE TRAILER #2 (WEST) 75 15-Oct-19 15-Jan-20 12 473 PRE-DELIVERYPRE-DELIVERY 6 15-Oct-19 21-Oct-19 60 474 670.HYG.2 U/G Plumbing 1 15-Oct-19 15-Oct-19 60 475 671.HYG.2 Trenching 1 16-Oct-19 16-Oct-19 60 476 672.HYG.2 Bedding 1 17-Oct-19 17-Oct-19 60 477 673.HYG.2 Pipe Install 1 18-Oct-19 18-Oct-19 60 478 674.HYG.2 Pressure Test 1 19-Oct-19 19-Oct-19 60 479 675.HYG.2 Backfill 1 21-Oct-19 21-Oct-19 60 480 POST-DELIVERYPOST-DELIVERY 11 20-Dec-19 03-Jan-20 22 481 680.HYG.2 Trailers on Site 1 20-Dec-19 20-Dec-19 12 482 681.HYG.2 Sanitary Plumbing Under Trailer 5 21-Dec-19 27-Dec-19 12 483 682.HYG.2 Potable Water to Trailer 5 21-Dec-19 27-Dec-19 22 484 683.HYG.2 Electrical Hook Up 5 28-Dec-19 03-Jan-20 12 485 684.HYG.2 Hose Bib 5 28-Dec-19 03-Jan-20 22 486 685.HYG.2 Drywell Pit 5 28-Dec-19 03-Jan-20 22 487 STAIRS / RAMPSSTAIRS / RAMPS 10 04-Jan-20 15-Jan-20 12 488 690.HYSTR.RMPS.2 Install Decks 3 04-Jan-20 07-Jan-20 12 489 691.HYSTR.RMPS.2 Stairs 2 08-Jan-20 09-Jan-20 12 490 692.HYSTR.RMPS.2 Ramps 3 10-Jan-20 13-Jan-20 12 491 693.HYSTR.RMPS.2 Handrails / Core 2 14-Jan-20 15-Jan-20 12 492 CLOSEOUTCLOSEOUT 4 31-Jan-20 04-Feb-20 0 493 700.CX Project Punchlist 4 31-Jan-20 04-Feb-20 0 494 701.CX Commission 4 31-Jan-20 04-Feb-20 0 495 702.CX Project Completion 0 04-Feb-20* 0
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2019 2020
Install Decks
Stairs
Ramps
Handrails / Core
15-Jan-20, HYGENE TRAILER #2 (WEST)
21-Oct-19, PRE-DELIVERY
U/G Plumbing
Trenching
Bedding
Pipe Install
Pressure Test
Backfill
03-Jan-20, POST-DELIVERY
Trailers on Site
Sanitary Plumbing Under Trailer
Potable Water to Trailer
Electrical Hook Up
Hose Bib
Drywell Pit
15-Jan-20, STAIRS / RAMPS
Install Decks
Stairs
Ramps
Handrails / Core
04-Feb-20, CLOSEOUT
Project Punchlist
Commission
Project Completion
A BRIDGE HOME SHELTER
VA WEST LA
Remaining Work Critical Work Milestone Summary
BASELINE CPM Data Date: 19-Aug-19