About this file

36C26219Q0018 0002 S02 SOLICITATION atch, RFI 003 response.pdf

View the file

Other files

File Type Posted
36C26219C0020-000.docx DOCX document
36C26219Q0018-0002006.docx DOCX document
36C26219Q0018-0001004.docx DOCX document
36C26219Q0018-0002005.pdf PDF
36C26219Q0018-0002004.pdf PDF
36C26219Q0018-0002002.pdf PDF
36C26219Q0018-0002001.pdf PDF
36C26219Q0018-0002000.docx DOCX document
36C26219Q0018-0001001.pdf PDF
36C26219Q0018-0001000.docx DOCX document
36C26219Q0018-0001002.pdf PDF
36C26219Q0018-0001003.pdf PDF
36C26219Q0018-001.pdf PDF
36C26219Q0018-000.docx DOCX document
36C26219Q0018-004.pdf PDF
36C26219Q0018-002.docx DOCX document
36C26219Q0018-005.pdf PDF
36C26219Q0018-003.docx DOCX document
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI FORM

Contractor Name: IO Environmental & Infrastructure, Inc.

Address:

Phone/Fax:

Send to: cecil.nichols@va.gov

RFI

(REQUEST FOR INFORMATION)

PROJECT NO.:

RFI NO.:

PROJECT NAME:

SERVICE to PERFORM UST D.O. Inspections &

Monitoring, VALB

DATE REQUESTED:

10/19/2018

SOLICITATION NO.:

36C26219Q0018

REFERENCE:

DRAWING:

SPECIFICATION

SECTION:

DESCRIPTION OF PROBLEM OR INFORMATION BEING REQUESTED

Please be specific as possible:

Scope item 8.2.1.10 mentions a pressure test of the vent lines listed with the 30-day designated operator inspection scope. I am not aware of this requirement. Would you please provide more details regarding this requirement, its origin, and frequency it shall be performed?

PROJECT MANAGER’S RESPONSE

Pressure test of the vent lines is required every three (3) years during the SB-989 testing.

TRACKING NO.: AMENDMENT NO.:

VA PROJECT ENGINEER/MANAGER:

Keith Didrickson, COR

DATE:

October 25, 2018 mailto:cecil.nichols@va.gov