This document provides additional questions and answers related to a solicitation for fire sprinkler testing and maintenance services for facilities within the VA Northern California Health Care System. The solicitation requires maintenance, inspection, and testing of wet pipe sprinkler systems according to NFPA 25 standards at medical centers in Martinez, Mather, Mare Island, and Fairfield. Services must be provided at 20 sprinkler risers at Mather and 12 risers at Mare Island. Joint Commission inspection requirements apply to specific buildings. Pricing is required for the initial base period of performance from August 1, 2020 to July 31, 2021. The solicitation is set aside for Service-Disabled Veteran Owned Small Businesses. No incumbent was identified and the VA indicated it intends to award a full-service contract to cover all requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fire Sprinkler Testing and Maintenance for VA Northern California Health Care System (VANCHCS) 36C26120Q0556 Additional Questions and Answers (new questions see 9 – 13 and correction to answer 3 & 7)

Question 1: Are any of the sprinklers dry systems? If so, how many?

Answer 1: No. All fire sprinkler systems are known to be wet-sprinkler systems.

Question 2: The oldest building is 78 years old, has the 10, 20, and 50 year sprinkler head testing been kept up to date? If not, how many heads need to be caught up?

Answer 2: Last documented 5-year test for SVD Buildings: 647, 649, 650, 652, 700, 701, 702, 728. November 11, 2015.

Last documented 5-year test for EBD Buildings: Bldg. 19 March 6, 2018; Bldg. 20 January 3, 2019.

The facility focus has been Joint Commission inspected buildings. Little attention has been applied to other buildings within our area of responsibility. The intent is to ensure all buildings are inspected/certified per NFPA 25.

Question 3: Who are the manufacturers of the installed fire alarm panels (Siemens, Notifier, Simplex, EST) and who is the incumbent on the fire alarm inspection contract?

Answer 3: Fairfield Outpatient Clinic (Travis Air Force Base): 103 Bodin Circle, Travis AFB CA, 94535

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Simplex 4100
FF OPC
1st Floor

Mare Island Outpatient Clinic: 201 Walnut Avenue, Vallejo CA, 94592

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Cerberus Pyrotronics MXL-IQ
201
1st and 2nd Floors

Martinez Community Based Outpatient Clinic (CBOC): 150 Muir Road, Martinez CA, 94553

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Notifier NFS2-640
1
1st Floor
Notifier NFS2-640
12
1st Floor
Notifier NFS2-640
13
Tied into Building 12
Notifier NFS2-640
14
Tied into Building 12
Notifier NFS2-640
19
1st and 2nd Floors
Notifier NFS2-640
20
1st Floor
Notifier NFS2-640
21
1st, 2nd, 3rd, and 4th Floors
Notifier NFS2-640
22
1st and 2nd Floors (slave panel)
Notifier NFS2-640
23
1st and 2nd Floors (slave panel)
Notifier FSP-851
24
Stand-alone
Building Under Construction
25
1st and 2nd Floors (Under Construction)
Notifier NFS2-640
26
1st and 2nd Floors
Tied into AB7
AB6
1st Floor
Notifier NFS2-640
AB7
1st Floor
Notifier NFS2-640
R1
1st Floor
Tied into R1
R2
1st Floor
Notifier NFS2-640
R4
1st Floor

Oakland Outpatient Clinic: 2221 Martin Luther King Jr. Way, Oakland CA, 94612

Make/ Model
Building Number
Floor of Main & Auxiliary Panels
Honeywell Silent Knight 6700
2221
1st, 2nd, and 3rd Floors

Note: Oakland is a leased building. Oakland is not included in the SOW/PWS.

Sacramento Medical Center (Mather): 10535 Hospital way Mather, CA. 95655 Secutron Panels at Mather:

Model
Building Number
Floor or Building on the Main Panel
MR 2100
631
630
MR 2100
645
Stand-alone
MR 2100
646
Stand-alone
MR 2100
647
649, T-8
MR 2900
650
1st, 2nd, 3rd Floors and T-9
MR 2100
651
Stand-alone
MR 2200
652
Warehouse Stand-alone
MR 2200
700
1st, 2nd, 3rd, 4th, 5th Floors and ED
MR 2100
703
701, 702
MR 2200
707
803, 805, 806, 807
MR 2200
720
722, 722A, 802
MR 2900
728
727
MR 2200
730
731
MR 2100
801
798, 799, 800, 801A, 801B

EST Panels at Mather:

Model
Building Number
Floor or Building on the Main Panel
4X-CAB5DR
726
Stand-alone

McClellan Outpatient Clinic: 5342 Dudley Blvd McClellan, CA. 95652 Secutron Panels at MCC:

Model
Building Number
Floor or Building on the Main Panel
MR 2100
88
Dental
MR 2100
949
1st, 2nd, 3rd Floors

Silent Knight Panels at MCC:

Model
Building Number
Floor or Building on the Main Panel
NA
209
Stand-alone for all Floors

Notifier (By Honeywell):

Model
Building Number
Floor or Building on the Main Panel
DR-C4
29
Maintenance and LMS
DR-C4
98
Stand-alone

Question 4: What is the month of the annual inspection for sprinkler and fire alarm?

Answer 4: There is no set month for inspections as long as the inspection interval is maintained. We have service contracts pending for Fire Alarm services and whether the contractor will follow the fiscal year calendar or standard year calendar is yet to be determined.

Question 5: What future years are the 3 and 5 year inspections due? To calculate this cost, bidders need to know the number of riser per location.

Answer 5: Please use information from Question #2 to determine when inspections are due. Bidders can assume that each major building has its own fire riser location.

Question 6: Will the VA consider self-performing the weekly work (pump runs) as this may cut 50% off the price?

Answer 6: No. The intent is to have a full-service contract for our facility.

Question 7: What is the current contract number?

Answer 7: There is no current contract.

Question 8: I was looking at the inventory spreadsheet and did not see the amount of sprinkler risers listed. To perform the 5 year internal inspections we would need the amount of wet and dry systems.

Answer 8: All sprinkler systems are wet. The number of risers for SMC/MCC is 20. The number of risers for MTZ is 12.

Question 9: We’d like to request the last inspection reports from each of the buildings listed on the excel spreadsheet accompanying the bid.

Answer 9: See Attached (PDFs)

Question 10: Which of the buildings listed on the excel spreadsheet will require Joint Commission Reporting AND will require inspections to fall within their required timelines?

Answer 10: The Joint Commission Buildings are noted below:

SMC:

Building 700 Building 726

MTZ:

Building 20

The intent is to have all buildings inspected to this standard.

Question 11: Page 6, PP A states that “maintenance & repair” of the fire sprinkler systems and Page 7, PP B states inspections, “maintenance & repair” of the fire sprinkler systems, however Page 4 of the Cost Schedule does not state “repair”.

Answer 11: Yes, Contractor will make all repairs.

Question 12: Below is a list of the devices that we would need quantities.

Air Pressure Switch

Fire Pump (GPM, Electric or Diesel)

Tamper Switch

Waterflow Switch

Fire Hydrant

FDC

Dry Sprinkler System

Wet Sprinkler System

Pre-Action Sprinkler

Standpipe

Main Drain

Backflow Preventers

Control Valves

Answer 12: Below is the answer to your question: (Note: see revised spreadsheet titled - Inventory list and buildings by geographical locations and device inventory revised June 23, 2020)

SMC
MCC

Air Pressure Switch

Fire Pump (GPM, Electric or Diesel)
B-702 x2; Electric

B-651 x1; Electric None

Tamper Switch
52
Waterflow Switch
38

Fire Hydrant

FDC

Dry Sprinkler System
None
None
Wet Sprinkler System
All Buildings
All Buildings
Pre-Action Sprinkler
None
None

Standpipe

Main Drain
One per building
One per building
Backflow Preventers
One per building
One per building

Control Valves

MTZ
Mare Island
Fairfield

Air Pressure Switch

Fire Pump (GPM, Electric or Diesel)
None
None
None
Tamper Switch
33
9
4
Waterflow Switch
One per building
One per building
One per building
Fire Hydrant
11
2
FDC
11
Dry Sprinkler System
None
None
None
Wet Sprinkler System
All Buildings
All Buildings
All Buildings
Pre-Action Sprinkler
None
None
None
Standpipe
11
Main Drain
One per building
One per building
One per building
Backflow Preventers
One per building
One per building
One per building

Control Valves