This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by Network Contracting Office 20 to extend the deadline for receipt of offers on solicitation 36C26027Q0033, originally dated August 11, 2026. The amendment extends the offer receipt deadline to October 9, 2026, at 1:00 PM Mountain Daylight Time. The requisition/purchase request number is 648-27-1-157-0002, and the issuing office is located at 1601 E. Fourth Plain Blvd, Building 17, Suite B428, Vancouver, WA 98661.

The amendment addresses one question received from potential bidders regarding contractor responsibilities for pit preparation and installation work. The government clarified that the contractor is responsible for all aspects of the project from start to finish, including pit painting, epoxy application, cleaning, and ensuring the machine fits within the pit specifications. Offerors must acknowledge receipt of this amendment prior to the extended deadline by completing the required forms, acknowledging receipt on their offer copies, or submitting separate written communication that references the solicitation and amendment numbers.

View the file

Other files

File Type Posted
RFQ 36C26027Q0033 0003 Amend to Extend.pdf PDF
36C26027Q0033_4.pdf PDF
36C26027Q0033_3.pdf PDF
36C26027Q0033_2.pdf PDF
S02 RFQ 36C26027Q0033 0001 Answers and site visit.pdf PDF
S02 RFQ 36C26027Q0033 Cage Washer.pdf PDF
36C26027Q0033_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 2

0002 08-20-2026

648-27-1-157-0002

36C260

Network Contracting Office 20

ATTN: V4CONT

1601 E. Fourth Plain Blvd

Bldg.17, Suite B428

Vancouver WA 98661

36C260

Network Contracting Office 20

ATTN: V4CONT

1601 E. Fourth Plain Blvd

Bldg.17, Suite B428

Vancouver WA 98661

To all Offerors/Bidders

36C26027Q0033

08-11-2026

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 10-09-2026 1PM MDT

648-3670160-157-820100-2220 010040243

X ONE

a. The purpose of this amendment is to answer a question and to extend the date for receipt of offers.

b. The next page of this amendment lists the answers to thequestion received regarding this solicitation. The questions are in black, while the answers are in red.

c. This solicitation is extended and all responses are now due on 10/9/2026 by 1PM Mountain Time.

CONTINUATION PAGE

Question 1: Is the winning bidder responsible for pit painting, epoxy, cleaning, etc? Or does the vendor need to just make sure that the machine fits in the pit?

Answer: Contractor is responsible for everything from start to finish..