Amendment 0003 Attachment 3 Racks and Flooring Chart.xlsx

XLSX spreadsheet 13 KB Posted

Attached to
Z2DA--Project 605-20-420 Electronic Health Record Modernization (EHRM) Infrastructure Upgrades Federal contract opportunity
Solicitation number
36C26220B0004
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 22

About this file

This document contains an amendment to a federal contract opportunity for infrastructure upgrades at a Veterans Affairs medical center. The amendment provides a chart detailing flooring and racking requirements across multiple buildings and rooms. The contractor will replace racks and install new two-post racks in various shared technical and server rooms according to drawings. Flooring will generally remain the same except in specific server rooms. The federal contract opportunity involves construction services for an electronic health record modernization project at the VA Loma Linda Healthcare System in California. The work includes general construction, alterations, mechanical, electrical and utility upgrades, and demolition. The procurement is set aside for Service-Disabled Veteran-Owned Small Businesses. The North American Industry Classification code is 236220 and the project value is estimated between $10 million to $20 million. The solicitation will be issued on September 15th via beta.sam.gov and include a mandatory site visit.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--Project 605-20-420 Electronic Health Record Modernization (EHRM) Infrastructure Upgrades, newest first.
File Type Posted
Amendment 0004 36C26220B0004.pdf PDF
Amendment 0004 Attachment 1 Additional RFI Questions and Answers.pdf PDF
Amendment 0003 36C26220B0004.pdf PDF
Amendment 0003 Attachment 2 Uncompressed Project Drawings.pdf PDF
Amendment 0003 Attachment 1 RFI Questions and Answers.pdf PDF
Amendment 0002 Attachment 1 Site Visit Sign In Sheet.pdf PDF
Amendment 0002 Attachment 5 FAR 52.225-12.pdf PDF
Amendment 0002 Attachment 4 Specification 01 10 00 - Summary.pdf PDF
Amendment 0002 36C26220B0004.pdf PDF
Amendment 0002 Attachment 3 Specification 00 01 10 - Table of Contents.pdf PDF
Amendment 0002 Attachment 2 Asbestos and Lead Report.pdf PDF
Attachment 1 Electrical Drawings.pdf PDF
Attachment 2 Plumbing Drawings.pdf PDF
Amendment 0001 36C26220B0004.pdf PDF
Attachment D Drawings File 3 of 5.pdf PDF
Attachment G Specifications.pdf PDF
Attachment H Cable Specifications.pdf PDF
Attachment B Drawings File 1 of 5.pdf PDF
Attachment I Network Diagram.pdf PDF
36C26220B0004.pdf PDF
Attachment A Basis of Design Narrative.pdf PDF
Attachment J Wage Rates.pdf PDF
Attachment F Drawings File 5 of 5.pdf PDF
Attachment E Drawings File 4 of 5.pdf PDF
Attachment C Drawings File 2 of 5.pdf PDF
36C26220B0004_1.docx DOCX document
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BuildingFloorRoomFunctionFlooringNew floor type?Current rack typeNew rack type
111C04E/1C15BServer RoomRaised Flooring over concreteFlooring to remainMixAll racks outside of cage are outside of scope. All racks inside cage are to be replaced. Drawings exist detailing new racks in cage on page AE-1.06 with the mark that all rack placement will require coordination with COR.
111SB1TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111SB2TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111SB3TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111SB4TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111SB5TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111SB6TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111SB7TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111SB8TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
111E75TRConcreteFlooring to remain2-postVendor to install 2-Post rack in addition to existing 2-post rack
111G110TRConcreteFlooring to remain2-postRacks to remain
111H114TRConcreteFlooring to remain2-postRacks to remain
122SB1TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
122SB2TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
122SB3TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
122SB4TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
122SB5TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
122SB6TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
122SB7TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
122SB8TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133E18Server RoomRaised Flooring over concreteFlooring to remainMixedVA will remove 4 post racks on left side. Contractor will install 2-post racks on left side. All racks on right side are out of scope.
133SB1TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133SB2TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133SB3TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133SB4TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133SB5TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133SB6TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133SB7TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
133SB8TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB1TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB2TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB3TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB4TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB5TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB6TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB7TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
144SB8TR/Shared SpaceConcreteFlooring to remainWall-mountedContractor will install 2-post racks per drawings
2011A107TRTile on concreteFlooring to remain2-PostRacks to Remain
291BUILDING OUT OF SCOPENANANANA
301116Tile on concrete2-PostRacks to remain
3122B104Tile on concrete2-PostVendor to install 2-Post rack in addition to existing 2-post rack
3211A102Tile on concrete2-PostRacks to remain
3222C103ATile on concrete2-PostRacks to remain
511Building in process of demolitionNANANANA

File details come from the government source that posted it. Updated .