DIVISION CONSTRUCTION COSTS- Roll Up Door.docx
DOCX document 21 KB Posted
- Attached to
- J049--654-24-4-6090-0633 | 36C261-24-AP-4966 | replace/upgrade | Pipeshop Roll-up Garage Door
- Solicitation number
- 36C26124R0080
About this file
This document appears to be a divisional cost breakdown template for a federal contract opportunity to replace a roll-up garage door. The solicitation number is 36C26124R0080, and the project is to replace a roll-up door. The template requires the contractor to provide a complete divisional cost breakdown for the entire project, with line items for various construction divisions such as general requirements, concrete, metals, doors and windows, and electrical. The total cost, as well as line items for bonds, insurance, overhead, and profit, must be provided. This document is to be used for price analysis purposes only and is not a response to the solicitation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REQUEST FOR INFORMATION FORM- 1.docx | DOCX document | |
| 36C26124R0080.docx | DOCX document | |
| Wage Determination 20230040 8.18.23.pdf | ||
| 010000 General Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C26124R0080 SOLICITATION: 36C26124R0080 PROJECT: Replace Roll Up door
PROVIDE COMPLETE DIVISIONAL COST BREAK-OUT FOR COMPLETE PROJECT.
*If necessary, add additional lines for each Division applicable to this project.
**This document is to be used only for price analysis
| REF |
| DESCRIPTION |
| TOTAL |
00000
| DIVISION 0-SPECIAL SECTIONS |
| $ |
| 01000 |
| DIVISION 1-GENERAL REQUIREMENTS |
| $ |
| 02000 |
| DIVISION 2-EXISTING CONDITIONS |
| $ |
03000
| DIVISION 3-CONCRETE |
| $ |
04000
| DIVISION 4-MASONRY |
| $ |
05000
| DIVISION 5-METALS |
| $ |
06000
| DIVISION 6-WOOD AND PLASTIC |
| $ |
07000
| DIVISION 7-THERMAL AND MOISTURE PROTECTION |
| $ |
08000
| DIVISION 8-DOORS AND WINDOWS |
| $ |
09000
| DIVISION 9-FINISHES |
| $ |
10000
| DIVISION 10-SPECIALTIES |
| $ |
11000
| DIVISION 11-EQUIPMENT |
| $ |
12000
| DIVISION 12-FURNISHINGS |
| $ |
13000
| DIVISION 13-SPECIAL CONSTRUCTION |
| $ |
14000
| DIVISION 14-CONVEYING EQUIPMENT |
| $ |
21000
| DIVISION 21-FIRE SUPPRESSION |
| $ |
22000
| DIVISION 22-PLUMBING |
| $ |
23000
| DIVISION 23-HEAT, VENTILATING, AND AIR CONDITIONING |
| $ |
26000
| DIVISION 26-ELECTRICAL |
| $ |
27000
| DIVISION 27-COMMUNICATIONS |
| $ |
28000
| DIVISION 28-ELECTRONIC SAFETY AND SECURITY |
| $ |
31000
| DIVISION 31-EARTHWORK |
| $ |
32000
| DIVISION 32-EXTERIOR IMPROVEMENTS |
| $ |
33000
| DIVISION 33-UTILITIES |
| $ |
34000
| DIVISION 34-TRANSPORTATION |
| $ |
SUB TOTAL:
OTHER
| BONDS AND INSURANCE |
| Not Required under $30,000.00 |
| $ |
OVERHEAD
PROFIT
TOTAL
| _______________________________________________ | ___________ |
| (Signature and Typed Name of Authorized Representative) | Date |
(Title of Authorized Representative)