36C26119R0026 0002 Circuit Schedule for Headwall units.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26119R0026-0002000.docx | DOCX document | |
| 36C26119R0026-0002011.pptx | PPTX presentation | |
| 36C26119R0026-0002010.pdf | ||
| 36C26119R0026-0002006.jpg | JPG image | |
| 36C26119R0026-0002005.jpg | JPG image | |
| 36C26119R0026-0002012.pdf | ||
| 36C26119R0026-0002001.pdf | ||
| 36C26119R0026-0002003.jpg | JPG image | |
| 36C26119R0026-0002004.jpg | JPG image | |
| 36C26119R0026-0002002.pdf | ||
| 36C26119R0026-0002008.pdf | ||
| 36C26119R0026-0002007.jpg | JPG image | |
| 36C26119R0026-0001000.docx | DOCX document | |
| 36C26119R0026-0001001.pdf | ||
| 36C26119R0026-007.pdf | ||
| 36C26119R0026-008.pdf | ||
| 36C26119R0026-002.docx | DOCX document | |
| 36C26119R0026-004.docx | DOCX document | |
| 36C26119R0026-006.pptx | PPTX presentation | |
| 36C26119R0026-010.pdf | ||
| 36C26119R0026-005.pdf | ||
| 36C26119R0026-011.pdf | ||
| 36C26119R0026-003.docx | DOCX document | |
| 36C26119R0026-009.pptx | PPTX presentation | |
| 36C26119R0026-001.docx | DOCX document | |
| 36C26119R0026-000.docx | DOCX document |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
20A Emergency
Receptacle
20A Normal
Receptacle
20A Single
Outlet for Bed
1A-24 2 L1EX - 3 L1E2 - 1 L1E2 - 34
1A-25 2 L1EX - 3 L1E2 - 13 L1E2 - 34
1A-39 2 L1EX - 27 L1E1 - 40 L1E2 - 36
1A-40 1 L1EX - 27 L1E1 - 19 L1E2 - 36
1A-42 1 L1EX - 30 L1E1 - 11 L1E2 - 36
1A-44 1 L1EX - 30 L1E1 - 11 L1E2 - 36
1A-46 1 L1EX - 5 L1E1 - 42 L1E2 - 38
1A-48 1 L1EX - 5 L1E1 - 42 L1E2 - 38
1A-50 1 L1EX - 5 L1E1 - 3 L1E2 - 38
1A-51 2 L1EX - 4 L1E1 - 3 / 8 L1E2 - 38
1A-52 1 L1EX - 4 L1E1 - 8 L1E2 - 40
1A-54 1 L1EX - 6 L1E1 - 16 L1E2 - 40
1A-56 1 L1EX - 6 L1E1 - 24 L1E2 - 40
1A-59 2 L1EX - 32 L1E1 - 11 L1E2 - 42
1A-60 1 L1EX - 32 L1E1 - 2 L1E2 - 42
1A-61 1 L1EX - 32 L1E1 - 2 L1E2 - 42
1. Circuit numbers noted are from As-built drawings and for reference only. Contractor is responsible to investigate existing conditions and verify existing load on each circuit being reused.
2. ALL duplex and single receptacles to be 20A Hospital Grade type, no exception.
3. Receptacle designated for “Emergency” shall have a red outlet and cover plate.
4. Grayed-Out circuit shown in this table to indicate:
Provide new 2#12, 1#12G – 3/4" C. Extend back to existing panel and reuse existing 20A C/B.
5. Contractor is responsible to provide a complete installation in accordance with all required codes.
Existing circuits being affected by this upgrade/ replacement with new headwall units shall also have the correct conductors throughout the run and the home-run back to panel. The contractor shall provide a neutral conductor for each home-run, per code.
Headwall Unit ONLY - Existing/New power source.
Project #662-17-008 - Replace upgrade Med Gas and Headwalls
Patient
Room
Headwall
Unit Notes
File details come from the government source that posted it.